Northern Gateway pipeline project, Canada

12th August 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Northern Gateway pipeline project, Canada.

Client
Endridge.

Project Description
The project involves the construction of a 1 177 km twin pipeline, from Northern Alberta’s oil sands, through Northern British Columbia to the deep-water port of Kitimat, at the head of the Douglas Channel.

The Kitimat marine terminal will include two ship berths and 19 tanks for oil and condensate. While docked at the terminal, tankers loading export oil will be surrounded by a containment boom.

The forecast is for the terminal to have the capacity to serve about 220 ship calls a year.
The westbound 36-inch-diameter pipeline will carry up to 525 000 bbl/d of oil.

Value
C$7.9-billion.

Duration
Not stated.

Latest Developments
A Canadian court has overturned the approval of Enbridge’s Northern Gateway oil pipeline, adding another steep obstacle to a project fiercely opposed by environmentalists and many First Nations.

Canada’s former Conservative government approved the project in 2014, subject to more than 200 conditions.

After the approval, numerous British Columbia First Nations, along with environmental groups, filed lawsuits seeking to overturn the decision.

The Federal Court of Appeal ruled in a two-to-one decision released in June this year that government had failed in its duty to consult with aboriginal groups on the project and sent the matter back to Prime Minister Justin Trudeau’s cabinet for a “prompt redetermination”.

In its 153-page judgment, the court determined that Canada’s consultation with First Nation communities was “brief, hurried and inadequate.” It said government failed to grapple with their concerns and had not shown any intention to correct any errors or omissions in the original regulatory panel review.

The court also noted that it would have taken government little time and effort to meaningfully engage with First Nations, but that it had not been done. Trudeau’s cabinet will now have to fulfil that duty before a new permit can be issued.

The court decision has been heralded by environmental groups and First Nations, which have said the decision “shuts the door” on the 1 177-km pipeline.

Meanwhile, Enbridge has said in a statement that it remains “fully committed” to building the C$7.9-billion pipeline and that it is working with partners, including First Nation communities who support the project, to determine the next steps.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Enbridge, tel +1 403 231 3900 or fax +1 403 231 3920.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.107 0.162s - 159pq - 2rq
Subscribe Now