https://www.engineeringnews.co.za

Ingula pumped-storage scheme project, South Africa

Bedford dam at Ingula

Bedford dam at Ingula

24th February 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Ingula pumped-storage scheme project.

Location
The project is located on the border between the Free State and KwaZulu-Natal provinces, South Africa.

Client
Eskom.

Project Description
The Ingula pumped-storage scheme, located within the Little Drakensberg mountain range, 23 km north-east of Van Reenen’s Pass, will comprise an upper dam (Bedford) and a lower dam (Braamhoek). The upper reservoir site is located in the Free State and the lower reservoir site in KwaZulu-Natal. The escarpment forms the border between the two provinces.

The distance between the upper and lower reservoirs will be 4.6 km, with an elevation difference of about 470 m.

The reservoirs will be connected through underground waterways and the underground powerhouse complex, which will house four pump turbines with a total capacity of 1 332 MW, a machine hall, a transformer hall and associated tunnels, shafts and caverns.

The twin headrace waterways, consisting of concrete and steel-lined headrace tunnels, pressure tunnels and shafts, will link the upper reservoir with the pump turbines.

The draft tubes, concrete-lined surge shafts and concrete-lined tailrace tunnel will connect the pump turbines to the lower reservoir.

The upper reservoir is a concrete-faced rockfill embankment dam, 41 m high, with a total capacity of 22.4-million cubic metres and an active water storage volume of 19.2-million cubic metres. The 39-m-high lower dam comprises roller-compacted concrete, with a total capacity of 26.3-million cubic metres, and an active storage volume of 21.9-million cubic metres.

The scheme will be operated on a weekly cycle and will have an overall cycle efficiency of 78%.

The plant represents 16 hours of storage, or 21 000 MWh, and is the fourteenth-largest pumped-storage scheme in the world.

Jobs to be Created
Not stated.

Value
Eskom recently reported cumulative project costs of R26.8-billion against a revised budget of R25.9-billion and an initial budget of R8.9-billion.

Duration
Construction at Ingula started in 2006, but there were major challenges, including the death of six construction workers in October 2013.

This resulted in the closure of the site for a number of months, delaying project completion.

Ingula’s Unit 4 was the first to enter into commercial operation on June 10, 2016. The second unit of the scheme entered into commercial operation on August 22, 2016.

Unit 1 entered into commercial operation on August 30, 2016.

Unit 3 entered commercial operation at the end of January.

Construction of the lower waterways was completed on December 13, 2015, and filled with water from the lower dam.

Latest Developments
Unit 3 of the Ingula pumped-storage scheme has been brought into commercial operation, adding 333 MW to the South African power grid.

All four units at Ingula are now commercial and produce a combined 1 332 MW.

“The commercial operation of Unit 3 completes the Ingula pumped-storage scheme project.

This will further strengthen security of power supply to South African homes and businesses,” Eskom acting CEO Matshela Koko has said.

Unit 4 went into commercial operation in June 2016, while units 1 and 2 went into commercial operation in August 2016.

Key Contracts and Suppliers
Braamhoek Consultants Joint Venture (JV), or BCJV, consisting of Gibb, Knight Piésold and SSI (civil, mechanical and electrical engineering, detailed design, tender documentation, design monitoring and construction supervision); Murray & Roberts (exploratory tunnel); Grinaker-LTA (access roads); CMI JV, comprising CMC di Ravenna, PG Mavundla and Salini Impregilo (underground civil works); Royal HaskoningDHV (design and construction of upper and lower dams, access roads, visitors centre, administration building and main underground works); Afriscan (water supply, sewage treatment, small access roads and construction of temporary Eskom offices); B&E Quanza Group (aggregate quarry); Acer Africa (environmental consultants); Braamhoek Dam JV (BDJV), comprising Concor Roads & Earthworks, Wilson Bayly Holmes-Ovcon, Edwin Construction and Silver Rock (dam contract); Voith Siemens Hydro Power Generation (main generating plant); Deutsche Bank (R1-billion loan); Voith (mechanical auxiliary plant, turbines and generators); ABB (electrical balance of plant); NCC Environmental Services (independent environmental control officer services); Konecranes (heavy-duty cranes); Letacla (fibre-optic communications); Siemens (generator transformers); Roshcon (line integration – main contractor); Optipower and Babcock Ntuthuko (line integration – subcontractors); and CBI and Prysmian (supply and installation of 400 kV cables).

On Budget and on Time?
The project has materially overrun its budget and reported significant schedule slippages.

Contact Details for Project Information
Eskom media desk, tel +27 11 800 3304/3309/3343/3378, fax +27 11 800 3805 or email mediadesk@eskom.co.za.
Eskom senior project manager Avin Maharaj,
email Avin.Maharaj@eskom.co.za; or communications manager Mlungisi Shongwe, email mlungisi.shongwe@eskom.co.za.
Ingula Visitors Centre, tel +27 36 342 3122 or email fifi.meyer@eskom.co.za.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Alco-Safe
Alco-Safe

An unmanned breathalyser that is made to be tough and simple to use. Can be used in any environment for operator-free breathalyser testing.

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.088 0.139s - 159pq - 2rq
Subscribe Now