Completion date for southern Malawi road project extended

12th September 2014

By: Marcel Chimwala

Creamer Media Correspondent

  

Font size: - +

Completion of the ongoing construction of the 102 km Zomba–Jali–Phalombe–Chitakale road, in southern Malawi, has been extended from June to December 15 because of persistent rains and difficulties in paying the contractor.

The project is being undertaken by Kuwait’s MA Kharafi & Sons and financed by a S$76-million loan that the Malawi government has obtained from the Organisa- tion of the Petroleum Exporting Countries Fund for International Development, the Kuwaiti Fund for Arab Economic Development and the Arab Bank for Economic Development in Africa.

The contractor has applied for the extension of the period for completion of the construction works because of persistent rains in the construction area and challenges in accessing payments.

Construction started in 2005 and the project was expected to be completed in 2008. However, the project was suspended after the $57-million funding initially earmarked to complete the project was exhausted.

“The Malawi government entered into negotiations with the contractor to resolve the outstanding issues and the contractor remobilised to site in October 2012. It was expected that, by the end of June 2014, the project would be completed, but the contractor has applied for an extension to December 15,” says Malawi Roads Agency spokesperson Portia Kajanga.

She explains that the project’s price tag has gone up from the initial estimate of $57-million to $76-million, owing to increases in the prices of construction materials, as well as weather conditions.

The Arab financial institutions are also financing the construction of the 92 km Thyolo–Thekerani–Muona–Bangula road, in southern Malawi, the cost of which has also escalated – $64-million to $92-million – owing to similar reasons.

The other road projects currently under construction or rehabilitation in Malawi include the 69 km Jenda–Edingeni road, the 160 km Lilongwe–Nsipe road, the Zomba–Blantyre road, the Lilongwe City West bypass road and the Masauko Chipembere highway.

Besides the Arab financial institutions, the other financiers of road projects in Malawi include the European Union, the African Development Bank and the Japanese government.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.076 0.134s - 137pq - 2rq
Subscribe Now