https://www.engineeringnews.co.za

Resgen defers some Boikarabelo activities until finalisation of debt funding

21st January 2015

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – JSE- and ASX-listed Resource Generation (Resgen) is continuing negotiations to finalise debt funding to fast-track the development of its Boikarabelo coal mine, in the Waterberg.

Over the three months to March, the company planned to focus on the development of power infrastructure and a 13 km section of pipeline, with some of the other activities to be deferred until debt funding was finalised.

Resgen noted that although its pursuit of $400-million debt funding was protracted, the continuation of negotiations indicated that all parties “seek to agree a structure that provides the funding” required to complete construction of site infrastructure and the rail link.

In a report for the three months to December 31, Resgen noted making progress on the construction of infrastructure at the mine, with EHL Energy having started erecting power poles for the 132 kV power transmission lines.

With earthworks completed, the construction of the substation and switch room, which was funded from a deferred payment facility, was on track for completion in October this year.

Meanwhile, earthworks for the rail network stabilisation facility were mostly completed, with the final drainage and retaining walls set for completion this month.

Resgen also completed the construction of the first three of seven rail link bridges under and over the rail line. The rail turnouts and associated signalling would be installed by mid-year.

Meanwhile, the permanent water supply infrastructure had been completed, including holding tanks and pumping facilities, while the earthworks for the 13 km section of the pipeline adjacent to a main road were concluded. The pipes had been delivered for installation during the March quarter.

The construction camp and services, offices, kitchen and dining facilities for 1 320 people and the accommodation units for 400 workers had been built.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/04/2024)
12th April 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.121 0.182s - 156pq - 2rq
Subscribe Now