Oracle a step closer to finalising approval for Pakistan project

21st June 2017

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – UK energy developer Oracle Coalfields is a step closer to finalising the necessary approvals for a mine-mouth power plant in Pakistan with a date now having been set for public hearings to consider the project’s environmental and social impact assessment (ESIA).

Oracle reported on Wednesday that it expected the final approval of the ESIA “shortly after” the public hearing, which would be held on July 13.

The company is developing a combined lignite mineral resource and mine-mouth power plant in the Thar Desert in the southeast of Sindh province. Oracle believes that a power shortage in that country makes the development of Thar a compelling development.

The company’s subsidiary, TEPL, has registered the 660 MW mine-mouth power plant with the Private Power Infrastructure Board (PPIB), a division of the Ministry of Water and Power, which approves independent power producer's proposals to build, own and operate power plants in Pakistan. This registration proposes an overall project of 1 320 MW to be constructed in two phases. In order to obtain the full approval for the project from PPIB a generation licence and electricity tariff also need to be agreed with the authorities along with an approved ESIA for the proposed power plant.

Edited by Creamer Media Reporter

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.122 0.178s - 156pq - 2rq
Subscribe Now