Rooppur nuclear power plant, Bangladesh
Name of the Project
Rooppur nuclear power plant (NPP).
Location
The project is located in Ishwardi Upazilla, 160 km from Dhaka, in Bangladesh.
Client
Bangladesh Atomic Energy Commission (BAEC).
Project Description
The Rooppur NPP will comprise two WWER-1200 reactors, with a total capacity of 2 400 MW.
Potential Job Creation
About 4 200 are engaged in construction works.
Value
Not stated.
Duration
Construction of the first unit started in November 2017 and will be commissioned in 2023.
The second unit started construction in July 2018 and is expected to be commissioned in 2024.
Latest Developments
Concrete works have been completed for the turbine hall foundation slab of Rooppur 1, Russian state nuclear corporation Rosatom has announced.
The concrete slab structure, with 3813 t of rebars and 24 285 m3 of concrete, was completed in January, following the completion of operations to stabilise the soil under the main and auxiliary buildings, and structures of the Rooppur construction site. More than 1.2-million tonnes of cement were used to strengthen 4.5-million cubic metres of soil to meet design requirements for a load-carrying capacity.
Preparations have begun at the site to erect the walls of the reactor building and auxiliary reactor compartment. The work has been undertaken in cooperation with specialist European and Bangladeshi companies under the management of Rosatom subsidiary AtomStroyExport, while the construction works for the Rooppur NPP are on schedule, Rosatom has said.
Key Contracts and Suppliers
AtomStroyExport – Rosatom’s engineering division (general construction contractor); Atomenergomash – Rosatom’s machine building division (equipment for the reactor island and auxiliary equipment for the turbine island).
Various divisions of Rosatom are in charge of manufacturing reactor vessels, steam generators, pumps, heat-exchangers and other equipment.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
BAEC, tel +880 2818 1846 or fax +880 2818 1842.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation