R/€ = 15.26Change: -0.01
R/$ = 14.41Change: -0.03
Au 1057.95 $/ozChange: 0.07
Pt 835.50 $/ozChange: 0.00
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?

And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters About Us
RSS Feed
Article   Comments   Other News   Research   Magazine  
Dec 05, 2008

Medupi project on track for scheduled delivery

Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
© Reuse this

Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines (150 word limit)
Other Electricity News
Ratings firms Moody's and Standard and Poor's kept South African utility Eskom's credit status unchanged, saying recent cash injections by government had eased a funding crunch, the power firm said on Friday. Moody's affirmed the Ba1, or speculative grade, rating of...
Fund management firm Gaia Infrastructure Partners has concluded a landmark equity transaction in the Dorper wind farm project, a preferred bidder under Round 1 of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) run by the Department of...
JSE-listed investment holding company Labat Africa has concluded a R560-million subscription and buy-back agreement for the acquisition of a 100% interest in Reinhardt Transport Group (RTG) and its Chrome Carriers subsidiary. The acquisition, which would see...
Article contains comments
Article contains comments
Article contains comments
Latest News
French conglomerate Bollore may have to halt work on the Niger to Benin section of its giant West Africa rail project after a rival company won a court order to stop it going ahead. The dispute concerns rival rail schemes in the area.
A week ahead of the second annual gathering of the Forum on China–Africa Cooperation (Focac), in Johannesburg, the JSE is rolling out the proverbial red carpet for Chinese investors looking to Africa’s largest bourse for possible investment opportunities, calling...
The South African National Roads Agency Limited (Sanral) applied for leave to appeal on Friday against the Western Cape High Court judgment that set aside the approvals that would enable it to toll sections of the N1 and N2 freeways in Cape Town. This prompted the...
Recent Research Reports
Water 2015: A review of South Africa's water sector (PDF Report)
Creamer Media’s Water 2015 Report considers the aforementioned issues, not only in the South African context but also in the African and global context in terms of supply and demand, water stress and insecurity, and access to water and sanitation, besides others.
Input Sector Review: Pumps 2015 (PDF Report)
Creamer Media’s 2015 Input Sector Review on Pumps provides an overview of South Africa’s pumps industry with particular focus on pump manufacture and supply, aftermarket services, marketing strategies, local and export demand, imports, sector support, investment...
Liquid Fuels 2015: A review of South Africa's liquid fuels sector (PDF Report)
Creamer Media’s Liquid Fuels 2015 Report examines these issues in the context of South Africa’s business environment; oil and gas exploration; fuel pricing; the development of the country’s biofuels industry; the logistics of transporting liquid fuels; and...
Road and Rail 2015: A review of South Africa's road and rail sectors (PDF Report)
Creamer Media’s Road and Rail 2015 report examines South Africa’s road and rail transport system, with particular focus on the size and state of the country’s road and rail infrastructure and network, the funding and maintenance of these respective networks, and...
Defence 2015: A review of South Africa's defence sector (PDF Report)
Creamer Media’s Coal 2015 report examines South Africa’s coal industry with regards to the business environment, the key participants in the sector, local demand, export sales and coal logistics, projects being undertaken by the large and smaller participants in the...
Real Economy Year Book 2015 (PDF Report)
There are very few beacons of hope on South Africa’s economic horizon. Economic growth is weak, unemployment is rising, electricity supply is insufficient to meet demand and/or spur growth, with poor prospects for many of the commodities mined and exported. However,...
This Week's Magazine
The BMW Group will invest R6-billion at BMW Group South Africa’s (BMW SA’s) Rosslyn plant to produce the next-generation X3 sports-activity vehicle (SAV) for the local and export markets. Rosslyn will continue production of the current 3 Series through its lifecycle,...
The lack of consequences for poor performance and transgressions on the part of contractors remains a significant hurdle to tackling South Africa’s service delivery challenges, delegates heard at the Consulting Engineers South Africa Infrastructure Indaba, on...
City of Ekurhuleni executive mayor Mondli Gungubele earlier this month officially named the city’s bus rapid transit (BRT) system, Harambee.
NICK CHRISTODOULOU As about 58% of data stored by organisations is dark, they must identify this dark data to expose risks and valuable information
About 58% of unstructured data stored by companies is dark data, which means that the value or regulatory importance of the data has not been determined. Subsequently, most of the stored data add costs, rather than increasing revenue or reduce regulatory risks, says...
BRIAN VERWEY Effective management, review and administration of non-core elements can improve business operations and increase revenue and decrease unforeseen risks
Effective logistics, import/export and manufacturing consulting services require detailed industry knowledge and experience, but can add significant value to these industries by providing expert advice on various technical elements in their value chains, says...
Alert Close
Embed Code Close
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96