Minister says 58 renewables sites are in production

20th October 2017

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Energy Minister Mmamoloko Kubayi reports that, as at the end of July, the combined installed generation capacity of renewable-energy independent power producers (IPPs) stood at more than 3 200 MW across 58 sites.

In a reply to a Parliamentary question posed by Economic Freedom Fighters MP Mzingisi Dlamini, the Minister said 27 of these operating IPPs were in the Northern Cape, 13 in the Eastern Cape and 9 in the Western Cape.

Thirty-three IPPs produce electricity using solar photovoltaic (PV) generation technology, while 18 produce electricity using wind turbines. There are also four operating concentrated solar power IPPs, two small-scale hydro sites and one landfill gas IPP.

In total, all the IPPs had generated slightly under 18 000 GWh of energy by the end of July, with the wind farms generating 9 161 GWh and the solar PV sites 7 726 GWh.

The Minister’s snapshot of renewables generation was provided against a backdrop of ongoing delays in introducing new renewable-energy projects, owing to Eskom’s refusal to sign power purchase agreements for solar PV and wind projects procured through the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) in 2015.

However, in a separate response, Kubayi confirmed that government remained committed to ensuring that the contracts for REIPPPP bid windows 3.5 and 4 were signed by the end of this month.

On September 1, she announced Eskom would be expected to sign PPAs for 26 outstanding renewable-energy IPP projects on the proviso that the projects met a 77c/kWh tariff cap, regardless of the generation technology involved.

She also announced a moratorium on all future procurement rounds until the finalisation of the long-awaited update to the Integrated Resource Plan (IRP).

The Minister said public consultation on the IRP had been concluded and that a process was under way to finalise the policy document. The target date of February 2018 was also reaffirmed for promulgation of the IRP.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.162 0.215s - 137pq - 2rq
Subscribe Now