https://www.engineeringnews.co.za

Kusile power plant project, South Africa

4th August 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kusile power plant project.

Location
Mpumalanga, South Africa.

Client
State-owned power utility Eskom.

Project Description
The Kusile power station project, near the existing Kendal power station, in the Nkangala district of Mpumalanga, will comprise six units, each rated at an 800 MW installed capacity for a total capacity of 4 800 MW. Once completed, Kusile will be the fourth-largest coal-fired power station in the world.

The Kusile project will include a power station precinct, power station buildings, administrative buildings (control buildings and buildings for medical and security purposes), roads and a high-voltage yard.

The associated infrastructure will include a coal stockyard, coal and ash conveyors, temporary and permanent water-supply pipelines, temporary electricity supply during construction, water and wastewater treatment facilities, ash disposal systems, a railway line, limestone offloading facilities, access roads (including haul roads) and dams for water storage, as well as a railway siding and railway line to transport the limestone supply (sorbent).

The power station will be the first in South Africa to install flue-gas desulphurisation (FGD) – a state-of-the-art technology used to remove oxides of sulphur, such as sulphur dioxide, from exhaust flue gases in power plants that burn coal or oil.

This technology abates atmospheric emissions, in line with current international practice, to ensure compliance with air-quality standards, especially since the power station is located in a priority air-shed area.

The FGD plant is a totally integrated chemical plant using limestone as feedstock and producing gypsum as a by-product.

Each supercritical tower boiler will be about 115 m high. The air-cooled condensers will be constructed on and supported by twenty 60-m-high concrete columns.

Jobs to be Created
A comprehensive exit and outreach strategy, which plans to gradually upskill and release local labour to the job market, has been formalised in partnership with key stakeholders. This allows for project stability in the face of the gradual demobilisation of workers once milestones are achieved. It will further enable the project to mitigate the risk of local community disruptions.

Value
The cumulative cost incurred on the project as at March 31, 2017, was
R112.4-billion (March 2016 – R95.1-billion) against the revised budget of R161.4-billion. All amounts exclude capitalised borrowing costs.

Duration
Eskom has indicated that the first synchronisation of Kusile Unit 1 is expected to enter commercial operation only in the second half of 2018.

Latest Developments
Since the synchronisation of Unit 1 on December 26, 2016, the unit achieved full load of 800 MW on March 10, 2017. The focus is on optimising the unit to achieve commercial operation, which is expected within six to nine months after synchronisation.

The project completed hydrotesting of the Unit 2 boiler in October 2016. After achieving boiler registration ahead of schedule in March 2017, Unit 2 is focused on insulation and cladding, mechanical construction and cabling, as well as control and instrumentation (C&I) installation.

To ensure the boiler guarantees remain in effect, more stringent coal specifications have been instituted for the commissioning period at Kusile.

A request for proposals for the coal procurement was issued in April 2017, covering the commissioning period and the life of the station. Meanwhile, Eskom has signed a long-term contract for the supply of limestone for Kusile’s FGD plant, which will reduce sulphur dioxide emissions.

During March 2017, the distributed control system was powered on for the air condensate cooling system, the condensate polishing plant and the FGD system, supporting the on-site integration testing. The project has also mechanically completed and commissioned the first wet FGD on the African continent.

The project continues to closely manage contractor productivity. Eskom has reported that performance is improving, most notably through milestones being achieved ahead of the business case dates. The new C&I contractor, which mobilised in 2015, has delivered the engineering and manufacturing of equipment within tight schedules to ensure integration with other packages.

Key Contracts and Suppliers
Eskom, in partnership with Black & Veatch International (project management and engineering services); Ninham Shand Consulting Services (environmental-impact assessment, geotechnical investigation and traffic impact); AirShed Planning Professionals (air-quality impact); Jongens Keet Associates (noise impact); Strategic Environmental Focus, or SEF (visual impacts); Makecha Development Association (impacts on terrestrial fauna and flora); Golder Associates, through Ecosun (aquatic-ecosystem impact); Groundwater Consulting Services (groundwater impact); Ilitha Riscom (risk assessment); Northern Flagship Institution (archaeological impact); University of the Free State (impacts on agricultural potential); Urban-Econ (socioeconomic impacts); Seaton Thomson & Associates (planning implications); Mark Wood Environmental Consultants (process review); Mitsubishi Hitachi Power Systems Africa, or MHPSA, a subsidiary of Hitachi Power Europe, or HPE (boiler contract); Actom, formerly Alstom S&E Africa (main turbine area); ABB SA(C&I, including supply of medium-voltage switchgear and associated equipment); Mikropul, subcontracted by Alstom (axial-flow fans and auxiliary equipment for the turbine halls' ventilation); Murray & Roberts, or M&R (boiler construction contract); Roshcon, a subsidiary of Eskom (enabling civils, terracing construction and site services); Concrete Finishing Equipment (dust filters and silo and environmental safety); Kusile Civil Works, or KCW, Joint Venture (JV), comprising Stefanutti Stocks, Basil Read, Group Five and WBHO Construction (main civil works); Siemens (generator transformers and electrical and auxiliary power); EsorFranki Geotechnical, formerly Franki Africa, and Stefanutti Stocks Geotechnical JV, under a subcontract to KCW JV (piling works for the turbine, boiler and air-cooled condensers); Concor Karrena JV (construction of chimney shells/structures); Tubular (engineering, supply and installation of FGD system); DSE Structural Engineers & Contractors, subcontracted by Genrec Engineering (fabrication of steel columns for boilers 1 to 3); Steel Services Direct, or SSD (steel, pipes and wax plants); GB Bearings (supplier of HSR horizontal bearing assemblies and profile bore bearings); Sulzer Pumps South Africa, subcontracted by Actom (supply of booster and boiler feed pumps); Steloy Castings, subcontracted by Sulzer Pumps South Africa (supply of chrome steel components for the pumps); Clyde Bergemann Power Group, subcontracted by MHPSA (supplier of sootblowers for boilers); Clyde Bergemann Africa (fly ash handling system); PD Naidoo & Associates, or PDNA, Industrial Projects (main water and wastewater treatment contractor); GE Water Engineered Systems, subcontracted by PDNA Industrial Projects (advanced water and wastewater treatment equipment); Bateman Africa (coal stockyard and terrace materials handling systems); Lesedi Nuclear Services (procurement and supply of the balance of plant equipment); Grinaker-LTA Metals & Minerals (supply and erection of piping, steelwork and free-issue chemicals); US Export-Import Bank, or Ex-Im Bank (loan finance); TBD (railroad construction and combustion water terrace construction phases 1 and 2); Zest WEG Group (auxiliary transformers); Aberdare Cables, a Powertech company within the JSE-listed Altron Group (cables); Konecranes (heavy-duty cranes); Energy Engineered Products (supply of valves) and Turnmill Proquip Engineering (material for boiler ducting).

On Budget and on Time?
The project has had massive cost overruns and delays and its completion date has been postponed from 2017 to 2022.

Contact Details for Project Information
Eskom media desk, tel +27 11 800 3304/3343/3378, cell +27 82 805 7278, fax +27 86 664 7699 or email mediadesk@eskom.co.za.
Kusile power station communication department – media relations, tel +27 13 699 7405/ 7377 or email kusilelimelight@eskom.co.za.
 
 

Edited by Creamer Media Reporter

Comments

Array

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.087 0.139s - 159pq - 2rq
Subscribe Now