http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.67Change: -0.07
R/$ = 12.39Change: -0.01
Au 1169.14 $/ozChange: -2.75
Pt 1065.00 $/ozChange: 3.80
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Jan 18, 2008

R20bn boiler contract not initially awarded to Hitachi – Eskom

Back
Engineering|Africa|CoAL|Coal-fired Power Station|Eskom|Generators|Health|PROJECT|SECURITY|Africa|Power
Engineering|Africa|CoAL|Coal-fired Power Station|Eskom|Generators|Health|PROJECT|SECURITY|Africa|Power
engineering|africa-company|coal|coalfired-power-station|eskom|generators|health|project|security|africa|power
© Reuse this South African power utility Eskom confirmed last month that the initial letter of award for the R20-billion Medupi boiler contract had, in fact, been extended to the Alstom Steinmüller consortium and not to the Hitachi consortium, which was officially named as the winning bidder on November 13.



However, in a letter sent to Engineering News in December, entitled ‘Summary of the Medupi Tender Process’, the utility also went to some length to emphasise the integrity of the pro- cess and the eventual outcome. The letter quotes extensively from the findings of the external review by Deloitte, which gave the process a clean bill of health.

The contract, awarded to Hitachi Power Africa and Hitachi Power Europe (Germany), is for six 800-MW utility steam generators for a coal-fired power station being built at a cost of R78,6-billion, at a site near Lephalale, in Limpopo province. The consortium will also supply a similar offering for the R80-billion-plus Project Bravo, which is to be built almost simultaneously at a site near Emalahleni, in Mpumalanga.

The revelation of a revised contract award is likely to raise eyebrows, coming as it does on the back of revelations that Chancellor House – which is said to have strong ties with the ruling African National Congress (ANC) and has even been described by the Mail & Guardian as an ANC business front – is the 25% black economic-empowerment shareholder in Hitachi Power Africa.

CONFLICT OVER REFERENCES
Further, it arises in the midst of something of a conflict of opinion between Hitachi Power Africa and Steinmüller over which of the two companies has claim to the 20 000 MWe of boiler tech- nology reference sites that have been installed in South Africa over the last number of decades.

Hitachi claims that, through a series of mergers and acquisitions, it is the current owner of all the know-how and references of the for-mer L&C Steinmüller Group, which includes the Majuba, Tutuka, Duvha and Kriel boilers, even though it did not build these facilities. But Steinmüller Africa MD Hermann Brummer told Engineering News recently that, while it was true that Hitachi acquired the know-how, such ownership could not be considered a sufficient basis for a claim of ‘references’.

Eskom had refrained from commenting on the award, but in its letter, dated December 11, asserted that an independent review by Deloitte had adjudged Eskom to have “acted diligently” and to have “followed due process” in the reassessment of the letter of award to Alstom Steinmüller, and that “given the urgency of the situation, Eskom’s decision to approach Hitachi was justified”.

REAWARD EXPLAINED
Eskom explained that, while it had indeed pre- sented Alstom Steinmüller with the letter of award on August 31, 2007, certain conditions still had to be met before the contract could be officially awarded. Eskom revealed, too, that, on September 3, the Hitachi Boiler Consortium was advised that its tender had been unsuccessful.

“[There were a number] of technical and commercial issues that needed to be resolved with regard to the Alstom Steinmüller boiler tender and the Alstom Steinmüller Consortium did not accept the boiler letter of award. Amongst others, one of the issues related to a different interpretation of the scope of the works. This resulted in a significant difference in the prices originally tendered,” Eskom explained in the letter.

It said that, in an attempt to resolve the matter, Eskom suggested that an agreement be concluded that the outstanding matters be dealt with in terms of the mechanisms of the contract. But the Alstom Steinmüller Consortium rejected that proposal.

The utility then entered into a process of engagement with the con- sortium “in a final attempt to resolve the outstanding issues”, but this process failed and Eskom then informed the Alstom Steinmüller Consortium that it would consider alternatives.

“The choice faced by Eskom was to reissue the tender for the boiler package or to approach the other tenderer, that is the Hitachi Boiler Consortium, regarding the boiler tender. In the light of the delays that would result from a new tender process, the view was that it was necessary to ensure security of supply and it was, therefore, in Eskom’s best interests to approach the Hitachi Boiler Consortium. External legal opinion was also obtained in this regard and confirmed that this approach by Eskom was justifiable from a legal perspective,” the utility explained.

The upshot was a recommendation from the Eskom board tender committee and supported by the Eskom board that the Medupi boiler tender be awarded to the Hitachi Boiler Consortium. The contract was then signed at a function held at Eskom’s Megawatt Park head office, in November.

In the letter, Eskom stressed that the board was particularly concerned about the potential for “conflicts of interests” throughout the tender process and stated that “a detailed integrity check was done on the employees involved in the pro- cess as well as the members of exco, and the board, and that no concerns were reported”.

During this process, the participation of Chan- cellor House as a shareholder was reportedly highlighted in the Deloitte report. But the report concluded that “there was no information that indicated that there was any political influence in this regard”.

FLEET STRATEGY and BRAVO
The utility again acknowledged that it would be pursuing a ‘fleet strategy’ as a result of the limited response received following the issue of tenders for the procurement of the turbine and boiler packages for Medupi. In fact, although Eskom had prequalified 19 potential bidders and 14 had expressed interest in the turbine and boiler contracts, only two eventually submitted bids for both work packages, despite the extension beyond the November 10, 2006, deadline to encourage further bids.

The utility said the objective of the fleet model was to secure a supplier relationship that would allow Eskom to meet its capacity expansion objectives in the most effective and sustain- able manner.

For this reason, negotiations for the turbine and boiler packages for the second coal-fired station, currently dubbed Project Bravo, to be built in Mpumalanga, would also be conducted with the Alstom and Hitachi consortiums respectively.

“The fleet strategy is based on the award of the Medupi tender and, therefore, does not involve a tender process. In this regard, external legal opinions have confirmed that such an approach can be justified as meeting the constitutional requirements of a procurement process that is competitive, equitable, cost effective, fair and transparent,” Eskom stated.

Edited by: Martin Zhuwakinyu
Creamer Media Senior Deputy Editor
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Electricity News
Nigeria's Transcorp plans to spend $1.575-billion from 2016 to 2018 to raise its power generation capacity to 2 500 megawatts (MW) from 610 MW now, the company said on Thursday. Transcorp, which also has interest in hotels, oil and gas, said it expected the...
DEPENDABLE SUPPLIER Tswelopele Engineering has established itself as a supplier of voltage regulators, surge arresters and auto-reclosers
Black-owned engineering specialist Tswelopele Engineering is taking part in Power-Gen Africa (PGA) “to enter new markets and to reach potential solution seekers in all of Africa,” says company CEO Bongane Madondo. PGA, which Madondo describes as a product-awareness...
SUPPLY SUCCESS Cable Croc successfully supplied 1 520 units of its patented Cable Croc anchoring system to the uMhlathuze municipality, in KwaZulu-Natal
Cable theft prevention systems developer Cable Croc is aiming to improve its Level 4 black economic empowerment (BEE) rating to increase the company’s accessibility to markets that require higher BEE ratings, such as municipalities, as well as the mining and rail...
More
 
 
Latest News
State-owned entity Transnet National Ports Authority (TNPA) has started the registration process for its integrated port management system (IPMS), which is scheduled to go live in the Port of Durban at the end of July. TNPA started issuing registration instructions...
The development of rural road infrastructure and public transport services remains critical to the delivery of South Africa’s – and other African States’ – developmenta agenda, requiring meticulous planning that ties in with the socioeconomic needs of the host...
South Africa-focused mineral explorer and developer White Rivers Exploration (WRE) has signed a memorandum of understanding (MoU) with Windfall Energy to facilitate the joint exploration and development of WRE’s Heilbron and Kroonstad gas assets in the Witwatersrand...
More
 
 
Recent Research Reports
Real Economy Year Book 2015 (PDF Report)
There are very few beacons of hope on South Africa’s economic horizon. Economic growth is weak, unemployment is rising, electricity supply is insufficient to meet demand and/or spur growth, with poor prospects for many of the commodities mined and exported. However,...
Real Economy Insight: Automotive 2015 (PDF Report)
Creamer Media’s Real Economy Year Book comprises separate reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, gold, iron-ore and platinum sectors.
Real Economy Insight: Water 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Construction 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Electricity 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Road and Rail 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
 
 
 
 
 
This Week's Magazine
NHLANHLA NENE The main constraints to economic growth are domestic
Finance Minister Nhlanhla Nene earlier this month stated that, while South Africa’s 2015 economic growth target of 2% was achievable, it was not enough to deliver the tax revenue needed to combat the country’s challenges.
The World Steel Association has published the 2015 edition of the World Steel in Figures report, which shows an increase in steel production as well as provides an overview of steel industry activities from crude steel production to apparent steel use.
The 25-year master plan for Gauteng’s Aerotropolis project will go through a process of approval and adoption during June and July, says Aerotroplis project manager Jack van der Merwe. “We are also in the process of putting together a special purpose vehicle (SPV) to...
SOLAR PANELS The existing buildings in the Coega Industrial Development Zone lent themselves well to rooftop solar panel installations
The Coega Development Corporation (CDC) plans to fit 15 of its buildings, totalling 127 000 m2 of roof space, in the Coega Industrial Development Zone (IDZ), in the Eastern Cape, with solar panels.
The Supreme Court of Appeal’s (SCA’s) November 2014 judgment, ordering steel producer ArcelorMittal South Africa (AMSA) to hand over the 2003 Environmental Master Plan for its Vanderbijlpark steel plant to environmental pressure groups, confirmed the right of civil...
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96