Kariba dam rehabilitation project, Zambia

13th May 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Kariba dam rehabilitation project, Zambia.

Client
Zambezi River Authority (ZRA), a joint venture between Zambia and Zimbabwe, the African Development Bank (AfDB), the European Union, Sweden and the World Bank.

Project Description
After 50 years of serving the Southern Africa region, the Kariba dam requires a series of rehabilitation works for its continued safe operation.

Failure to invest in the timely rehabilitation of the dam will result in the gradual degradation of key safety features associated with the structure to a level that is not acceptable in accordance with international standards.

These works include:
• the design, fabrication and installation of an emergency gate and a new gantry to prevent the uncontrolled loss of water in the event of floodgate failure, which will result in water levels dropping to below the minimum operating levels and interrupting power production;
• the refurbishment of the upstream stop-beam guides and the replacement of secondary concrete to prevent failure during the operation of stop-beams; and
• the reshaping of the plunge pool downstream of the dam to limit scouring and erosion that could potentially undermine the dam foundations, leading to dam failure.
The Kariba dam is one of the world’s largest hydro dams, generating more than 1 300 MW of hydropower. The dam’s wall, which is 128 m high, straddles Zambia and Zimbabwe. Should it collapse, flooding from the Zambezi river could affect parts of Zambia, Zimbabwe, Malawi and Mozambique, affecting millions of people.

Value
The cost of the Kariba dam rehabilitation is estimated at $200-million, based on a series of feasibility and design studies completed in July 2012 by consultants appointed by the ZRA.

Duration
The Kariba dam faces collapse if not repaired in three years.

Latest Developments
Zambia and Zimbabwe plan to start repairs to Kariba dam in the first quarter of next year without affecting hydropower supply in either country, which is generated from the reservoir, a senior World Bank official has said.

Key Contracts and Suppliers
AfDB (loan finance).

On Budget and on Time?
Not stated.

Contact Details for Project Information
ZRA, tel +260 1 228401, fax +260 1 227498 or email zaraho@coppernet.zm.
AfDB senior power engineer Elizabeth Muguti, email e.muguti@afdb.org.

Edited by Creamer Media Reporter

Comments

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
Magni SA
Magni SA

Magni SA is committed to developing the safest Telehandlers available to our customers for underground and surface mining, construction, forestry,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.329 0.386s - 159pq - 2rq
Subscribe Now