Medupi power station project, South Africa

10th April 2015

  

Font size: - +

Name and Location
Medupi power station project, Limpopo, South Africa.

Client
Eskom.

Project Description
Medupi is located on an 883 ha site in Lephalale, Limpopo.  It will be a dry-cooled coal-fired, baseload power-generating plant, comprising six 800 MW units, with a 4 800 MW installed capacity. It will be the fourth-largest coal plant and the largest of its kind with dry cooling in the world.

The planned operational life of the station is 50 years.

The power station will use high-tech supercritical boilers, which will operate at higher temperatures and pressures than older boilers, thereby providing greater efficiency.

It is the first baseload coal-fired station to be built in South Africa in more than 20 years and its delivery on schedule is viewed as critical.

The project is somewhat unique because Medupi is being built in reverse order – traditionally Eskom has always started building Unit 1 and ended with Unit 6. This new approach is the result of the rock agglomeration on the southern side of the site, which was excavated and reused for engineering fill on the northern side.

The project will form part of the utility's integrated strategic electricity plan and is designed to be flue-gas desulphurisation ready.

Value
The cost of the project is R105-billion.

Duration
Construction activities started in May 2007.  The first unit, Unit 6, will be synchronised to the grid in the first quarter of 2015.

Latest Developments
Construction has been halted again at Eskom’s Medupi power plant as the remaining construction workers have joined the dismissed group belonging to the National Union of Metalworkers of South Africa (Numsa). The Medupi site was  evacuated on March 25, after some workers began protesting against certain conditions while also demanding completion bonuses. These workers are employed by contractors and not by Eskom.

Numsa said on April 9 that its members had joined the dismissed 1 700 in a gesture of solidarity to compel employers to reverse the dismissal motion.

Eskom-contracted companies at the Medupi power plant have dismissed workers and locked them out as they returned to work after the Easter weekend.

Eskom has accused workers of embarking on an unprotected strike.

Numsa regional organiser Mahlodi Modike has said that will not bow to a divide and rule strategy, adding that by allowing workers who are on strike to return to work and targeting others, employers are "dividing workers" and sowing discontent.

Eskom spokesperson Khulu Phasiwe told Fin24 on April 8 that disciplinary action was taking place against 1 700 workers who took part in the unprotected strike action on March 25.

“Those members are only allowed to come to Medupi for their disciplinary hearing,” he said.

Numsa head of collective bargaining Steve Nhlapo has demanded that Eskom open the site so that workers can continue their duties.

Meanwhile, Eskom has said that full power from Medupi Unit 6 should be reached by the end of May and that it is working to ensure that the completion of the remaining five units is not undermined by further technical or labour problems.

The first 800 MW unit was synchronised to the national power grid on March 2, and is being tested and optimised to enable its full integration into the utility’s larger operating fleet. Once the other five units are completed, the 4 800 MW power plant will represent 12% of the State-owned utility’s installed capacity.

Eskom has also reported that, since its first synchronisation, Unit 6 has been delivering 400 MW. However, owing to testing and combustion optimisation, the power is being delivered intermittently, which will will continue until full power (800 MW) is reached by “around end-May 2015”.

Key Contracts and Suppliers
Main packages:
Parsons Brinckerhoff (execution partner); Roshcon (enabling civils); Rula Bulk Materials Handling (coal overland conveyor and ash dump conveyor); Mitsubishi Hitachi Power Systems Africa, or MHPSA (boiler); Alstom S&E Africa (turbine); LP Services consortium (engineering, procurement and construction contract for the low-pressure services); Ovivo Aqua SA (water treatment plant); Karrena-Concor joint venture, or JV (chimneys and silos); MPS JV (main civils); Actom (electrical power installation); General Electric (low-voltage switchgear system); Actom (medium-voltage switchgear); Siemens (auxiliary transformers and generator transformers); Standby Systems (uninterruptible power supply); Alstom C&I (control and instrumentation); Honeywell Automation and Control Solutions South Africa (condition-based maintenance systems); T-Systems (information technology (IT) and IT infrastructure); Siemens ACI Open Consortium (laboratory and analysers); Civcon/G4 JV (miscellaneous infrastructure and reservoirs); Basil Read (buildings Phase 2, ash dump infrastructure and clarifiers); NCI (diesel generators); ThyssenKrupp Materials Handling (coal stockyard equipment); Clyde Bergemann Africa (dust handling and conditioning systems); ELB Engineering Services (terrace coal and ash); Aveng Grinaker-LTA (buildings phases 1 and 3) and Tubular (supply and erection of conveyors).

On Budget and on Time?
Following various delays, including a protracted strike that resulted in work on the project being delayed for more than six months in 2013 alone, Eskom initially indicated that synchronisation of Unit 6 would take place in late December 2014.

There had also been delays regarding the boiler blow-through process, which was one of the final commissioning steps ahead of grid synchronisation. The process is used to clean the steam of residue and particles prior to feeding it through to the turbine. It was then indicated that the schedule for first synchronisation would be shifted to late February or early March.

Eskom and Mitsubishi Hitachi Power Systems Africa, the boiler contractor, subsequently set up a joint technical task team to review the blow-through procedure ahead of future blow-through tests at Medupi and Kusile.

Contact Details for Project Information
Eskom project director Roman Crookes, email roman.crookes@eskom.co.za.
Eskom media desk, email mediadesk@eskom.co.za.

Main packages:
Parsons Brinckerhoff, tel +27 11 787 4141, fax +27 11 886 0359 or email project@pbworld.com.
Roshcon, tel +27 11 629 8000 or fax +27 11 626 3460.
Rula Bulk Materials Handling, tel +27 11 795 1040, fax +27 11 795 1004 or email info@rula.co.za.
Ovivo Aqua SA, tel +27 11 886 0266.
Actom, tel +27 11 820 5111 or fax +27 11 820 5100.
GE corporate investor communications, tel +1 203 373 2460.
Siemens, tel +27 11 652 2000 or fax +27 11 652 2711.
Standby Systems, tel +27 861 782 632, fax +27 11 794 3598 or email standbypower@mweb.co.za.
Honeywell Automation and Control Solutions South Africa, tel +27 11 695 8000 or fax +27 11 805 1554.
Civcon/G4 JV, tel  +27 11 206 9660, fax +27 11 316 6604 or email info@civcon.co.za; tel +27 11 396 1793, fax +27 11 396 2344 or email info@g4.co.za.
Basil Read, tel +27 11 418 6300 or fax +27 11 418 6333.
NCI, tel +27 21 553 8840, fax +27 21 553 8841 or email info@nci-sa.co.za.
ThyssenKrupp Materials Handling, tel +27 11 236 1000, fax +27 11 236 1235 or email info.tkmh@thyssenkrupp.com.
Clyde Bergemann Africa, tel +2 7 11 704 0580, fax +27 11 704 0597 or email enquiry@cbz.co.za.
ELB Engineering Services, tel +27 11 772 1400, fax +27 11 325 6680 or email sales@elb.co.za.
Aveng Grinaker-LTA, tel +27 11 578 6000 or fax +27 11 578 6161.

Other contractors:
a.b.e. Construction Chemicals, tel +27 11 306 9000.
Afrimat investor and corporate relations, tel +27 11 325 5944 or fax +27 11 325 5942.
BKS Group, tel +27 12 421 3500, fax +27 12 421 3501 or email group@bks.co.za.
DSE Structural Engineers & Contractors, tel +27 11 871 4111, fax +27 11 871 4141 or email dse@grinaker-lta.co.za.
Exxaro Resources, tel +27 12 307 4189.
GEA Aircooled Systems, tel +27 11 861 1521.
Genrec Engineering, tel +27 11 876 2300, fax +27 11 827 1733 or email sales@genreceng.co.za.
Hansen Transmissions, tel +27 11 571 9611.
MHPSA head of sales and business development David Milner, tel +27 11 260 4300, fax +27 11 656 3609 or email info@za.mhps.com.
Mitsubishi Hitachi Power Europe, tel +49 203 80 38 0 or fax +49 203 80 38 1809.
Kwikspace, tel +27 11 903 8993 or email barney@kwikspace.co.za.
IWC, tel +27 11 466 0699, fax +27 11 466 8180 or email mail@iwc.co.za.
Lesedi Nuclear Services, tel +27 21 525 1300 or fax +27 21 525 1333.
Mikropul, tel +27 478 0456, fax +27 478 0371 or email sales@mikropul.co.za.
Murray & Roberts, tel +27 11 723 2080.
Royal HaskoningDHV, tel +27 11 798 6000, fax +27 11 798 6005 or email corporate@rhdhv.com.
Sarens, tel +27 11 861 3800, fax +27 11 861 3899 or email info@sarenssa.co.za.
SSD, tel +27 11 828 0439 or fax +27 11 828 2810.
Steloy Castings, tel +27 13 933 3331, fax +27 13 933 3653 or email info@steloy.com.
Sulzer Pumps South Africa, tel +27 11 820 6252 or fax +27 11 820 6205.
TKMH, tel +27 11 236 1000 or fax +27 11 236 1235.
Tubular, tel +27 11 553 2000, fax +27 11 450 2160 or email th@tubular.co.za.
Voith Turbo, tel +27 11 418 4076 or fax +27 11 418 4059.
Wetback Contracts, tel +27 11 392 8000, fax +27 11 392 5856 or email info@wetback.co.za.
Lighting Structures, tel +27 87 310 1000 or fax +27 86 699 6999.
Konecranes, tel +27 11 864 2800.
Wade Walker, tel +27 11 466 0377.
Energy Engineered Products, tel  +27 11 466 1926 or fax +27 11 466 1692.
Turnmill Proquip Engineering, tel +27 16 986 0030 or fax +27 16 986 0127.

Edited by Creamer Media Reporter

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.089 0.14s - 159pq - 2rq
Subscribe Now