Néstor Kirchner-Jorge Cepernic hydroproject, Argentina

8th September 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Néstor Kirchner-Jorge Cepernic hydroproject.

Location
Santa Cruz, Argentina.

Client
Secretaría de Energía y Mineria, a subsidiary of the Ministerio de Planificación Federal.

Project Description
The Néstor Kirchner-Jorge Cepernic hydroproject will use water from the Santa Cruz river to generate electricity. The hydrocomplex is also expected to produce surplus energy, which could potentially be sold to Brazil.

The Néstor Kirchner dam will be 75.5 m high, include six Francis turbines and have an installed capacity of 1 140 MW, while the Jorge Cepernic dam will be 43.5 m high, include five Kaplan turbines and have an installed capacity of 600 MW.

Jobs to Be Created
The project is expected to employ 5 000 workers during the construction stage.

Value
The project is expected to cost about $5-billion to implement.

Duration
The project is expected to be completed by 2020.

Latest Developments
The Argentina government has announced that it will directly award the contract for the 1 740 MW Kirchner-Cepernic hydrocomplex to expedite its completion, forgoing public tenders.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Secretaría de Energía y Mineria, tel +54 4349 8018.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.101 0.157s - 159pq - 2rq
Subscribe Now