Major engineering milestone as Lesotho dam achieves full capacity

23rd August 2018

By: Creamer Media Reporter

     

Font size: - +

This article has been supplied as a media statement and is not written by Creamer Media. It may be available only for a limited time on this website.

The new $100-million Metolong Dam in Lesotho has achieved a significant project success this year, with the dam spilling for the first time since its completion in 2016.


Spilling occurs when the dam is at full capacity, and the dam’s spillway – meant to direct excess water downstream during flood periods – comes into operation. This was the first time the dam was subjected to the full range of stresses it was designed for. The dam passed this test with flying colours.


Metolong Dam Project Manager Beyers Havenga, a Technical Executive at GIBB, said that the spilling stage was the last test of the integrity of the dam following the construction phase of the project.


“Now we can say that the project was a success. It’s fulfilling its objective, which is to supply water to Maseru and environs for domestic use, as well as for economic development.”


The 83m-high Metolong Dam is situated 30km east of Maseru. It features a 280m-long crest, with a 75m spillway just below it. It is a roller-compacted concrete (RCC) gravity dam, with a total concrete volume of 315 000m3. It is designed to hold a capacity of 63 million m3 of water.


The project was built using an innovative new concrete blend of Ordinary Portland Cement (OPC) and Pulverised Fly Ash (PFA), which improves workability, and reduces the temperature of the mixture when setting and helps to prevent cracking. The Metolong Dam project also comprises an intake tower, outlet works and a raw-water pump station.


The Metolong Dam Water Supply Programme forms part of the Lesotho Lowlands Water Project, aimed at improving water supply for domestic water consumption and for local industry, which was hampered by an acute water shortage in the mountain kingdom.


According to the World Bank[1], the new dam supplies water to two-thirds of Lesotho’s two million population,and created employment for 3 000 Basotho during its construction phase.


The broader project is also electrifying 75 villages and providing healthcare and HIV/AIDS community support programmes to 15 000 local residents.


“Despite only achieving capacity now, the dam has been yielding water for several years,” said Havenga. “The dam now delivers water to the water treatment works, which supplies Maseru and neighbouring towns like Mazenod, Morija, Roma and Teyateyaneng.
 
“Lesotho is urbanising quickly,” said Havenga. “A large proportion of Lesotho citizens now reside in and around Maseru, and this is where most industrial development happens. This puts pressure on infrastructure and other water resources. This project was necessary to support the growth of the country.”


The Metolong Dam Water Supply Programme was worth $450 million and was financed by the World Bank and a consortium of funders from the Middle East, Europe and South Africa, with the government of Lesotho.


In dam construction, the first time a dam spills is a fascinating, but critical time, explained Havenga. “This is the first opportunity to see the spillway operating as intended. It is a day for great celebration for us engineers, especially considering how many thousands of people will benefit.”

Edited by Creamer Media Reporter

Comments

Projects

Image of Kenya map/flag
High Grand Falls dam, Kenya
Updated 2 hours 56 minutes ago By: Sheila Barradas

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.075 0.128s - 158pq - 2rq
Subscribe Now