Medupi-linked water scheme delayed, but ‘poses no risk’ to start up

The Medupi power station site.

The Medupi power station site.

Photo by Duane Daws

3rd March 2014

By: Terence Creamer

Creamer Media Editor

  

Font size: - +

The first phase of the Mokolo and Crocodile Water Augmentation Project (MCWAP), which is under construction partly to provide water from Mokolo dam to the Medupi power station, is behind schedule, Eskom has confirmed. However, the State-owned power utility insists that the delay does not pose a water-supply risk to the power station, the first 800 MW unit of which, Unit 6, is scheduled for commissioning in the second half of 2014.

The delay on both the pipeline and the pump-station components of the scheme has been attributed to strike-related disruptions, as well as damage to the works caused by heavy rainfall and contractor underperformance. State-owned Trans-Caledon Tunnel Authority is the project owner and the Aveng and Umbutho Civil and Electrical Joint Venture the construction contractor.

Eskom tells Engineering News Online that, as of the end of January, 25.5 km of what will be a 43 km pipeline had been laid and that the full pipeline is expected to be completed by June 9.

“The construction of the pump station is 97% complete, with dry commissioning forecast for completion on July 16,” Eskom said in a reply to questions. The projected “full water delivery date” is September 9, but should there be further disruptions, the delivery schedule could slip to December 9.

“Project teams from the contractor and employer are managing the expected fallout due to the demobilisation of labour, by engaging the labour and interested stakeholders,” Eskom reports, noting that agreement has been reached on a demobilisation plan.

The contractor is also incurring penalties for the late delivery of the project, but has committed to completing the project by September 9.

Eskom insists that there is sufficient pipeline capacity and water already available to meet Medupi’s water requirements for commissioning and operations.

It notes that the 10.3 km section of the MCWAP Phase 1 gravity pipeline was commissioned on October 29 last year, which has raised the existing pipeline capacity from 14.7-million cubic metres a year to 23-million cubic metres.

“There is, thus, enough pipeline infrastructure capacity to supply six units of Medupi power station from Mokolo dam, excluding water required for flue gas desulphurisation abatement technology, which Eskom will install once MCWAP Phase 2 is completed.”

Once MCWAP Phase 1 is commissioned, the water transfer capacity will increase to 30-million cubic metres a year, with Medupi receiving a maximum of 10.9-million cubic metres. The plant’s yearly demand will be 15.4-million cubic metres and additional water will be supplied from the second phase of MCWAP.

Eskom says it is currently in negotiations with the Department of Water Affairs regarding the MCWAP Phase 2 supply agreements and that water delivery from this phase is projected to be by the end 2019.

Edited by Creamer Media Reporter

Comments

Showroom

Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.52 0.572s - 150pq - 2rq
Subscribe Now