Kibo, Sepco agree development refund for MCPP
JOHANNESBURG (miningweekly.com) – Aim- and AltX-listed Kibo Mining and Chinese firm Sepco III have agreed that $10.94-million is a fair reflection of the Mbeya coal-to-power project (MCPP) development costs over the past four years.
Upon the financial close of the MCPP, Sepco III will refund Kibo some 50%, or $5.49-million, of the final development cost incurred as part of the terms of the redefined agreement for the progression of the Tanzania-based project.
The agreement, which was signed in August, allowed Sepco III to earn the right to become the sole bidder for the engineering, procurement and construction (EPC) contract to build the power plant component of MCPP.
“We are very pleased with the outcome of this week's meetings in China with Sepco III and General Electric (GE), as well as our MCPP advisers Tractebel Engineering.
“We are particularly pleased that we have reached agreement on the MCPP development costs and the balance of funds refundable to the company,” said Kibo CEO Louis Coetzee.
Kibo already received an advance of $1.8-million, with the total outstanding amount payable to Kibo now $3.67-million.
Kibo, Sepco III, Tractebel and GE have made significant progress towards finalising the EPC and original-equipment manufacturer (OEM) bid proposals for the power component of the MCPP.
“Progress in relation to the finalisation of the EPC and OEM bid proposals also exceeded our expectations and marks another major step forward in moving the MCPP towards financial close,” Coetzee said.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation