Medupi power station project, South Africa

30th September 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name of the Project
Medupi power station project.

Location
Medupi is located on an 883 ha site in Lephalale, Limpopo, in South Africa.

Client
Eskom.

Project Description
Medupi will be a dry-cooled, coal-fired, baseload power-generating plant, comprising six 800 MW units, with a 4 800 MW installed capacity. It will be the fourth-largest coal plant, and the largest of its kind with dry cooling, in the world.

The planned operational life of the station is 50 years.

The power station will use high-tech supercritical boilers, which will operate at higher temperatures and pressures than older boilers, thereby providing greater efficiency. Supercritical technology will result in better use of natural resources, such as water and coal, and will have improved environmental performance.

It is the first baseload coal-fired power station to be built in South Africa in more than 20 years and its delivery on schedule is viewed as critical.

The project is somewhat unique because Medupi is being built in reverse order – traditionally Eskom has always started building Unit 1 and ended with Unit 6. This new approach is the result of the rock agglomeration on the southern side of the site, which was excavated and reused for engineering fill on the northern side.

The project will form part of the utility’s integrated strategic electricity plan and is designed to be flue-gas desulphurisation ready.

Jobs to be Created
Not stated.

Value
In July this year, Eskom officially updated its cost-to-completion estimates for Medupi. The State-owned utility reported that Medupi was now expected to cost R145-billion, rather than the earlier revised estimate of R105-billion. The estimate did include interest during construction.

Duration
The entire six-unit Medupi project is expected to be completed in 2020.

Construction activities started in May 2007.

The first unit, Unit 6, was first synchronised to the grid in the first quarter (beginning March) of 2015. In August 2015, Unit 6 of Medupi became commercially operational.

Unit 5 was synchronised to the grid in September this year. The unit is expected to become commercially operational by March 2018.

Latest Developments
Public Enterprises Minister Lynne Brown confirmed on September 8 that the second 800 MW unit – Unit 5 – at the Medupi coal-fired power station project had been synchronised to the grid.

Synchronisation, Eskom explains, is when the generator in the unit is connected into the power grid so that it is aligned with all other generators on the national grid. It then starts to generate and deliver electricity into the grid over several months. Unit 5 will become commercially operational by March 2018.

Key Contracts and Suppliers
Main packages:
Parsons Brinckerhoff (execution partner); Roshcon (enabling civils); Rula Bulk Materials Handling (coal overland conveyor and ash dump conveyor); Mitsubishi Hitachi Power Systems Africa, or MHPSA (boiler); Alstom S&E Africa (turbine); LP Services consortium (engineering, procurement and construction contract for the low-pressure services); Ovivo Aqua SA (water treatment plant); Karrena-Concor joint venture, or JV (chimneys and silos); MPS JV (main civils); Actom (electrical power installation); General Electric (low-voltage switchgear system); Actom (medium-voltage switchgear); Siemens (auxiliary transformers and generator transformers); Standby Systems (uninterruptible power supply); Alstom C&I (control and instrumentation); Honeywell Automation & Control Solutions South Africa (condition-based maintenance systems); T-Systems (information technology (IT) and IT infrastructure); Siemens ACI Open Consortium (laboratory and analysers); Civcon/G4 JV (miscellaneous infrastructure and reservoirs); Basil Read (buildings Phase 2, ash dump infrastructure and clarifiers); NCI (diesel generators); ThyssenKrupp Materials Handling (coal stockyard equipment); Clyde Bergemann Africa (dust handling and conditioning systems); ELB Engineering Services (terrace coal and ash); Aveng Grinaker-LTA (buildings phases 1 and 3) and Tubular (supply and erection of conveyors).

On Budget and on Time?
The project has been afflicted by technical and labour difficulties and is running years behind schedule and well over its initial budget.

Contact Details for Project Information
Eskom project director Phillip Dukashe, email phillip.dukashe@eskom.co.za.
Eskom media desk, email mediadesk@eskom.co.za.

Main packages:
Parsons Brinckerhoff, tel +27 11 787 4141, fax +27 11 886 0359 or email project@pbworld.com.
Roshcon, tel +27 11 629 8000 or fax +27 11 626 3460.
Rula Bulk Materials Handling, tel +27 11 795 1040, fax +27 11 795 1004 or email info@rula.co.za.
Ovivo Aqua SA, tel +27 11 886 0266.
Actom, tel +27 11 820 5111 or fax +27 11 820 5100.
GE corporate investor communications, tel +1 203 373 2460.
Siemens, tel +27 11 652 2000 or fax +27 11 652 2711.
Standby Systems, tel +27 861 782 632, fax +27 11 794 3598 or email standbypower@mweb.co.za.
Honeywell Automation & Control Solutions South Africa, tel +27 11 695 8000 or fax +27 11 805 1554.
Civcon/G4 JV, tel +27 11 206 9660, fax +27 11 316 6604 or email info@civcon.co.za; tel +27 11 396 1793, fax +27 11 396 2344 or email info@g4.co.za.
Basil Read, tel +27 11 418 6300 or fax +27 11 418 6333.
NCI, tel +27 21 553 8840, fax +27 21 553 8841 or email info@nci-sa.co.za.
ThyssenKrupp Materials Handling, tel +27 11 236 1000, fax +27 11 236 1235 or email info.tkmh@thyssenkrupp.com.
Clyde Bergemann Africa, tel +2 7 11 704 0580, fax +27 11 704 0597 or email enquiry@cbz.co.za.
ELB Engineering Services, tel +27 11 772 1400, fax +27 11 325 6680 or email sales@elb.co.za.
Aveng Grinaker-LTA, tel +27 11 578 6000 or fax +27 11 578 6161.

Other contractors:
a.b.e. Construction Chemicals, tel +27 11 306 9000.
Afrimat investor and corporate relations, tel +27 11 325 5944 or fax +27 11 325 5942.
BKS Group, tel +27 12 421 3500, fax +27 12 421 3501 or email group@bks.co.za.
DSE Structural Engineers & Contractors, tel +27 11 871 4111, fax +27 11 871 4141 or email dse@grinaker-lta.co.za.
Exxaro Resources, tel +27 12 307 4189.
GEA Aircooled Systems, tel +27 11 861 1521.
Genrec Engineering, tel +27 11 876 2300, fax +27 11 827 1733 or email sales@genreceng.co.za.
Hansen Transmissions, tel +27 11 571 9611.
MHPSA head of sales and business development David Milner, tel +27 11 260 4300, fax +27 11 656 3609 or email info@za.mhps.com.
Mitsubishi Hitachi Power Europe, tel +49 203 80 38 0 or fax +49 203 80 38 1809.
Kwikspace, tel +27 11 903 8993 or email barney@kwikspace.co.za.
IWC, tel +27 11 466 0699, fax +27 11 466 8180 or email mail@iwc.co.za.
Lesedi Nuclear Services, tel +27 21 525 1300 or fax +27 21 525 1333.
Mikropul, tel +27 478 0456, fax +27 478 0371 or email sales@mikropul.co.za.
Murray & Roberts, tel +27 11 723 2080.
Royal HaskoningDHV, tel +27 11 798 6000, fax +27 11 798 6005 or email corporate@rhdhv.com.
Sarens, tel +27 11 861 3800, fax +27 11 861 3899 or email info@sarenssa.co.za.
SSD, tel +27 11 828 0439 or fax +27 11 828 2810.
Steloy Castings, tel +27 13 933 3331, fax +27 13 933 3653 or email info@steloy.com.
Sulzer Pumps South Africa, tel +27 11 820 6252 or fax +27 11 820 6205.
TKMH, tel +27 11 236 1000 or fax +27 11 236 1235.
Tubular, tel +27 11 553 2000, fax +27 11 450 2160 or email th@tubular.co.za.
Voith Turbo, tel +27 11 418 4076 or fax +27 11 418 4059.
Wetback Contracts, tel +27 11 392 8000, fax +27 11 392 5856 or email info@wetback.co.za.
Lighting Structures, tel +27 87 310 1000 or fax +27 86 699 6999.
Konecranes, tel +27 11 864 2800.
Wade Walker, tel +27 11 466 0377.
Energy Engineered Products, tel +27 11 466 1926 or fax +27 11 466 1692.
Turnmill Proquip Engineering, tel +27 16 986 0030 or fax +27 16 986 0127.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.163s - 159pq - 2rq
Subscribe Now