http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 14.24Change: 0.09
R/$ = 10.57Change: 0.03
Au 1306.05 $/ozChange: -6.58
Pt 1486.50 $/ozChange: -2.00
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Suppliers Directory Research Jobs Announcements Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 05, 2008

Medupi project on track for scheduled delivery

Back
Construction|Engineering|Africa|Alstom South Africa|Civils|CoAL|Concor|Eskom|Generator|Hitachi Power Africa|Medupi|Murray & Roberts|PROJECT|Project Management|Resources|Roshcon|Safety|Turbines|Africa|South Africa|Exxaro’s Grootegeluk Mine|Grootegeluk Mine|Matimba Power Station|Boiler Contractor|Civils Contractors|Mining|Turbine Generator Contractor|Environmental|Fabrication|Fani Zulu|Power|Turbines
construction|engineering|africa-company|alstom-south-africa|civils|coal|concor|eskom|generator|hitachi-power-africa|medupi|murray-roberts|project|project-management|resources|roshcon|safety|turbines-company|africa|south-africa|exxaros-grootegeluk-mine-facility|grootegeluk-mine|matimba-power-station|boiler-contractor|civils-contractors|mining|turbine-generator-contractor|environmental|fabrication|fani-zulu|power|turbines-person
© Reuse this




Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines
 
 
 
 
 
 
 
 
Other Electricity News
Nersa's Thembani Bukula
Updated 17 minutes ago A standardised tariff for electricity resellers is needed to avoid consumers being overcharged, energy regulator National Energy Regulator of South Africa (Nersa) said on Tuesday. "The pressing problem right now is that there is a standardised tariff that they...
Updated 2 hours 10 minutes ago Anti-fracking lobby group Treasure the Karoo Action Group (TKAG) and social rights group AfriForum hand delivered a letter to President Jacob Zuma this week calling on him to declare a fresh moratorium on hydraulic fracturing in South Africa, or face possible legal...
The Ilanga II
The University of Johannesburg (UJ) will participate in the Sasol Solar Challenge 2014 with its latest solar car, the Ilanga II. Ilanga is the isiZulu word for the sun.
Article contains comments
More
 
 
Latest News
Nersa's Thembani Bukula
Updated 17 minutes ago A standardised tariff for electricity resellers is needed to avoid consumers being overcharged, energy regulator National Energy Regulator of South Africa (Nersa) said on Tuesday. "The pressing problem right now is that there is a standardised tariff that they...
Economic Development Minister Ebrahim Patel
Updated 25 minutes ago Economic Development Minister Ebrahim Patel says government will be prioritising six ‘I’s as part of its “radical economic transformation” agenda for the coming five years. Delivering his Budget Vote in Parliament on Tuesday, Patel said the six components...
Venetia mine
Updated 37 minutes ago In what could be the single-largest contract awarded to construction major Murray & Roberts (M&R) since the Eskom power build programme, M&R subsidiary M&R Cementation has secured a R2.6-billion contract to develop an underground mine beneath diamond major De...
More
 
 
Recent Research Reports
Real Economy Year Book 2014 (PDF Report)
This edition drills down into the performance and outlook for a variety of sectors, including automotive, construction, electricity, transport, steel, water, coal, gold, iron-ore and platinum.
Real Economy Insight: Automotive 2014 (PDF Report)
This four-page brief covers key developments in the automotive industry over the past 12 months, including an overview of South Africa’s automotive market, trade figures, production and the policies influencing the sector.
Real Economy Insight: Construction 2014 (PDF Report)
This five-page brief covers key developments in the construction industry over the past 12 months. It provides an overview of the sector and includes details of employment in the sector, infrastructure and municipal spending, as well as insight into companies’...
Real Economy Insight: Electricity 2014 (PDF Report)
This five-page brief covers key developments in the electricity industry over the past 12 months, including details of State-owned power utility Eskom’s generation activities, funding and tariffs, independent power producers and prospects for the sector.
Real Economy Insight: Road and Rail 2014 (PDF Report)
This six-page brief covers key developments in the road and rail industries over the past 12 months, including details of South Africa’s road and rail network and prospects for both sectors.
Real Economy Insight: Steel 2014 (PDF Report)
This four-page brief covers key developments in the steel industry over the past 12 months. It provides an overview of the global and South African steel and stainless steel markets, South Africa’s major steel producers and events that have shaped these markets.
 
 
 
 
 
This Week's Magazine
Local aerospace company Denel Aerostructures (DAe), part of the State-owned Denel Group, has won a fourth contract to manufacture parts for the Airbus A400M military air transport and air-to-air refuelling aircraft. The new contract, which was won in an international...
Bob Skinstad
Although CEO Mark McChlery and chief marketing officer Bob Skinstad likened themselves to children in a playground when taking on the task of “reengineering and repositioning” the Seartec brand, the “young, dynamic and enthusiastic guys” were like proud...
An increasing number of buyers, in both the new and used car markets, are opting for finance structures that lower their monthly repayments, says asset financing company WesBank. These include the use of large balloon payments (also known as residuals), as well as...
Tertiary education institutions can use search engine giant Google’s Chromebook to provide secure mobile end-point devices for students on which they can share documents, work collaboratively on documents and access education materials and applications being used...
Local ceiling and partition company Abbeycon has beaten global competition at the Saint-Gobain Gypsum International Trophy competition, which was held last month in Berlin, Germany.
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks