http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.37Change: -0.35
R/$ = 11.97Change: -0.10
Au 1181.43 $/ozChange: -28.42
Pt 1138.00 $/ozChange: -22.50
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 05, 2008

Medupi project on track for scheduled delivery

Back
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Mining|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Mining|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
construction|engineering|africa-company|civils|coal|contractor|design|eskom|fabrication|generator|mining|project|project-management|resources|safety|training|turbines-company|africa|service|environmental|power|turbines-person
© Reuse this




Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Top Projects News
RUSH HOUR The overall Gautrain airport service continues to show positive growth since it started operations on June 8, 2010
To continue offering safe, convenient and efficient service to passengers, rapid transit train Gautrain’s airport service from Sandton to OR Tambo International Airport was improved in August with earlier trains in the mornings and later trains in the evenings, says...
MEDUPI BOILERS Mitsubishi Hitachi Power Systems Africa took over the boiler contacts that were awarded to Hitach
Johannesburg-based company Mitsubishi Hitachi Power Systems Africa, which is constructing boilers for State-owned power utility Eskom’s new Medupi and Kusile power stations, announced a revised top structure, including a new executive chairperson and a new chief...
INDUSTRIAL CHEMICALS Reba Chemicals exports its products to Zimbabwe, Botswana, Namibia, Swaziland and Mozambique
Johannesburg-based chemical manufacturer Reba Chemicals attended this year’s Lephalale Mining Expo, hosted by Mining and Technical Exhibitions (MTE), to establish partnerships that can expand the company’s reach in the area. Reba Chemicals MD Freddy Motau told...
More
 
 
Latest News
Tesla Motors CEO Elon Musk.
Clean energy leader Tesla Motors on Thursday night launched a new range of batteries that could power homes and commercial buildings at a fraction of the expected cost, highlighting the growing demand for the minerals such a s graphite, cobalt and lithium required to...
Eskom said load-shedding should not be needed this weekend. According to the bi-weekly System Status Bulletin‚ released on Thursday‚ the power utility “will once again embark on a massive plant maintenance drive this long-weekend in an effort to improve the...
With just hours to go before the Broad Based Black Economic Empowerment (B-BBEE) Amended Codes of Good Practice come into law on 1 May‚ the Department of Trade and Industry (DTI) had still not clarified several important points - including the draft Qualifying Small...
More
 
 
Recent Research Reports
Steel 2015: A review of South Africa's steel sector (PDF Report)
Creamer Media’s Steel 2015 report provides an overview of the key developments in the global steel industry and particularly of South Africa’s steel sector over the past year, including details of production and consumption, as well as the country's primary carbon...
Projects in Progress 2015 - First Edition (PDF Report)
In fact, this edition of Creamer Media’s Projects in Progress 2015 supplement tracks developments taking place under the Renewable Energy Independent Power Producer Procurement Programme, which has had four bidding rounds. It appears to remain a shining light on the...
Electricity 2015: A review of South Africa's electricity sector (PDF Report)
Creamer Media’s Electricity 2015 report provides an overview of State-owned power utility Eskom and independent power producers, as well as electricity planning, transmission, distribution and the theft thereof, besides other issues.
Construction 2015: A review of South Africa’s construction sector (PDF Report)
Creamer Media’s Construction 2015 Report examines South Africa’s construction industry over the past 12 months. The report provides insight into the business environment; the key participants in the sector; local construction demand; geographic diversification;...
Liquid Fuels 2014 - A review of South Africa's Liquid Fuels sector (PDF Report)
Creamer Media’s Liquid Fuels 2014 Report examines these issues, focusing on the business environment, oil and gas exploration, the country’s feedstock supplies, the development of South Africa’s biofuels industry, fuel pricing, competition in the sector, the...
Water 2014: A review of South Africa's water sector (PDF Report)
Creamer Media’s Water 2014 report considers the aforementioned issues, not only in the South African context, but also in the African and global context, and examines the issues of water and sanitation, water quality and the demand for water, among others.
 
 
 
 
 
This Week's Magazine
Mercedes-Benz will launch ten plug-in hybrid models by 2017, says the German automaker’s parent company, Daimler. Following the launch of the S 500 plug-in hybrid, March saw the introduction of the C 350 e, the second model to feature the drive-train concept. Under...
Energy Minister Tina Joemat-Pettersson's recent unveiling of something of a road map for an upscaled and accelerated deployment of independent power producer (IPP) capacity has been widely welcomed. Besides plans to accelerate and expand the hitherto successful...
South African Airways (SAA) acting CEO Nico Bezuidenhout has firmly denied reports that a stake in the airline was going to be sold to Air China. “Categorically, SAA is not in any talks with any airline to sell itself at the moment,” he stated at a media briefing at...
Russian State-owned nuclear group Rosatom has confirmed that it is in talks with Nigeria about the construction of nuclear power plants (NPPs) in that country, but has denied that any agreement has been signed. This follows a recent report in the Nigerian media that...
HANDIGAS LPG LPG users can order products at the Afrox website or through the Afrox call centre and receive next-day delivery
Gas products and services company Afrox has launched a pilot programme to deliver its range of Handigas liquefied petroleum gas (LPG) to domestic consumers to fill a gap in the market, thereby expanding its direct contact with end-users.
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96