Creamer Media’s Engineering News Online
Advanced Search
 
 
 
We have detected that the browser you are using is no longer supported. As a result, some content may not display correctly.
We suggest that you upgrade to the latest version of any of the following browsers:
         
close notification
powered by
GOLD 1734.30 $/ozChange: -2.47
PLATINUM 1655.00 $/ozChange: 9.00
R/$ exchange 7.57Change: -0.02
R/€ exchange 10.02Change: -0.11
 
RENEWABLE ENERGY
Regulator includes more renewable technologies in Refit, outlines purchase agreement
 
20th July 2009
TEXT SIZE
Text Smaller Disabled Text Bigger
 

The National Energy Regulator of South Africa (Nersa) has released a consultation paper for phase-two of the renewable energy feed-in-tariff (Refit), on its website, and was requesting inputs and comment from stakeholders and the public.

The consultation paper included a lengthy draft of the power purchase agreement (PPA), which renewable energy project developers had been awaiting, before being able to get started with projects.

Stakeholder input was requested on the content, structure and risk allocation between the seller and buyer of the Refit PPA.

It was understood that the PPAs, with Eskom’s Renewable Energy Purchasing Agency as the single-buyer of power generated from renewable energy projects, would be a 20-year contract.

Potential additional renewable energy technologies, excluded from the initial Refit, were also outlined in the Refit phase-two consultation document.

A qualifying renewable energy generator under phase two of the Refit would be defined as a new investment in electricity generation using the following technologies: concentrated solar power (CSP) plant without storage; solid biomass; biogas; solar photovoltaic (PV) systems, large ground or roof-mounted; concentrating PV; concentrated solar power central tower.

Considering the market conditions, reference technology cost, and performance assumptions, Nersa, in its consultation document, outlined the levelised cost of electricity for CSP without storage as R3,132/kWh. For PV greater than 1MW the levelised cost of electricity is R4,488/kWh; solid biomass is R1,181/kWh; biogas is R0,962/kWh, concentrating PV without storage is R5,481/kWh; and CSP tower with storage is R2,308/kWh.

Wave, tidal and geothermal technologies were excluded, as Nersa said these technologies were not yet commercially available, although they could be included in later years, and considered during the yearly Refit review.

At first glance, renewable energy industry stakeholders and interested parties said that the release of the consultation paper was a long-awaited, and a good development.

"The inclusion of the new technologies is a great step forward for renewable energy in South Africa, and plugs some of the gaps from the first Refit," said Inspired Evolution executive director Chrisopher Clarke.

He added that clarity of the PPAs was progressing, and would need to be further reviewed before comment was made.

World Wide Fund for Nature Climate Change programme manager Richard Worthington said that another Refit issue that required clarity was the need for a set of procedures, and timelines to be followed by the purchasing agent, that would ensure that Eskom does not have discretion as to whether it awards a PPA or not, because it was felt that it should be a purely administrative process and not at the discretion of Eskom in any way.

Eskom as the single buyer was a major concern for some renewable energy project developers, however, it was viewed as better than developing an entirely new institution to act as the buyer, as Eskom already has the resources.

Nersa published the initial Refit guidelines on March 26 this year, and following public comments requesting the inclusion of additional technologies, said it would investigate and consider the possibility of including other technologies under the tariff, after six months.

Under the existing Refit, a wind tariff of R1,25/kWh was sanctioned, while small-scale hydro would receive 94c/kWh, landfill gas 90c/kWh and concentrated solar would receive R2,10/kWh.

Nersa said that all regulatory concepts and principles adopted in the first phase regulatory guidelines would remain unchanged and applicable to Refit phase two.

Written comments should be submitted to Nersa by August 20, which was also the closing date for interested parties to register to attend the public hearings into the Refit phase two.

The public hearings for Refit phase two were scheduled to take place in September, and the electricity sub-committee would make recommendations to the regulator in October.

Nersa approval of the Refit phase two was expected on October 29, 2009.

Edited by: Mariaan Webb
FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
 
 
 
Hide Comments  
 
This article contains no Comments

 
 
All comments must be approved by our editors, click here to read the editorial guidelines for comments. Please allow some time for our editors to approve your comment after posting.
 * Required Fields

image
image
 *
 

 

image
image
 *
 

image
image
 

Verification Image

image
image
 * Please enter the text you see in the above image.