Inpex sticks to Ichthys start-up date despite power project blow

27th January 2017

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Energy major Inpex has brushed off concerns about delays at its 8.9-million-tonne-a-year Ichthys liquefied natural gas (LNG) project, after project house UGL terminated its construction and commissioning contract of the combined cycle power plant (CCPP), in Darwin.

The termination of the contract is the result of a spat between UGL, which was recently bought by Cimic, and main contractor JKC Australia, reportedly over project delays and cost blow-outs. The cancellation of the contract resulted in 300 people losing their jobs.

“This is a matter between JKC and its subcontractors,” Inpex said in a statement to Mining Weekly Online.

“The Ichthys LNG project is 90% complete as at September 2016. Outstanding works to complete the remaining CCPP scopes are not on the critical path for the start of production. Our target remains to start production in the third quarter of 2017,” the company said.

JKC for its part said that it was disappointed that UGL had taken this action, saying that construction of the CCPP had been temporarily halted.

“The CCPP is approximately 89% complete, and JKC remains committed to delivering its scope of work and the overall Ichthys project onshore LNG facilities,” the contractor said.

Commercial analyst Wood Mackenzie (Woodmac) this week foreshadowed delays in the start-ups of some major LNG projects scheduled for completion in 2017, including Ichthys, the Gorgon Train 3, Wheatsone and Prelude LNG projects.

Woodmac said in a memo that it was inevitable that some of the major LNG projects would suffer further schedule slippages.

“In the Carnarvon basin, both Chevron's $60-billion Gorgon and $36-billion Wheatstone projects have suffered cost and schedule overruns. In the Browse basin, Inpex's $40-billion Ichthys project and Shell's pioneering $14-billion Prelude floating LNG project have also suffered setbacks.”

The analyst noted that construction challenges, competition for resources between the Ichthys and Prelude projects, and financial challenges facing the yard contractor, have contributed to delays in these projects.

“Both projects' operators aim to move the facilities from the yards in 2017 before cyclone season begins around the fourth quarter. However, both facilities are likely to face a lengthy commissioning process, which could push first LNG cargoes into 2018. Any carryover work left to be done after leaving the yards will result in additional costs and delays,” Woodmac said.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.074 0.129s - 156pq - 2rq
Subscribe Now