R15m Kilburn street bridge rehabilitation to start this quarter

10th January 2023

By: Darren Parker

Creamer Media Contributing Editor Online

     

Font size: - +

Rehabilitation work on Kilburn street bridge, in Discovery, Roodepoort, is scheduled to start in the first quarter, following the total collapse of the bridge in early December owing to heavy flooding experienced across Johannesburg.

The Johannesburg Roads Agency (JRA) has prioritised repairs to the Kilburn street bridge at an estimated cost of R15-million owing to previously identified severe embankment erosion, the collapse of the ageing corrugated stormwater culvert pipe and the road layers.

Severe flooding in December led to the total structural collapse of the culvert and road section. The road section has been closed and a traffic diversion plan is in place, the JRA said on January 10.

“An initial design has been completed, which includes a new precast box culvert large enough to carry higher capacity loading and maximum water levels. The old galvanised metal steel corrugated pipe was severely eroded and became too small to support the 14 m wide dual carriageway with a central barrier and single sidewalk, as well as the water flow capacity,” JRA acting CEO Louis Nel said.

The JRA will appoint a contractor through emergency regulations.

In addition, as the bridge culvert falls within an environmentally sensitive area, the JRA has also made an emergency application and applied for an extension from the Department of Agriculture, Rural Development and the Environment, because these applications can ordinarily take up to 24 months to approve.

“We envisage a review of the initial design once reconstruction commences and geotechnical studies have been undertaken to verify the soil conditions. This may impact the initial projected R15-million reconstruction cost,” Nel warned. 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.143 0.203s - 227pq - 2rq
Subscribe Now