Moz energy demand to grow 14% a year amid infrastructure challenges
The demand for electricity in Mozambique is set to grow by 14% a year, while regional demand in the South African Power Pool (SAPP) would increase by nearly 1 500 MW a year between 2012 and 2020, according to new analysis by Frost & Sullivan.
Frost & Sullivan’s energy and environmental business unit leader Cornelis van der Waal said the higher demand could be serviced by over 5 000 MW of additional generation capacity which would come on line by 2020.
Mozambique’s two biggest new generation projects, Mphanda Nkuwa and the Cahora Bassa North Bank Expansion, in the Tete province, were estimated to come on line in 2019 and 2020 respectively.
However, the lack of a direct transmission line between the Cahora Bassa power station in the North and the State capital, Maputo, in the South, meant that electricity first has to be exported to South Africa and then imported at an increased cost.
“The lack of adequate transmission and distribution infrastructure in Mozambique is one of the biggest restraints in the electricity industry.
“A widely dispersed population often makes building this infrastructure financially unviable. Off-grid electrification, which allows isolated communities access to electricity, represents a solution to overcoming this restraint,” Said Van der Waal.
Only around 18% of Mozambique’s population had access to the national electricity grid, with an additional 12% having access to electricity through off-grid electrification.
In addition, as a result of low electricity tariffs, utilities were unable to generate enough revenue to invest in maintaining and upgrading electricity infrastructure, which made the power generation market an unviable proposition for independent power producers (IPPs).
“The government of Mozambique is currently revising the electricity tariff structure; if the electricity tariffs are cost-reflective, the market will attract IPPs to finance and build additional electricity infrastructure,” Van der Waal said.
He added that, even though the electricity sector reform had not been completed, IPPs could approach the Ministry of Energy with proposals to finance and construct electricity infrastructure.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation