http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 13.36Change: -0.01
R/$ = 12.16Change: 0.00
Au 1190.60 $/ozChange: 1.57
Pt 1110.50 $/ozChange: 0.00
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters Contact Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Jun 08, 2012

Hospital, prison infrastructure projects under way

Back
Construction|DURBAN|Engineering|Natal|PIETERMARITZBURG|Bitumen|Building|Concrete|Contractor|Copper|Design|Fire|Health|Installation|Lighting|Pipe|Pipelines|Pipes|PROJECT|Projects|Road|Safety|SECURITY|SSI|System|Systems|transport|Waste|Water|Ballito Pipeline|ED4 Pipeline|Estcourt Prison|Ngwelezane Hospital|Equipment|Fire Prevention Systems|Hospital Site|Kitchen Equipment|Medical Gas|Pipes|Steel|Systems|Environmental|Cobus Van Deventer|Darren Van Rooyen|Infrastructure|Power|Waste|Water|Pipe|Pipelines|Valves
Construction|Engineering||Bitumen|Building|Concrete|Contractor|Copper|Design|Fire|Health|Installation|Lighting|Pipe|Pipelines|Pipes|PROJECT|Projects|Road|Safety|SECURITY|SSI|System|Systems|transport|Waste|Water||Equipment|Pipes|Steel|Systems|Environmental|Infrastructure|Power|Waste|Water|Pipe|Pipelines|Valves
construction|durban|engineering|natal|pietermaritzburg|bitumen|building|concrete|contractor|copper|design|fire|health|installation|lighting|pipe-company|pipelines-company|pipes|project|projects|road|safety|security|ssi|system|systems-company|transport|waste-company|water-company|ballito-pipeline|ed4-pipeline|estcourt-prison|ngwelezane-hospital-facility|equipment|fire-prevention-systems|hospital-site|kitchen-equipment|medical-gas|pipes-industry-term|steel|systems|environmental|cobus-van-deventer|darren-van-rooyen|infrastructure|power|waste|water|pipe|pipelines|valves
© Reuse this



Engineering and environmental consultancy SSI is undertaking a number of infrastructure upgrades in KwaZulu-Natal (KZN), including structural and building infrastructure upgrades at the Ngwelezane and Empangeni provincial hospitals and the Estcourt prison.

The R7-million Empangeni Hospital Project was awarded to SSI in September 2003 by the KwaZulu-Natal Public Works Department and includes work at both the Empangeni and Ngwelezane hospitals.

The overall project is scheduled for completion in December 2013.

The main contract is a four-storey exten- sion to the existing Empangeni hospital building, which is currently under construction, with 20% already complete.

The extension of the Empangeni provincial hospital accounts for 60% of the total project scope and involves the complete upgrade of the existing hospital, including a 200-bed extension, essentially doubling the hospital’s size, says SSI sector area manager Cobus van Deventer.

The project scope for the remaining work at the Empangeni provincial hospital site entails the replacement of the cold-water piping with copper piping, as well as the chillers; the upgrade of the nursery and the new-mothers lodge, all of which have been completed.

Upgrades to the existing building include work at the antiretroviral clinic; the corridor, kitchen, laundry and store areas; the nurses residences; the security and transport building; the workshop; and the refuse and medical waste areas.

A paediatric centre is being added onto the existing hospital and is 20% complete, says Van Deventer.

Meanwhile, the project scope at the Ngwelezane hospital site includes chiller replacement, corridor upgrades and exten- sions to the trauma and casualty depart- ments, all of which have been completed.

Upgrades were also undertaken at the mortuary, the workshops, the nurses college, the transport facility and the clinical engineering offices of the existing hospital.

Further, two new staff residences have been built, as well as a psychiatric ward, a psychiatric outpatient clinic and a therapy department.

The existing wards were demolished and replaced with new 72-bed wards.

Future work at the hospital will include the construction of a new 72-bed ward, a theatre block, an administation block and upgrading of the existing kitchen and laundry areas.

An additional project awarded to SSI by the KwaZulu-Natal Public Works Department is the R2.3-million upgrade of the Estcourt Prison.

Van Deventer reports that the site was handed over at the end of May, following the tender process and contractor appointment.

The scope of the project, which is scheduled for completion in July 2013, comprises the complete electrical design and installation, including reticulation; power; lighting and closed-circuit television, an intercom system and wireways for telephones.

It also includes heating, ventilation and air conditioning; refrigeration; fire prevention systems; kitchen equipment; medical gas; and a hot water plant.

SSI is responsible for submitting a progress report to the KwaZulu-Natal Depart- ment of Public Works, as well as the part-time contract administration and site supervision.

Water Infrastructure
SSI is also involved in water infrastructure upgrades in KZN, including the augmentation of the Hazelmere to Ballito pipeline, the ED2–ED4 pipeline and the ED4 to Umlaas road pipeline.

These bulk water infrastructure upgrades are being undertaken in response to the increasing water demands of the eThekwini municipality and the Durban and Pieter- maritzburg areas.

The latest pipeline upgrade is the 13-km-long ED4 to Umlaas road pipeline, which was awarded to onshore pipeline rehabilitator Esorfranki Pipelines, in April and is scheduled for completion in January 2014.

This upgrade forms part of the so-called existing ’61 Pipeline, which conveys potable water from the Midmar water treatment works (WTW) to Pietermaritzburg and Durban.

SSI water engineer Darren van Rooyen explains that the duplication of the ’61 Pipeline will be done in stages, with a second pipeline system being installed parallel to the existing system.

“The first stage consists of the pipeline from ED2 to ED4, while the second stage consists of the pipeline from ED4 to Umlaas road – with a simultaneous project to supply bulk potable water to Richmond.”

Umgeni Water contracted Esorfranki Pipelines as the contractor for both projects.

Subcontractors include PPT, which was reponsible for the cathodic protection; subconsultancy JCM Surveys, which conducted engineering surveys; and Intervention Systems, which is the health and safety agent on the project.

The R52-million ED2–ED4 pipeline comprises a 3.8 km 1 300-mm-diameter pipe with 40 bar-rated valves, which was recently completed.
The next stage, the R196-million ED4 to Umlaas road pipeline comprises a 13 km 1 100-mm-diameter pipe with PN 40- and PN 25-rated valves.

Both pipelines are continuously welded steel pipes with epoxy linings and bitumen coatings, notes Van Rooyen.

The ED4 to Umlaas road pipeline crosses under the N3 in a jacked sleeve with a 15-m-high vertical access shaft on the northern side.

Van Rooyen says both pipelines include offtakes and cross connections with the existing ’61 Pipeline.

He adds that a significant challenge during the ED2–ED4 project was the tie-in of the new pipeline to the existing ’61 Pipeline.

“The amount of work required on such large-diameter pipes and fittings is [extensive considering] the short shutdown periods allowed. To mitigate a water shortage to consumers in Edendale and eThekwini, only short shutdown periods were allowed,” explains Van Rooyen.
SSI was able to overcome this challenge by conducting the tie-ins in smaller, more manageable stages than originally planned, to reduce downtime.

“The design of the three projects was carried out by SSI under one appointment to handle all the complexities of the inter- connected hydraulic and operational requirements, states Van Rooyen.

SSI is also involved in the R52-million Hazelmere to Ballito pipeline project, which will transport water from the Hazelmere WTW to the La Mercy bifurcation point.

“The project entails the supply and laying of 10.8 km of 700-mm-diameter continuously welded steel pipeline with a cement mortar lining and a polyurethane coating by the main project contractor, Icon Construction,” says Van Rooyen.

SSI is responsible for providing the detailed design, water hammer analyses, preparation of construction drawings, tender documentation and reporting, construction management and construction monitoring, as well as the commissioning and handover to the client.

Phase 1 of the pipeline was designed and commissioned by SSI in 1995, while the detailed design of Phase 2 was awarded in August 2009.

Phase 2 is about 30% complete.

“Umgeni Water’s target date for completion is November, in line with peak water demand, owing to the influx of holidaymakers to Ballito,” states Van Rooyen.

Minor rehabilitation and concrete work on the pipeline will be completed by March 2013.

An area of difficulty during the project was the stringent environmental conditions set by the Dube TradePort (DTP) – an international airport and trade development in KZN – to accommodate a future road to the DTP, which would cross the pipeline serviture and require SSI to make late changes to accommodate this.

To overcome these difficulties, an agreement between the environmental control officers of both Umgeni Water and DTP was reached to reallocate a portion of DTP’s offset wetland to accommodate the pipeline.

Edited by: Chanel de Bruyn
Creamer Media Senior Deputy Editor Online
© Reuse this Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Construction News
Updated 7 hours ago JSE-listed Tower Property Fund has acquired the Link Hills Shopping Centre, in Waterfall, KwaZulu-Natal for R160.9-million from The Sabre Trust and Matlu Family Trust. The shopping centre, on Inanda Road, was situated in an upper-high-growth residential area, next to...
While a healthy appetite for investment in government’s infrastructure development programme existed among international and domestic providers of capital, policy coherence, a clear roll-out strategy and a champion in government were critical to triggering this...
Under the auspices of the World Economic Forum (WEF) on Africa, being held in Cape Town from June 3 to 5, South Africa will reiterate its stance that it is open for business, showcasing what it has to offer other countries and global business. The event, which would...
More
 
 
Latest News
Updated 7 hours ago All grades of petrol will increase by 47c/ℓ on Wednesday, the Department of Energy announced on Friday. The reef price for unleaded 93 and LRP petrol was currently standing at R12.61/ℓ, while unleaded 95 cost R12.89/ℓ.
Updated 7 hours ago JSE-listed Tower Property Fund has acquired the Link Hills Shopping Centre, in Waterfall, KwaZulu-Natal for R160.9-million from The Sabre Trust and Matlu Family Trust. The shopping centre, on Inanda Road, was situated in an upper-high-growth residential area, next to...
Updated 7 hours ago South Africa recorded a trade deficit of R2.51-billion ($207-million) in April from a revised shortfall of R9-million in March, data from the revenue agency showed on Friday. Exports fell by 7.5% to R84-billion, while imports were down 4.8% to R86.5-billion on a...
More
 
 
Recent Research Reports
Steel 2015: A review of South Africa's steel sector (PDF Report)
Creamer Media’s Steel 2015 report provides an overview of the key developments in the global steel industry and particularly of South Africa’s steel sector over the past year, including details of production and consumption, as well as the country's primary carbon...
Projects in Progress 2015 - First Edition (PDF Report)
In fact, this edition of Creamer Media’s Projects in Progress 2015 supplement tracks developments taking place under the Renewable Energy Independent Power Producer Procurement Programme, which has had four bidding rounds. It appears to remain a shining light on the...
Electricity 2015: A review of South Africa's electricity sector (PDF Report)
Creamer Media’s Electricity 2015 report provides an overview of State-owned power utility Eskom and independent power producers, as well as electricity planning, transmission, distribution and the theft thereof, besides other issues.
Construction 2015: A review of South Africa’s construction sector (PDF Report)
Creamer Media’s Construction 2015 Report examines South Africa’s construction industry over the past 12 months. The report provides insight into the business environment; the key participants in the sector; local construction demand; geographic diversification;...
Liquid Fuels 2014 - A review of South Africa's Liquid Fuels sector (PDF Report)
Creamer Media’s Liquid Fuels 2014 Report examines these issues, focusing on the business environment, oil and gas exploration, the country’s feedstock supplies, the development of South Africa’s biofuels industry, fuel pricing, competition in the sector, the...
Water 2014: A review of South Africa's water sector (PDF Report)
Creamer Media’s Water 2014 report considers the aforementioned issues, not only in the South African context, but also in the African and global context, and examines the issues of water and sanitation, water quality and the demand for water, among others.
 
 
 
 
 
This Week's Magazine
While strongly welcoming the promulgation of the new Part 101 of South Africa’s civil aviation regulations, governing the commercial operation of civil remotely piloted aircraft (RPAs) in South Africa, the Commercial Unmanned Aircraft Association of Southern Africa...
LSM Distributors has contracted engineering consultancy WSP | Parsons Brinckerhoff Africa to undertake the R100-million restoration of the 54-year-old Kyalami racetrack, situated in Midrand. The restoration will assist in re-establishing it as a venue for...
South African Defence Minister Nosiviwe Mapisa-Nqakula has expressed the hope that the defence budget will be significantly increased over the next five years. She did so while addressing the media in her recent budget vote media briefing. The 2015/2016 defence...
The African Development Bank (AfDB) has been an implementing agency for the Global Environment Facility (GEF) since 2008. The relatively young portfolio has 28 projects over 30 countries on the continent according to the 2014 AfDB and GEF annual report released...
PAUL SPEAR Training and development should be an integral and proportionate part of the long-term strategy of all companies, regardless of their size
Investment in South African youth through apprenticeships and learnerships will not only create direct benefits for businesses but will also contribute significantly to job creation and socioeconomic transformation in the country.
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96