https://www.engineeringnews.co.za
Coal|Energy|Power|Projects|Renewable Energy|transport
Coal|Energy|Power|Projects|Renewable Energy|transport
coal|energy|power|projects|renewable-energy|transport

High Court dismisses bid by coal transporters to interdict renewables projects

26th March 2019

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

A court application to have 20-year power purchase agreements (PPAs) signed between Eskom and 26 independent power producers (IPPs) in 2018 declare null and void has been dismissed with costs.

The legal challenge was initiated last year by the Coal Transporters Forum (CTF), a voluntary association made of 50 companies that transport coal to Eskom power stations. The respondents to the application included Eskom, the National Energy Regulator of South Africa (Nersa), Energy Minister Jeff Radebe and more than 30 IPPs.

The CTF asked the court to interdict the signing of the PPAs, which arose from Bid Window 4 of South Africa’s Renewable Energy Independent Power Producer Procurement Programme.

The PPAs were signed on April 4, 2018, following a three-year delay brought about by Eskom’s refusal, made public in 2016, to enter into new contracts with renewable energy IPPs, despite the fact that the projects had been legally procured by government in 2015.

In his March 26 ruling, High Court Judge Pieter Meyer said that the CTF’s contention that the projects had not received a generation licences from Nersa had no merit.

Meyer also dismissed the CTF’s contention that Eskom was not entitled to conclude the PPAs with the IPPs until the regulator had pronounced on several other issues, ranging from the tariffs agreed in the PPAs to the terms and conditions contained in the PPAs.

“All the parties in the know – the regulator, Eskom and the IPPs – testify that the regulator has taken the decisions in questions. CTF offer no evidence to the contrary,” the judgment reads.

“Finally, it bears mentioning that the process and procedure in challenging and setting aside an administrative action is by means of legality review proceedings, or review proceedings under the Promotion of Administrative Justice Act, and not proceedings wherein a party merely seeks that the contract concluded be set aside by a court of law or declared null and void,” Judge Meyer wrote.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.072 0.124s - 160pq - 2rq
Subscribe Now