Olifants River Water Resources Development Project Phase 2, South Africa

12th July 2013

By: Creamer Media Reporter

  

Font size: - +

Name and Location
Olifants River Water Resources Development Project Phase 2 (ORWRDP-2), Limpopo, South Africa.

Client
The Department of Water Affairs (DWA), represented by the Trans-Caledon Tunnel Authority (TCTA) for Phases 2B to 2G.

Project Description
The ORWRDP comprises two phases and several subphases:

Phase 1 involved the raising of the Flag Boshielo dam by five metres, which has been completed.

Phase 2 (Phases A to I) involves the development of additional water resource infrastructure in the middle part of the Olifants water management area.

Phase 2A entails the construction of the De Hoop dam, which will be a bulk storage facility to augment the current water supply around the Steelpoort and Olifants rivers, in Limpopo. Water will primarily be supplied to increasing mining activities around the Steelpoort area.

The De Hoop dam, which will be the thirteenth-largest in the country, is expected to have a 347-million-cubic-metre reservoir capacity.

This phase also includes the construction of a roller-compacted concrete (RCC) gravity dam on the Steelpoort river, en route from Stoffberg to Steelpoort, near the existing provincial road (the R555), of which a 20 km portion has been realigned. The dam wall is being built downstream from confluence of the Steelpoort and Klip rivers, the latter being a tributary joining from the eastern side.

Phases 2B to 2G will entail the construction of a bulk distribution system to be funded and implemented by the TCTA.

The ORWRDP-2 is consequently a multipurpose project, incorporating economic and social development objectives to cater for the water demands of commercial and social users.

The project will consist of more than 200 km of pipelines that will vary in diameter from 800 mm to 1 800 mm, several pumpstations and storage reservoirs.

Value
R4.5-billion.

Duration
The construction of the De Hoop dam started in July 2007 and was initially expected to be completed in April 2011; however, owing to the construction challenges, the dam will now be completed in the 2013/14 financial year.

The first construction contract of the bulk distribution system started in early 2012 and will be completed by the end of 2014.

Further phases will be packaged into future contracts, with the last contract likely to be completed as late as 2017.

Latest Developments
The DWA has reported that the De Hoop dam is in its final stage of completion, with the storage of water having started

Work on the first pipeline, which connects water treatment works at Steelpoort for the De Hoop dam, has also started and is expected to be completed by September 2014.

The pipeline to Sekuruwe, in the Waterberg, and Pruissen, in the Capricorn areas, is also planned to start this year.

Key Contracts and Suppliers
For Phase 2A, De Hoop, the key contractors are:
Main Road Contractor (realignment of the R555 road):
Hillary, Liviero & Eigenbau (HLE) joint venture [JV] (main contractor).

Main Civil Contractor (De Hoop dam): De Hoop Construction West and subcontractors B&E International and Quanza JV (supply of fine and course aggregate, crusher run and rip-rap); Limpopo RR & Construction (drilling and blasting); Regray Security (site security); SA Rock Drills (drilling and grouting of dame foundations); Drakensburg Technologies (supply of standard formwork); Formscaff (supply of special formwork); Allied Plant and Hire (erection of RCC conveyor system); SA French (erection of tower crane); NSI (commissioning and maintenance of batch plants); Twin Cities (supply of cement); Dura Pozz Bulk (supply of fly ash); BASF (supply of cement additives); and Steeledale Reinforcing (supply and fixing of reinforcement).

For TCTA, the status of key contracts is as follows:
The Aurecon Ndodana JV was awarded the design and supervision contract in 2009, following an open tender process. Basil Read was awarded the construction contract for Phase 2C and Phase 2H in February 2012.

On Budget and on Time?
Not stated.

Contact Details for Project Information
De Hoop Dam project manager Richard Martin, tel +27 12 336 8072;
De Hoop Dam contractor's representative, Wouter Theron, tel +27 13 260 1110/1111, fax +27 13 260 1356 or email wouter@dhcw.co.za.
TCTA, tel +27 12 683 1200, fax +27 12 683 1300 or email info@tcta.co.za.
HLE JV, Ed Hillary, tel +27 15 293 1221.

Edited by Creamer Media Reporter

Comments

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.1 0.152s - 159pq - 2rq
Subscribe Now