MITTAL STEEL CAPEX PROJECT
 
Refractory reline contract completed
 
29th June 2007
TEXT SIZE
Text Smaller Disabled Text Bigger
 

Turnkey refractory project specialist, the Dickinson Group, was awarded a contract for the installation of refractories of the blast furnace in Mittal Steel’s capital expenditure programme. The contract included the supply of in excess of 1 500 t of refractory materials and anchors.

A joint venture was set up with Pirson Refractories of the Nether-lands, part of the Pirson Group, in a bid to minimise costs and enhance erection time.

The contract involved the lining of a new bustle main; a new blast furnace hearth; tuy�re; the prebricking of copper and cast-iron staves; the installation of monolithic refractories in the furnace dome; the off-gas system and ancillary equipment. The preshut activities encompassed in the contract were executed during the months of November and December and the shutdown activities are currently being completed.


 

To subscribe to Engineering News's print magazine email subscriptions@creamermedia.co.za or buy now.

FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
SURGING FORWARD

The Dickinson Group supplied  in excess of 1500 t of refractory materials and anchors for Mittal Steel's capex project
 

SURGING FORWARD The Dickinson Group supplied in excess of 1500 t of refractory materials and anchors for Mittal Steel's capex project