Guajira transmission lines project, Colombia
Name of the Project
Guajira transmission lines project.
Location
La Guajira, Colombia.
Client
Elecnorte.
Project Description
The project involves the construction of two 110 kV transmission lines – one about 76.5 km long, between Riohacha and Maicao; and another about 62 km long, between Riohacha and Cuestecitas.
The lines will be double-circuit, although initially the wires will be installed to operate only one circuit, and will allow for a transmission line ring connecting the three substations of Cuestecitas, Riohacha and Maicao to close.
There will be 321 steel towers and 50 steel poles, the latter mainly installed in the 5.5 km stretch of the line crossing the City of Maicao before reaching the substation.
The project includes the refurbishment of the Riohacha, Maicao and Cuestecitas substations.
Potential Job Creation
The project is expected to require about 600 workers at the peak of construction, of whom up to 40% will be sourced locally. All the unskilled and semiskilled workers will be sourced locally. About 25 staff will be employed during the operations phase, in addition to the security personnel presence required to safeguard project infrastructure.
Value
The project is estimated at $116.7-million.
Duration
The project is expected to take nine months to complete.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Elecnorte, tel +571 6 40 32 95 or email info@elecnorte.com.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation