http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.69Change: -0.08
R/$ = 12.42Change: -0.04
Au 1168.42 $/ozChange: -3.47
Pt 1062.00 $/ozChange: 0.80
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 05, 2008

Medupi project on track for scheduled delivery

Back
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
Construction|Engineering|Africa|Civils|CoAL|Contractor|Design|Eskom|Fabrication|Generator|Health|Mining|OPENCAST|PROJECT|Project Management|Resources|Safety|Training|Turbines|Africa|Service|Environmental|Power|Turbines
construction|engineering|africa-company|civils|coal|contractor|design|eskom|fabrication|generator|health|mining|opencast|project|project-management|resources|safety|training|turbines-company|africa|service|environmental|power|turbines-person
© Reuse this




Despite the current slow progress being made on the development of the site of the Medupi power station, State-owned power utility Eskom is confident that the Medupi power station, which is being built in Limpopo, will be delivered on time.

Eskom spokesperson Fani Zulu, indicates that the current progress is based on a five-day work schedule. Efforts are being put into place to accelerate the work schedule.

Eskom says that the rock foundation conditions encountered at Medupi have not been as expected.

Specifically, it has been found that although normal blasting removed the rock, it also resulted in the shattering of rock some distance away from the intended areas. It has, therefore, been necessary to resort to the use of controlled blasting through the use of more, significantly smaller, explosive charges.

Zulu reports that this did not delay the completion of the site preparation and terracing work and the site was handed over to the main civils contractors on the agreed date.

Current indications from Eskom indicate that the first unit should be ready for commercial operation in April 2012.

After the completion of the preparation of the rock excavation area, Eskom handed over the area to its subsidiary, Roshcon, for site preparation and terracing. This has been completed and the rock excavation area has been handed over to the MPS joint venture between civils contractors Murray & Roberts, Concor and Grinaker-LTA.

The turbine generator contractor for the Medupi project, Alstom South Africa, is on site and is supervising the construction of the turbine hall in line with its overall design for the project.

Eskom reports that Hitachi Power Africa, boiler contractor for the Medupi project, is on site and is in the process of completing the construction of the company’s on-site fabrication plant.

The design reviews of the boilers and turbines are ongoing.

The interfaces between the main civils, turbine and boiler contracts are being clarified, with each of the contractors’ individual programmes being integrated into the overall Medupi schedule.

Environmental Concerns
During the preparation of the Medupi site, Eskom reports that the utility took a number of environmental issues into consideration.

In June, Engineering News reported that the foremost environ- mental consideration was the relocation of a baobab tree that was believed to be a few hundred years old and which has been described as a visual beacon.

After a lengthy process, the tree was relocated to where the future entrance to the power station will be sited. The 70-t tree sprouted its first leaves in February.

Many other indigenous trees were also either replanted or transported to a special nursery at the nearby Matimba power station.

Because the site for the Medupi power station was previously an area where a number of wild animals roamed freely, Eskom needed to relocate some 30 to 40 animals to a neighbouring nature reserve.

The utility reports that a programme has been initiated to capture and relocate all the snakes found on the construction site; this is being done in conjunction with a local snake expert. The snake expert also presents educational talks to the workers on site.

The topsoil and vegetation, which are being removed as part of the clearing process, are being preserved to be used for the rehabilitation of the existing Matimba power station ash dump, and possibly some of the Exxaro and Grootegeluk mine spoil dumps.

Coal Supply Contract
An agreement on the coal supply contract with Medupi has been reached between Eskom and coal-mining giant Exxaro.

In terms of the agreement, Exxaro’s Grootegeluk mine, will, over the next 40 years, supply an average of 14,6-million tons of power-station-grade coal to Medupi every year. The coal to Medupi will be supplied through a brownfield expansion of the Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate.

The coal beneficiation process will be handled by two new dense-media facilities, namely the Grootegeluk 7 and the Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
Exxaro has a similar coal supply agreement with Eskom for the Matimba power station.

Social Development
A significant challenge that Eskom is faced with on a continuous basis is the skills crisis. Eskom is resolving this crisis through ongoing recruitment exhibition events, sourcing skills locally and internationally, and entering into partnership with local and international project management companies.

Eskom reports that the require- ment of skills development and localisation of people and resources is receiving significant focus from the utility, as well as from contractors. Further, plans are in place for contractors to provide training for the local people and the main civils contractor has established a training centre near the site.

In June, it was reported that the utility had about 850 contractor employees working on the project.

However, this number was set to increase over the duration of the roll-out of the civils work.

This expansion has neces- sitated detailed planning and rigorous health, safety and environmental practices in an effort to instil a safe-practice philosophy in all its workers.

The Medupi power station is the first power station that is being constructed as part of Eskom’s capacity expansion programme, which aims to increase the utility’s service offering to the public. It is the first baseload, coal-fired station to be built in South Africa in over 20 years and its delivery is viewed as critical, given that Eskom is currently operating at an uncomfortably low reserve margin of well below 10%.

Once Medupi reaches full capacity in 2016, its 4 800-MW generation capacity will provide the utility with a capacity increase which will be in excess of 10%.

The baseload plant will be made up of six 800-MW units and will be commissioned in phases.

The first unit of the Medupi power station could be operational by mid-2012. The remaining units are scheduled to be commissioned at nine-monthly intervals, so the last units are expected to be commissioned by March 2016.

Edited by: Laura Tyrer
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Construction News
Updated 1 hour 55 minutes ago This eight-page brief is a synopsis of key developments in the construction industry over the past 12 months. It provides an overview of South Africa’s construction sector and includes details thereof in the public and private sectors, as well as labour and skills...
Cabinet in June approved the establishment of a Border Management Agency, to be tasked with integrating the functions of all government departments and agencies that operate at South African ports of entry, said Transport Minister Dipuo Peters on Monday. Speaking at...
The Gautrain Management Agency (GMA) and the Gautrain provincial government “were close to announcing” a R3-billion investment, funded by the Development Bank of Southern Africa, to buy additional rolling stock, build a new depot, and install additional signalling,...
More
 
 
Latest News
Sappi CEO Steve Binnie
Updated 10 minutes ago Dissolving wood pulp and paper products manufacturer Sappi and Norwegian firm Borregaard will invest R105-million on expanding the production capacity of their joint venture (JV) lignin manufacturing operation LignoTech South Africa, in KwaZulu-Natal, by 20 000 t/y....
Sphere Holdings CEO Itumeleng Kgaboesele
Updated 42 minutes ago Black-owned investment holding company Sphere Holdings plans to raise a further R1-billion in the coming months in support of its strategy of becoming a leading black industrial enterprise, which could ultimately seek a listing on the JSE. CEO Itumeleng Kgaboesele,...
Updated 58 minutes ago Deputy Minister of Home Affairs Fatima Chohan declared on Monday that she is willing to accompany representatives of the South African tourism industry to China in order to see how dropping visitor numbers from that country can be curbed. She took part in a visa...
More
 
 
Recent Research Reports
Real Economy Year Book 2015 (PDF Report)
There are very few beacons of hope on South Africa’s economic horizon. Economic growth is weak, unemployment is rising, electricity supply is insufficient to meet demand and/or spur growth, with poor prospects for many of the commodities mined and exported. However,...
Real Economy Insight: Automotive 2015 (PDF Report)
Creamer Media’s Real Economy Year Book comprises separate reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, gold, iron-ore and platinum sectors.
Real Economy Insight: Water 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Construction 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Electricity 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
Real Economy Insight: Road and Rail 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
 
 
 
 
 
This Week's Magazine
NHLANHLA NENE The main constraints to economic growth are domestic
Finance Minister Nhlanhla Nene earlier this month stated that, while South Africa’s 2015 economic growth target of 2% was achievable, it was not enough to deliver the tax revenue needed to combat the country’s challenges.
The World Steel Association has published the 2015 edition of the World Steel in Figures report, which shows an increase in steel production as well as provides an overview of steel industry activities from crude steel production to apparent steel use.
The 25-year master plan for Gauteng’s Aerotropolis project will go through a process of approval and adoption during June and July, says Aerotroplis project manager Jack van der Merwe. “We are also in the process of putting together a special purpose vehicle (SPV) to...
SOLAR PANELS The existing buildings in the Coega Industrial Development Zone lent themselves well to rooftop solar panel installations
The Coega Development Corporation (CDC) plans to fit 15 of its buildings, totalling 127 000 m2 of roof space, in the Coega Industrial Development Zone (IDZ), in the Eastern Cape, with solar panels.
The Supreme Court of Appeal’s (SCA’s) November 2014 judgment, ordering steel producer ArcelorMittal South Africa (AMSA) to hand over the 2003 Environmental Master Plan for its Vanderbijlpark steel plant to environmental pressure groups, confirmed the right of civil...
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96