http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.80Change: 0.00
R/$ = 12.58Change: -0.07
Au 1093.57 $/ozChange: -1.92
Pt 990.50 $/ozChange: 5.50
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 04, 2008

Medupi project on track for scheduled delivery

Back
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
construction|engineering|africa-company|civils|coal|contractor|design|eskom|fabrication|generator|health|mining|opencast|project|project-management|resources|safety|training|turbines-company|africa|service|environmental|power|turbines-person
© Reuse this




Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Electrical Power Generation and Transmission News
STRANDED POWER It would not be feasible to propose building a thermal plant in a location far from the nearest gas pipeline
Applying for an independent power producer (IPP) licence required extensive planning, with help from various industry-specific companies, said Nigeria-based energy advisory firm Lavayo Energy CEO Lolu Adubifa, who addressed delegates at the ‘How to Get an IPP...
EXPANDING USE OF SOLAR Regulations in Dubai are aimed at encouraging people to install solar energy
The regulations to govern solar power connection in Dubai homes and businesses in the United Arab Emirates (UAE), are in the final stages of development.
HARNESSING WIND POWER Siemens will manufacture rotor blade for wind turbines to contribute to the 2 GW of wind power capacity that will be generated in Egypt
Electrical engineering company Siemens and the Egyptian government reached two firm agreements on March 14, firstly to build a 4.4 GW combined-cycle power plant and, secondly, to install wind power capacity of 2 GW – both in Egypt.
More
 
 
Latest News
Not only were new oil and gas (O&G) discoveries in East Africa a catalyst for investment into road, rail and pipeline infrastructure, but they also contributed to the region’s economic growth, with growth of 5.5% projected for this year and an estimated 6% to 7% for...
Transnet has won the 2014 Nkonki State-Owned Company (SOC) Integrated Reporting Award for the best performer. Assurance and advisory firm Nkonki on Wednesday released the findings of its 2015 review of integrated reporting by South African SOCs. The report, titled...
Leading water scientists say it is no longer debatable that South Africa is experiencing a water crisis given that there are already serious problems in supplying enough water of sufficient quality to meet the country’s social and economic needs. CSIR researchers...
More
 
 
Recent Research Reports
Real Economy Year Book 2015 (PDF Report)
There are very few beacons of hope on South Africa’s economic horizon. Economic growth is weak, unemployment is rising, electricity supply is insufficient to meet demand and/or spur growth, with poor prospects for many of the commodities mined and exported. However,...
Real Economy Insight: Automotive 2015 (PDF Report)
Creamer Media’s Real Economy Year Book comprises separate reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, gold, iron-ore and platinum sectors.
Real Economy Insight: Water 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Construction 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Electricity 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Road and Rail 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
 
 
 
 
 
This Week's Magazine
Meyerton-based steel tank manufacturer Structa Technology is currently rolling out a water infrastructure build programme that supports local municipalities, water utilities, schools, hospitals and clinics.
Alternative funding models could be expected to begin coming to the fore in South Africa’s renewable-energy sector as the market becomes more competitive and domestic development finance institutions (DFIs) begin scaling back their direct involvement in projects....
DIMITRI MARKOULIDES An innovation champion must involve employees in innovation projects and keep them updated to enable them to support and drive innovation and create the future of the business
An innovation champion course that trains executives to manage innovation in their organisations aims to help companies grow revenue streams and tap new markets, says business change management consultancy BMGI South Africa innovation practice lead Dimitri...
Future digital workplaces will require employees to continuously learn new “literacies”, including new media, information and technical skills, to help their company thrive and spur personal growth. Information technology (IT) research firm Gartner, thus, suggests...
Only 25% of large construction projects surveyed in KPMG’s Global Construction Project Owner’s Survey, released in June, were concluded on time and within budget over the last three years. “Every project owner wants predictability when it comes to large projects, and...
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96