https://www.engineeringnews.co.za

Panama Canal expansion project

19th September 2014

  

Font size: - +

Name and Location
Panama Canal expansion project.

Client
The government of Panama, represented by Autoridad del Canal de Panamá (ACP).

Project Description
The project entails the expansion of the Panama Canal by adding a third set of locks, one at each end of the Pacific and Atlantic coasts of the canal.

Each lock facility will feature three consecutive chambers, with lateral water-saving basins, a lateral filling and emptying system, as well as rolling gates.

The Atlantic locks complex will be located east of the existing Gatún locks complex and the Pacific locks complex will be located south-west of the existing Miraflores locks. The location of both complexes will take up an extensive section of the excavations performed by the US government for the third set of locks project, which started in 1939.

The new locks will each be 427 m long, 55 m wide and 18.3 m deep, with a beam of 49 m and a draught of 15.2 m, suitable for ships of up to 366 m in length.

The existing locks are each 304.8 m long, 55 m wide and 18.3 m deep, with a beam of 32.3 m and a draught of 12.4 m, which can accommodate ships of up to 294.1 m in length.

The excavation of new navigational channels will allow for access between the new locks and the existing channels, as well as the deepening and widening of the existing channels. Widening the existing channels to 218 m will allow for the navigation of post-Panamax vessels through these channels in one direction at a time.

The Gaillard Cut and the Gatún Lake’s navigation channels will be deepened by 1.2 m to a precise level datum (PLD) of 9.2 m, raising the maximum operational level of the Gatún Lake by 0.45 m, from its existing 26.7 m PLD to 27.1 m PLD. This project component will increase the Gatún Lake’s functional water-reserve capacity.

The deepening of the Culebra Cut and Gatún Lake, as well as the raising of their maximum operating level, will improve the canal’s water supply and draft dependability.

These measures are intended to allow for the expanded canal to operate without the construction of new reservoirs.

Value
The project is estimated at more than $5.25-billion.

Duration
Commercial transits are expected to begin in mid-2015.

Latest Developments
The third shipment of four gates for the new locks of the Panama Canal expansion project have arrived at the Atlantic entrance of the waterway on September 7.

These gates will be used in the new locks at the Pacific side of the canal.

Two of the gates are 57.6 m long, 10 m wide, 31.92 m high and weigh 4 163 t each. These are the heaviest of the 16 rolling gates to be used in the expanded canal. The other two gates are 57.6 m long, 8 m wide, 22.3 m high and weigh 2 867 t each.

Only one shipment remains to complete the total of 16 gates required for the third set of locks, which is expected to arrive in January 2015. All gates must be in Panama by February 2015.
The expansion is 79% complete.

Key Contracts and Suppliers
Japan Bank for International Cooperation, European Investment Bank, Inter-American Development Bank, Andean Development Corporation and the International Finance Corporation (loan finance); Grupo Unidos por el Canal joint venture, comprising Jan de Nul, Sacyr Vallehermoso, Impregilo and Constructora Urbana (Cusa) (design and construction of the new third set of locks); Peri (planning and supply of formwork and scaffolding systems); Cusa (excavation of the Pacific access channel Phase 1); Cilsa Panama–Minera María consortium (excavation of the Pacific access channel Phase 2); Constructora Meco (excavation of the Pacific access channel Phase 3); a consortium comprising Constructora ICA, Fomento de Construcciones y Contratas and Constructora Meco (excavation of the Pacific access channel Phase 4); Dredging International (dredging of the Pacific entrance navigational channel, the Gatún Lake north access channel and the Atlantic entrance); ACP (dredging for the deepening and widening of Gatún Lake and deepening of the Culebra Cut); Jan de Nul (dredging of the new Pacific access channel north approach); Hyundai Samho Heavy Industries (conduit valves).

On Budget and on Time?
The project is six months behind its eight-year schedule.

Contact Details for Project Information
ACP corporate communications, tel +507 272 7602.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.071 0.122s - 159pq - 2rq
Subscribe Now