Renewables rhythm

28th July 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Once lauded as an international benchmark, South Africa’s Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) has struggled to rediscover its rhythm after being disrupted for seven years by the then State-captured Eskom leadership.

Prior to 2015 and Eskom’s announcement that it was no longer prepared to enter into power purchase agreements with new renewable- energy projects on the dubious claim of having returned to a generation surplus, the programme had developed a positive momentum.

After two very expensive rounds, renewables tariffs were starting to reflect the steep fall in global solar and wind prices, and nascent domestic supply chains were beginning to develop, while social pledges and transformation were improving round by round.

The much-delayed Bid Window Four (BW4) projects, which fell victim to Eskom’s policy-defying intransigence, even became something of a symbol of President Cyril Ramaphosa’s 2018 ‘New Dawn’, when then Energy Minister Jeff Radebe shepherded them towards construction.

It turned out to be a false dawn, however. It took a further two years for BW5 to be launched, with renewables-sceptic Gwede Mantashe, who took over the merged Mineral Resources and Energy portfolio, taking some time to gazette the Integrated Resource Plan of 2019 on which any procurement would be based and months more to publish the Ministerial determinations needed for the initiation of actual procurement.

Despite the distraction of, and subsequent delays to, the poorly designed emergency procurement for 2 000 MW of mostly powership capacity, it then appeared that the REIPPPP’s rhythm was about to be re-established.

In October 2021, Mantashe named 25 wind and solar preferred bidders for projects with a combined capacity of 2 583 MW and record-low tariffs. As the full extent of the supply chain disruptions associated with China’s harsh Covid lockdowns came to the fore and Russia’s invasion of Ukraine amped up energy prices across the board, including renewables component prices, it soon became clear that the BW5 tariff were mostly too good to be true.

Only a handful of the 19 projects that eventually reached legal close have achieved financial close and it appears that there will be some major casualties as the final deadline for entering into construction looms.

The disappointment did not end there. After expanding the BW6 to procure 4 200 MW in light of intensifying loadshedding, only the solar projects with a combined capacity of 1 000 MW were eventually named as preferred bidders in 2022. This, after the 23 wind projects vying for the 3 200 MW allocation were crowded out by a combination of poor and overly conservative grid management.

The net result is that only the BW4 projects that were initially procured in 2014 have entered production despite South Africa being desperately short of the energy that these variable plants could have provided had there been both greater political will and better coordination.

While the REIPPPP is thankfully no longer the only renewables game in town, it is still vital that it rediscovers its rhythm when BW7 is launched in September.

Edited by Terence Creamer
Creamer Media Editor

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.063 0.117s - 140pq - 2rq
Subscribe Now