Hummingbird study shows solid case for hydropower use at Liberia project
JOHANNESBURG (miningweekly.com) – A recently completed prefeasibility study (PFS) at Liberia-focused miner Hummingbird Resources’ Dugbe gold project, has confirmed the viability of a range of options for hydroelectric power (HEP) plant use in supplying a sustainable source of power for Dugbe, as well as the south-east Liberian region.
The 14-month study also showed that hydropower could potentially reduce the 4.2-million-ounce project’s all-in sustaining costs.
CEO Dan Betts said that as the largest gold deposit in Liberia, with a $186-million net profit value at a $1 300/oz gold price, the company was keen to move the project forward to development.
“The delivery of the hydropower PFS is a tangible deliverable in this process. Power costs make up over a third of our total process operational expenditure (opex) and finding savings in this area will have positive implications for the project’s economics,” he added.
Hummingbird used estimates of $0.28c/kWh for rented diesel power in the PFS. “Taking the total capital expenditure and opex for the HEP plant, over the current 20-year mine life, gives you a theoretical cost of $0.05c/kWh.
“This number does not compare directly, since it does not include the impact of the financing cost of building the hydro plant, as it is not yet known how this will be done or by whom.
“However, assuming a suitable financing solution was found, this could have a materially positive impact on the economics of the Dugbe project. Therefore, we are now considering our next steps with our partners on the PFS,” Betts said.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation