https://www.engineeringnews.co.za
Africa|Energy|Gas|Generators|Power|PROJECT|Resources|Storage|Technology
Africa|Energy|Gas|Generators|Power|PROJECT|Resources|Storage|Technology
africa|energy|gas|generators|power|project|resources|storage|technology

Nersa refuses to concur with determination for 3 GW Eskom gas plant

Only the determination for 14 791 MW of new  renewables and storage received the regulator's concurrence

Only the determination for 14 791 MW of new renewables and storage received the regulator's concurrence

Photo by Creamer Media

14th December 2022

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

The National Energy Regulator of South Africa (Nersa) has refused to concur with two electricity procurement determinations submitted by the Department of Mineral Resources and Energy (DMRE) under Section 34 of the Energy Regulation Act – including one for a 3 000 MW Combined Cycle Gas Technology (CCGT) project that Eskom plans to develop in Richards Bay, KwaZulu-Natal.

Earlier this year, the DMRE submitted three determinations for the regulator’s concurrence, which is required before public procurement can take place, including:

  • a determination for the procurement of 1 000 MW of new generation capacity from technologies such as landfill, biogas and co-generators;
  • the procurement of 14 791 MW of new generation capacity from renewables and storage by independent power producers; and
  • a determination for the procurement of 3 000 MW of new CCGT.

During a meeting on December 14, the Energy Regulator voted against concurring with the 1 000 MW determination or the 3 000 MW of CCGT, while approving the determination for 14 791 MW of new generation capacity from renewables and storage in line with the Integrated Resource Plan of 2019 (IRP 2019).

Concurrence was not provided for the 1 000 MW on the basis that a Section 34 determination was the incorrect instrument, as the energy could be procured by Eskom under a Short-Term Power Procurement Programme (STPPP) and the costs recouped through the tariff.

The Energy Regulator made the decision despite the previous STPPP having been mothballed partly because Nersa had refused to treat it as a pass-through cost when making Eskom revenue determinations.

The 3 000 MW CCGT determination was also rejected on the basis that a request to deviate from the IRP 2019 should be pursued as a Section 34 determination.

In its reasons for decision, which were not immediately shared, Nersa would reportedly make a recommendation for the approval to be sought using another section of the Act.

Edited by Creamer Media Reporter

Comments

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.101 0.152s - 156pq - 4rq
Subscribe Now