https://www.engineeringnews.co.za

Medupi power station project, South Africa

9th June 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Medupi power station project.

Location
Medupi is located on an 883 ha site in Lephalale, Limpopo, in South Africa.

Client
State-owned power utility Eskom.

Project Description
Medupi will be a dry-cooled, coal-fired, baseload power-generating plant, comprising six 794 MW units, with a 4 764 MW installed capacity. It will be the fourth-largest coal-fired power plant in the southern hemisphere, and the largest of its kind with direct dry cooling, in the world.

The planned operational life of the station is 50 years.

The power station will use high-tech supercritical boilers, which will operate at higher temperatures and pressures than older boilers, thereby providing greater efficiency. Supercritical technology will result in better use of natural resources, such as water and coal, and will have improved environmental performance.

It is the first baseload coal-fired power station to be built in South Africa in more than 20 years and its delivery on schedule is viewed as critical.

The project is somewhat unique because Medupi is being built in reverse order – traditionally Eskom has always started building Unit 1 and ended with Unit 6. This new approach is the result of the rock agglomeration on the southern side of the site, which was excavated and reused for engineering fill on the northern side.

The project forms part of the utility’s integrated strategic electricity plan and is designed to be flue-gas desulphurisation ready.

Jobs to be Created
About 18 000 construction contractor employees and 2 000 supporting staff were employed at the peak of construction.

Value
In July 2016, Eskom officially updated its cost-to-completion estimates for Medupi. The State-owned utility reported that Medupi was now expected to cost R145-billion, rather than the earlier revised estimate of R105-billion. The estimate included interest during construction.

Duration
The entire six-unit Medupi project is expected to be completed in 2020.

Construction activities started in May 2007.

The first unit, Unit 6, was first synchronised to the grid in the first quarter (beginning March) of 2015. In August 2015, Unit 6 of Medupi became commercially operational.

Unit 5, the second unit, was synchronised to the grid in September 2016 and was loaded to full capacity in December 2017, reaching commercial operation at the beginning of April 2017.

Unit 4 was synchronised to the grid in June 2017.

Latest Developments
Eskom announced on June 1 that Unit 4 had been synchronised to the grid.

This is the third of six units to come on stream. Synchronisation marks a key milestone towards the full commercial operation of a unit. Unit 4 is scheduled for commercial operation in 2018.
                                                                                                                                                              
Key Contracts and Suppliers
Main packages:
Parsons Brinckerhoff (execution partner); Roshcon (enabling civils); Rula Bulk Materials Handling (coal overland conveyor and ash dump conveyor); Mitsubishi Hitachi Power Systems Africa, or HMPSA (boiler); Alstom S&E Africa (turbine); LP Services consortium (engineering, procurement and construction contract for the low-pressure services); Ovivo Aqua SA (water treatment plant); Karrena-Concor joint venture, or JV (chimneys and silos); MPS JV (main civils); Actom (electrical power installation); General Electric (low-voltage switchgear system); Actom (medium-voltage switchgear); Siemens (auxiliary transformers and generator transformers); Standby Systems (uninterruptible power supply); Alstom C&I (control and instrumentation); Honeywell Automation & Control Solutions South Africa (condition-based maintenance systems); T-Systems (information technology (IT) and IT infrastructure); Siemens ACI Open Consortium (laboratory and analysers); Civcon/G4 JV (miscellaneous infrastructure and reservoirs); Basil Read (buildings Phase 2, ash dump infrastructure and clarifiers); NCI (diesel generators); ThyssenKrupp Materials Handling (coal stockyard equipment); Clyde Bergemann Africa (dust handling and conditioning systems); ELB Engineering Services (terrace coal and ash); Aveng Grinaker-LTA (buildings phases 1 and 3) and Tubular (supply and erection of conveyors).

Other contractors:
a.b.e. Construction Chemicals, Afrimat, BKS Group, DSE Structural Engineers & Contractors, Exxaro Resources, GEA Aircooled Systems, Genrec Engineering, Hansen Transmissions, MHPSA, Mitsubishi Hitachi Power Europe, Kwikspace, IWC, Lesedi Nuclear Services, Mikropul, Murray & Roberts, Royal HaskoningDHV, Sarens, SSD, Steloy Castings, Sulzer Pumps South Africa, Tubular, Voith Turbo, Wetback Contracts, Lighting Structures, Konecranes, Wade Walker, Energy Engineered Products, Turnmill Proquip Engineering, and SNC-Lavalin (inspections Unit 6), Vital Engineering (supply of Vitaclamps).

On Budget and on Time?
The project has in the past, been afflicted by technical and labour difficulties. However, measures have been put in place to accelerate the progress, and recover the lost time. This has been evident through the latest achievements of the project milestones as per the project plan.

Contact Details for Project Information
Eskom, Medupi Project, project director Phillip Dukashe, email phillip.dukashe@eskom.co.za.
Eskom media desk, email mediadesk@eskom.co.za.
 

Edited by Creamer Media Reporter

Comments

Showroom

SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.09 0.142s - 159pq - 2rq
Subscribe Now