https://www.engineeringnews.co.za

HFO plant’s commissioning process under way

HIGH FUEL OIL FACILITY he contract for the HFO storage facility design was was awarded to Energas in June 2016

SUCCESSFUL VENTURE Energas’s commissioned work was delivered on time and within budget

14th April 2017

By: Nadine James

Features Deputy Editor

     

Font size: - +

Specialised oil and gas equipment supplier Energas Technologies started the commissioning process last month for the heavy fuel oil (HFO) storage facility it specifically designed for multidisciplinary engineering firm DRA Global.

Energas’s scope for the project included the fabrication, inspection, testing, coating, preparation for transportation and delivery of the HFO facility to the Elandsfontein phosphate project site in the Western Cape, where the facility has been established.

Project specification included two 80 m3 tanks manufactured by Krugersdorp tank manufacturer Petrotank SA, as well as an offloading pump skid, and a pump and heating skid manufactured by specialised metal fabricators ERD Fabricators in Sasolburg.

DRA first contacted Energas in May last year. The contract for the HFO storage facility design – which included designs for the processing, mechanical, piping, electrical and instrumentation components of the facility – was awarded to Energas in June, with a contractual delivery date set for November 30 that same year.

Energas’s mandate inlcuded discharging HFO from the tanks using a dry-disconnect coupler. The HFO will be pumped into the storage tanks, with a separate pump skid pumping a portion of the HFO to a heater. The remaining HFO will be recirculated through the tanks to prevent oil build-up. If the oil in the tanks ever dropped in temperature, the control system would respond by recirculating the hot oil back into the tanks until the temperature reached appropriate levels.

The hot oil will be used to fuel the burners, which are used to dewater/dry the phosphate before it is conveyed to product handling. This is the last phase before it is loaded onto the trucks.

Energas delivered the completed skids to site, with all the equipment and piping on the skids preinstalled and tested at the fabricators. The team consisted of about 15 people that assisted in the fabrication of the structures and piping. The mechanical installation was handled by a team of just five people; three people were responsible for the electrical and instrumentation installation.

Breathing vents, also known as pressure-vacuum vents, were also installed on the tank to enable the tank to operate at atmospheric pressure.

Energas project engineer Marianne Lourens explains that breathing vents are always considered with fixed-volume tanks. “The tank holds a liquid that is transferred by either filling or emptying the tank. The movement of the liquid in and out of the tank will, respectively, decrease or increase the air volume above the liquid. This air volume is known as the vapour space.”

She notes that, when liquid is pumped into the tank, the vapour space decreases, so the gases compress and the tank pressure builds up. Thus, a breathing vent is required to allow the air to escape, thereby ensuring that the operating pressure of the tank is not exceeded.

Lourens illustrates the process of emptying the tank by comparing it to drinking from a plastic bottle: “If you keep your mouth over the opening, the volume decreases. The more liquid you drink, the higher the negative pressure, and eventually the bottle will contract. When you remove the nozzle from your mouth, air flow into the bottle is restored and the pressure in the bottle equalises.”

In the case of the tanks, the breathing vent is used to restrict thermal expansion of mediums, owing to temperature changes, she adds.

“A breathing vent was included to prevent the tank from rupturing or collapsing,” Lourens summarises.

“Energas’s commissioned work at the Elandsfontein phosphate project was delivered on time and within budget. The value of Energas’s contribution to the project is about R10-million,” she says.

The company was able to draw from its vast experience as it had to complete a similar project to this one, comprising a heater skid and heat exchanger for Sasol Oil’s HFO depot, in Pretoria West, earlier in the year.

Energas believes that it secured this phosphate project because of its ability to deliver the entire scope. Further, its access to experienced consultants and reputable suppliers was taken into consideration.

“The success of this project will definitely highlight our reputation for providing excellent service and on-time delivery, and more so since this is our first project for DRA Global. It also enabled us to gain more exposure to HFO applications and we would like to do more of these types of projects . . . ” Lourens says.

She notes that the main challenge of this project was the restricted timeline, as the long lead items had initially been scheduled to arrive in December last year; however, Energas managed to ship them by air instead of sea freight to reduce the delivery time.

Mining at the Elandsfontein site is expected to start later this year. Abut 1 100 people have been employed for the project’s construction phase, with almost 50% local employment, and more than 450 people will be employed as part of the Elandsfontein operational workforce.

Edited by Zandile Mavuso
Creamer Media Senior Deputy Editor: Features

Comments

Showroom

Aqs image
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.233 0.304s - 271pq - 2rq
Subscribe Now