Paladin’s Langer Heinrich output below forecast

20th October 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – September-quarter production from the Langer Heinrich mine, in Namibia, was significantly lower than expected, as unforeseen issues with process circuit scaling exacerbated production losses from planned maintenance, ASX- and TSX-listed Paladin Energy reported.

The uranium miner had previously warned shareholders that quarterly production for the three months to September would be down by about 20% on the previous quarter; however, the final production results have come in 23% lower.

The Langer Heinrich mine only produced 1.02-million pounds of uranium oxide (U3O8) during the quarter ended September, compared with the 1.33-million pounds U3O8 produced during the June quarter.

Paladin told shareholders that the source of the scale formation was identified and routine anti-scalant addition procedures were modified during the quarter. By the end of the period, scale formation had been brought under control and all major affected equipment had been cleaned.

In the case of affected process water pipelines, these have either been replaced or, in the case of major pipelines, duplicated to provide future redundancy.

Paladin has maintained its 2015 production guidance of between 5.4-million and 5.8-million pounds of U3O8.

The Kayelekera mine, in Malawi, did not operate during the period under review, as it transitioned to care and maintenance.

Meanwhile, sales during the quarter under review reached 1.25-million pounds U3O8, generating a revenue of $38.95-million.

Uranium deliveries scheduled for the December quarter would total 1.91-million pounds, with a higher expected average sales price, and above the September quarter average sales price, which Paladin said reflected both the improved spot uranium price and delivering volumes into defined price contracts.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.076 0.138s - 156pq - 2rq
Subscribe Now