http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 14.26Change: 0.05
R/$ = 11.30Change: -0.03
Au 1209.05 $/ozChange: 0.36
Pt 1272.50 $/ozChange: -29.50
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 05, 2008

Medupi project on track for scheduled delivery

Back
Construction|Engineering|Africa|Alstom South Africa|Civils|CoAL|Concor|Eskom|Generator|Hitachi Power Africa|Medupi|Murray & Roberts|PROJECT|Project Management|Resources|Roshcon|Safety|Turbines|Africa|South Africa|Exxaro’s Grootegeluk Mine|Grootegeluk Mine|Matimba Power Station|Boiler Contractor|Civils Contractors|Mining|Service|Turbine Generator Contractor|Environmental|Fabrication|Fani Zulu|Power|Turbines
Construction|Engineering|Africa|Civils|CoAL|Eskom|Generator|PROJECT|Project Management|Resources|Safety|Turbines|Africa|||Mining|Service||Environmental|Fabrication|Power|Turbines
construction|engineering|africa-company|alstom-south-africa|civils|coal|concor|eskom|generator|hitachi-power-africa|medupi|murray-roberts|project|project-management|resources|roshcon|safety|turbines-company|africa|south-africa|exxaros-grootegeluk-mine-facility|grootegeluk-mine|matimba-power-station|boiler-contractor|civils-contractors|mining|service|turbine-generator-contractor|environmental|fabrication|fani-zulu|power|turbines-person
© Reuse this




Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Electricity News
Article contains comments
Toshiba’s Westinghouse Electric Company on Monday launched an expedited review application in the South Gauteng High Court challenging Eskom’s decision to award a R4.3-billion contract to Areva, of France, for the replacement of steam generators at the Koeberg...
Cellular major MTN South Africa has approved two gas-powered generation developments for its Doornfontein (1 MW) and Newlands (6 MW) sites, in Gauteng, based on the success of its 2 MW trigeneration plant at its Roodepoort headquarters. MTN will expand this methane-...
Article contains comments
Efforts by the Kenya government to increase energy generation by 5 000 MW over the next three years received a major boost following the award of a $2-billion contract to build a coal power plant in Lamu.  Despite allegations of irregular tendering process, the...
Article contains comments
More
 
 
Latest News
Updated 1 hour 2 minutes ago The latest TransUnion Vehicle Pricing Index (VPI) contains a number of small, but significant indications that the tide may at last be turning for the beleaguered used car industry. For the third successive quarter, used car inflation has increased on a year-on-year...
Updated 1 hour 11 minutes ago JSE-listed Redefine Properties on Wednesday announced an equity raising of about R1-billion through the issue of new shares. The equity raise was subject to pricing acceptable to Redefine and would be implemented through an accelerated bookbuild process. Only public...
Updated 1 hour 28 minutes ago The seasonally adjusted Kagiso Purchasing managers’ index (PMI) rose above the neutral 50-point mark in September, signaling growth for the manufacturing sector for the first time since March, revealed Kagiso Tiso Holdings in a statement on Wednesday. BNP Paribas...
More
 
 
Recent Research Reports
Road and Rail 2014: A review of South Africa's road and rail infrastructure (PDF report)
Creamer Media’s Road and Rail 2014 report examines South Africa’s road and rail transport system, with particular focus on the size and state of the country’s road and rail network, the funding and maintenance of these respective networks, and the push to move road...
Real Economy Year Book 2014 (PDF Report)
This edition drills down into the performance and outlook for a variety of sectors, including automotive, construction, electricity, transport, steel, water, coal, gold, iron-ore and platinum.
Real Economy Insight: Automotive 2014 (PDF Report)
This four-page brief covers key developments in the automotive industry over the past 12 months, including an overview of South Africa’s automotive market, trade figures, production and the policies influencing the sector.
Real Economy Insight: Construction 2014 (PDF Report)
This five-page brief covers key developments in the construction industry over the past 12 months. It provides an overview of the sector and includes details of employment in the sector, infrastructure and municipal spending, as well as insight into companies’...
Real Economy Insight: Electricity 2014 (PDF Report)
This five-page brief covers key developments in the electricity industry over the past 12 months, including details of State-owned power utility Eskom’s generation activities, funding and tariffs, independent power producers and prospects for the sector.
Real Economy Insight: Road and Rail 2014 (PDF Report)
This six-page brief covers key developments in the road and rail industries over the past 12 months, including details of South Africa’s road and rail network and prospects for both sectors.
 
 
 
 
 
This Week's Magazine
Updated 50 minutes ago The latest TransUnion Vehicle Pricing Index (VPI) contains a number of small, but significant indications that the tide may at last be turning for the beleaguered used car industry. For the third successive quarter, used car inflation has increased on a year-on-year...
The South African new vehicle market is likely to reach around 630 000 units in 2014, down from the 650 000 units recorded in 2013, says Toyota South Africa Motors (TSAM) president and CEO Dr Johan van Zyl. Van Zyl is also president of the National Association of...
Efforts by the Kenya government to increase energy generation by 5 000 MW over the next three years received a major boost following the award of a $2-billion contract to build a coal power plant in Lamu.  Despite allegations of irregular tendering process, the...
Using crafty wordplay on a well-known Internet meme, brilliant South African-born US entrepreneur and businessperson Elon Musk announced that Tesla Motors would not initiate patent lawsuits against anyone who, in good faith, wanted to use its technology. Instead,...
August new vehicle sales declined by 1.4%, to 55 722 units, compared with the same month last year. Assisted by the car rental market, the South African new passenger car market, at 37 953 units, contracted by 1 047 units, or 2.7%, compared with August last year.
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks