http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.85Change: 0.03
R/$ = 10.93Change: 0.05
Au 1231.31 $/ozChange: -0.06
Pt 1248.50 $/ozChange: -1.00
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Jun 08, 2012

Hospital, prison infrastructure projects under way

Back
Construction|DURBAN|Engineering|Natal|PIETERMARITZBURG|SECURITY|Bitumen|Cement|Concrete|Copper|Fire|Lighting|Pipe|Pipelines|Pipes|PROJECT|Projects|Road|Safety|Security|SSI|System|Systems|Waste|Water|Ballito Pipeline|ED4 Pipeline|Estcourt Prison|Ngwelezane Hospital|Security|Building|Equipment|Fire Prevention Systems|Hospital Site|Kitchen Equipment|Medical Gas|Pipes|Security|Steel|Systems|Transport|Environmental|Cobus Van Deventer|Darren Van Rooyen|Infrastructure|Power|Security|Waste|Water|Pipe|Pipelines|Valves
Construction|Engineering|SECURITY|Bitumen|Cement|Concrete|Copper|Fire|Lighting|Pipe|Pipelines|Pipes|PROJECT|Projects|Road|Safety|Security|SSI|System|Systems|Waste|Water|Security|Building|Equipment|Pipes|Security|Steel|Systems|Transport|Environmental|Infrastructure|Power|Security|Waste|Water|Pipe|Pipelines|Valves
construction|durban|engineering|natal|pietermaritzburg|security|bitumen|cement-company|concrete|copper|fire|lighting|pipe-company|pipelines-company|pipes|project|projects|road|safety|security-company|ssi|system|systems-company|waste-company|water-company|ballito-pipeline|ed4-pipeline|estcourt-prison|ngwelezane-hospital-facility|security-facility|building|equipment|fire-prevention-systems|hospital-site|kitchen-equipment|medical-gas|pipes-industry-term|security-industry-term|steel|systems|transport-industry-term|environmental|cobus-van-deventer|darren-van-rooyen|infrastructure|power|security-person|waste|water|pipe|pipelines|valves
© Reuse this



Engineering and environmental consultancy SSI is undertaking a number of infrastructure upgrades in KwaZulu-Natal (KZN), including structural and building infrastructure upgrades at the Ngwelezane and Empangeni provincial hospitals and the Estcourt prison.

The R7-million Empangeni Hospital Project was awarded to SSI in September 2003 by the KwaZulu-Natal Public Works Department and includes work at both the Empangeni and Ngwelezane hospitals.

The overall project is scheduled for completion in December 2013.

The main contract is a four-storey exten- sion to the existing Empangeni hospital building, which is currently under construction, with 20% already complete.

The extension of the Empangeni provincial hospital accounts for 60% of the total project scope and involves the complete upgrade of the existing hospital, including a 200-bed extension, essentially doubling the hospital’s size, says SSI sector area manager Cobus van Deventer.

The project scope for the remaining work at the Empangeni provincial hospital site entails the replacement of the cold-water piping with copper piping, as well as the chillers; the upgrade of the nursery and the new-mothers lodge, all of which have been completed.

Upgrades to the existing building include work at the antiretroviral clinic; the corridor, kitchen, laundry and store areas; the nurses residences; the security and transport building; the workshop; and the refuse and medical waste areas.

A paediatric centre is being added onto the existing hospital and is 20% complete, says Van Deventer.

Meanwhile, the project scope at the Ngwelezane hospital site includes chiller replacement, corridor upgrades and exten- sions to the trauma and casualty depart- ments, all of which have been completed.

Upgrades were also undertaken at the mortuary, the workshops, the nurses college, the transport facility and the clinical engineering offices of the existing hospital.

Further, two new staff residences have been built, as well as a psychiatric ward, a psychiatric outpatient clinic and a therapy department.

The existing wards were demolished and replaced with new 72-bed wards.

Future work at the hospital will include the construction of a new 72-bed ward, a theatre block, an administation block and upgrading of the existing kitchen and laundry areas.

An additional project awarded to SSI by the KwaZulu-Natal Public Works Department is the R2.3-million upgrade of the Estcourt Prison.

Van Deventer reports that the site was handed over at the end of May, following the tender process and contractor appointment.

The scope of the project, which is scheduled for completion in July 2013, comprises the complete electrical design and installation, including reticulation; power; lighting and closed-circuit television, an intercom system and wireways for telephones.

It also includes heating, ventilation and air conditioning; refrigeration; fire prevention systems; kitchen equipment; medical gas; and a hot water plant.

SSI is responsible for submitting a progress report to the KwaZulu-Natal Depart- ment of Public Works, as well as the part-time contract administration and site supervision.

Water Infrastructure
SSI is also involved in water infrastructure upgrades in KZN, including the augmentation of the Hazelmere to Ballito pipeline, the ED2–ED4 pipeline and the ED4 to Umlaas road pipeline.

These bulk water infrastructure upgrades are being undertaken in response to the increasing water demands of the eThekwini municipality and the Durban and Pieter- maritzburg areas.

The latest pipeline upgrade is the 13-km-long ED4 to Umlaas road pipeline, which was awarded to onshore pipeline rehabilitator Esorfranki Pipelines, in April and is scheduled for completion in January 2014.

This upgrade forms part of the so-called existing ’61 Pipeline, which conveys potable water from the Midmar water treatment works (WTW) to Pietermaritzburg and Durban.

SSI water engineer Darren van Rooyen explains that the duplication of the ’61 Pipeline will be done in stages, with a second pipeline system being installed parallel to the existing system.

“The first stage consists of the pipeline from ED2 to ED4, while the second stage consists of the pipeline from ED4 to Umlaas road – with a simultaneous project to supply bulk potable water to Richmond.”

Umgeni Water contracted Esorfranki Pipelines as the contractor for both projects.

Subcontractors include PPT, which was reponsible for the cathodic protection; subconsultancy JCM Surveys, which conducted engineering surveys; and Intervention Systems, which is the health and safety agent on the project.

The R52-million ED2–ED4 pipeline comprises a 3.8 km 1 300-mm-diameter pipe with 40 bar-rated valves, which was recently completed.
The next stage, the R196-million ED4 to Umlaas road pipeline comprises a 13 km 1 100-mm-diameter pipe with PN 40- and PN 25-rated valves.

Both pipelines are continuously welded steel pipes with epoxy linings and bitumen coatings, notes Van Rooyen.

The ED4 to Umlaas road pipeline crosses under the N3 in a jacked sleeve with a 15-m-high vertical access shaft on the northern side.

Van Rooyen says both pipelines include offtakes and cross connections with the existing ’61 Pipeline.

He adds that a significant challenge during the ED2–ED4 project was the tie-in of the new pipeline to the existing ’61 Pipeline.

“The amount of work required on such large-diameter pipes and fittings is [extensive considering] the short shutdown periods allowed. To mitigate a water shortage to consumers in Edendale and eThekwini, only short shutdown periods were allowed,” explains Van Rooyen.
SSI was able to overcome this challenge by conducting the tie-ins in smaller, more manageable stages than originally planned, to reduce downtime.

“The design of the three projects was carried out by SSI under one appointment to handle all the complexities of the inter- connected hydraulic and operational requirements, states Van Rooyen.

SSI is also involved in the R52-million Hazelmere to Ballito pipeline project, which will transport water from the Hazelmere WTW to the La Mercy bifurcation point.

“The project entails the supply and laying of 10.8 km of 700-mm-diameter continuously welded steel pipeline with a cement mortar lining and a polyurethane coating by the main project contractor, Icon Construction,” says Van Rooyen.

SSI is responsible for providing the detailed design, water hammer analyses, preparation of construction drawings, tender documentation and reporting, construction management and construction monitoring, as well as the commissioning and handover to the client.

Phase 1 of the pipeline was designed and commissioned by SSI in 1995, while the detailed design of Phase 2 was awarded in August 2009.

Phase 2 is about 30% complete.

“Umgeni Water’s target date for completion is November, in line with peak water demand, owing to the influx of holidaymakers to Ballito,” states Van Rooyen.

Minor rehabilitation and concrete work on the pipeline will be completed by March 2013.

An area of difficulty during the project was the stringent environmental conditions set by the Dube TradePort (DTP) – an international airport and trade development in KZN – to accommodate a future road to the DTP, which would cross the pipeline serviture and require SSI to make late changes to accommodate this.

To overcome these difficulties, an agreement between the environmental control officers of both Umgeni Water and DTP was reached to reallocate a portion of DTP’s offset wetland to accommodate the pipeline.

Edited by: Chanel de Bruyn
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Construction News
Swedish Ambassador to South Africa Christian Meuwly will next week inaugurate the final roll-out of the new vertical shaft brick kiln (VSBK) at clay brick manufacturer Langkloof Bricks’ facility in Jeffrey’s Bay. The VSBK formed a part of economic, social and...
Tanzania and China have signed investment deals to build a $1 billion satellite city and $500 million financial centre in the commercial capital Dar es Salaam, the latest sign of Beijing's deepening ties with East Africa. The total of five deals, worth more than $1.7...
Rosatom logo
The Department of Energy (DoE) reported on Thursday night that it had concluded its first “nuclear vendor parade workshop” with a delegation from the Russian Federation and that further meetings were planned with vendor countries such as France, China, South Korea,...
More
 
 
Latest News
Swedish Ambassador to South Africa Christian Meuwly will next week inaugurate the final roll-out of the new vertical shaft brick kiln (VSBK) at clay brick manufacturer Langkloof Bricks’ facility in Jeffrey’s Bay. The VSBK formed a part of economic, social and...
Hot on the heels of the launch of Rustenburg’s rapid transport system’s brand name and logo last week, a negotiation framework agreement (NFA) has been formally agreed to and signed by the Rustenburg Local Municipality (RLM) and taxi and bus operators affected by the...
The runway at the George Airport, in the Western Cape, has been rehabilitated to improve safety, in terms of run-off and storm water drainage, and the structural capacity of the pavement surface. The scope of work comprised the extension of Runway 11/29, the...
More
 
 
Recent Research Reports
Defence 2014: A review of South Africa's defence industry (PDF Report)
Creamer Media’s Defence 2014 report examines South Africa’s defence industry, with particular focus on the key participants in the sector, the innovations that have come out of the sector, local and export demand, South Africa’s controversial multibillion-rand...
Road and Rail 2014: A review of South Africa's road and rail infrastructure (PDF report)
Creamer Media’s Road and Rail 2014 report examines South Africa’s road and rail transport system, with particular focus on the size and state of the country’s road and rail network, the funding and maintenance of these respective networks, and the push to move road...
Real Economy Year Book 2014 (PDF Report)
This edition drills down into the performance and outlook for a variety of sectors, including automotive, construction, electricity, transport, steel, water, coal, gold, iron-ore and platinum.
Real Economy Insight: Automotive 2014 (PDF Report)
This four-page brief covers key developments in the automotive industry over the past 12 months, including an overview of South Africa’s automotive market, trade figures, production and the policies influencing the sector.
Real Economy Insight: Construction 2014 (PDF Report)
This five-page brief covers key developments in the construction industry over the past 12 months. It provides an overview of the sector and includes details of employment in the sector, infrastructure and municipal spending, as well as insight into companies’...
Real Economy Insight: Electricity 2014 (PDF Report)
This five-page brief covers key developments in the electricity industry over the past 12 months, including details of State-owned power utility Eskom’s generation activities, funding and tariffs, independent power producers and prospects for the sector.
 
 
 
 
 
This Week's Magazine
Integrated energy and chemical company Sasol has partnered with Unisa Graduate School of Business Leadership (SBL) professor and founder and CEO of PanAvest Partnership Dr Douglas Boateng to publish a series of books on executive supply chain management aimed at...
MORNÉ DU PLESSIS Increased urgency and burgeoning awareness of the importance of these issues are beginning to change political risks and, thus, State responses to environmental concerns
The World Wide Fund for Nature’s (WWF’s) 2014 Living Planet Index (LPI) indicates that there has been a 52% decline in vertebrate species since 1970. The Index tracked the trends of 10 000 discrete populations of over 3000 vertebrate species between 1970 and 2010.
Rwanda has joined a number of East African countries seeking to import electricity from Ethiopia as its demand grows. After it became apparent several generation project it is implementing will not come on stream early enough, now plans to import 400 MW from Ethiopia...
Metrorail’s first new passenger train will arrive in November next year, says Passenger Rail Agency of South Africa (PRASA) CEO Lucky Montana. “Next year we will be able to put our hands around the infrastructure and equipment we have been talking about for so long.”
The Competition Commission has launched an investigation into what it says are “price fixing, market division and collusive tendering in the market for the manufacture and supply of automotive components to original equipment manufacturers” (OEMs, or vehicle...
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks