Mahenge graphite DFS results unveiled

24th October 2018

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A definitive feasibility study (DFS) into the Mahenge graphite project, in Tanzania, has increased the capital cost of the project, while both the estimated net present value (NPV) and internal rate of return (IRR) have dropped.

ASX-listed Black Rock Mining on Wednesday revealed that the Phase 1 capital expenditure has increased from the $90.7-million estimated in the 2017 prefeasibility study (PFS), to $115-million, while the Phase 2 capital cost have decreased from $72.2-million to $69.5-million, and the Phase 3 costs have increased slightly from $81.7-million to $84.2-million.

The project’s post-tax NPV declined from the $1.1-billion to $895-million, while the post-tax IRR decreased from 50.1% to 42.8%.

The project’s mine life has remained unchanged at 32 years, with average steady-state production also being maintained at 250 000 t/y.

“When setting out to deliver our DFS our primary objective was to develop the study to the point where it would support a bankable level of due diligence,” said Black Rock CEO John de Vries.

“With over 25 000 person hours using consultants and contractors with real graphite mine construction and operations’ experience, I am very confident we have differentiated ourselves, and delivered on that outcome.”

De Vries said that the core element of the DFS was the operation of the 90 t pilot plant, the largest plant ever run in the graphite sector at DFS stage.

“The plant provided invaluable data and operating performance for process plant design and flowsheet optimisation. Critically, the plant also delivered eight tonnes of concentrate with which we could engage customers and develop a dialogue around preferences and product attributes.

“We are confident that our approach to market segmentation, and a focus on channel strategy based on credible volumes of real products, will yield results with product offtake.”

Black Rock recently signed an offtake agreement with China’s Heilongjiang Bohao Graphite Company for natural flake graphite from the Mahenge project.

The three-year agreement would see Black Rock supply 30 000 t in the first year, 50 000 t in the second year, and up to 90 000 t in the last year of the offtake.

Edited by Creamer Media Reporter

Comments

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.177 0.228s - 156pq - 2rq
Subscribe Now