https://www.engineeringnews.co.za

New Gold’s Rainy River progresses on schedule, budget

28th June 2017

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – Canadian miner New Gold on Tuesday reported that construction of its $1-billion-plus Rainy River project, in Ontario, remains on track to start operations in September, with commercial production expected to follow in November.

“Through the second quarter, our team has both successfully commenced the staged commissioning of our process facility and delivered on our mining plan. As the pit has opened up, our operations team has recently delivered further increases in the mining rate, including several days over 130 000 t/d,” president and CEO Hannes Portmann said in a press release.

New Gold reported that overall earthworks are more than 85% complete and are tracking in line with its updated plan. Rock deliveries for the starter cell of the tailings management facility are scheduled for completion in late August. All key site overhead power lines have been energised and construction of the tailings pipeline corridor has been completed.    

All the key structural components of the process facilities have been finalised and the setting of mechanical equipment and installation of piping, electrical and instrumentation services is close to completion, the company advised.

The primary crusher and conveyor system was successfully commissioned on schedule and the first crush occurred on May 11. Commissioning of the ball mill and semi-autogenous grinding mill have started with completion scheduled for August. The refining portion of the circuit should be ready to start commissioning in July. Dry and wet commissioning of the full process circuit is scheduled for August.

At full production, the mine is expected to generate an average of 325 000 oz/y of gold, during a planned 14-year mine life. In the first nine years of production, Rainy River would be mined as an openpit operation, after which operations will move underground.

New Gold has guided for full-year output of 380 000 oz to 430 000 oz of gold this year, at an all-in sustaining cost of $760/oz to $800/oz.

Edited by Creamer Media Reporter

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.12 0.185s - 156pq - 2rq
Subscribe Now