Nova commissioning starts ahead of schedule
PERTH (miningweekly.com) – Commissioning of the nickel processing plant at the Nova project, in Western Australia, has started some four weeks ahead of schedule, owner Independence Group has reported.
The processing plant construction, which included wet commissioning, was completed on October 10, and crushing and milling operations started four days later, following several days of operating on waste to test all systems in slurry.
“The ore commissioning commencement is a great milestone for the Nova project and, combined with the progress that has been achieved with the underground development, marks a significant reduction in the development risk profile of the project,” said Independence MD and CEO Peter Bradford.
“We now expect that we will produce first concentrate, ahead of time, in November and potentially by late October.”
Bradford noted that the project continued on budget.
Over the coming weeks, Independence will focus on calibrating the processing plant control systems and achieving design concentrate grades and recoveries. The last phase of the commissioning process will be the commissioning of the concentrate filters and production of first concentrate.
At full production, the A$443-million Nova project was expected to deliver about 26 000 t/y of nickel, 11 500 t/y of copper and 850 t/y of cobalt over a ten-year mine life.
In July this year, Independence announced plans to accelerate the development of the Bollinger orebody at Nova, with early access to the deposit expected to deliver enhanced early cash flow and additional project value.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation