Group Five Kpone contract terminated, legal dispute resolution expected in early 2019

3rd December 2018

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

Construction company Group Five has been issued with a notice of termination of its Kpone gas and oil-fired combined cycle power plant project, in Ghana, by its client Cenpower.

In a statement issued late on Friday, Group Five denied Cenpower’s entitlement to terminate the contract, saying the purported notice of termination is wrongful and constitutes a repudiation of the contract.

Group Five, therefore, in turn, notified Cenpower that it accepted Cenpower’s repudiation of the contract and accordingly issued a notice of termination to the

client, effectively terminating the contract with immediate effect.

Cenpower’s action followed after it, in November, issued a demand for $62.7-million to be paid by Group Five for contract delay damages at Kpone.

Group Five had applied to the High Court of Johannesburg to interdict Cenpower’s demand, but the application was dismissed.

The judge confirmed, at the time, that the contractual claims and disputes presented are complex, but as the bond represents a standalone financial instrument separate to the contract, it had to be independently assessed.

His ruling therefore did not address the contract, the contractual claims process or provide judgment on whether the contractual claims or parties have merit, Group Five said on Friday.

As outlined in Group Five’s annual financial statements, stakeholders’ attention has in the past been drawn to the contingent risk of claims on guarantees relating to the the Kpone contract of a performance bond of $62.3-million, a retention bond of $41.5-million and an advance payment bond of $2.6-million.

The construction company has previously indicated that, notwithstanding any further potential delays to the project or to the dispute resolution process, the gross maximum delay damages exposure remained capped at $62.5-million.

Following Cenpower’s payment demand in November, Cenpower received payment for the maximum amount of the delay damages, Group Five said on Friday.

The group continues to challenge the liability for delay damages, with liability to be independently determined through a dispute resolution mechanism set out in the contract.

Group Five outlined that the remaining value of on-demand bonds in issue, from financial institutions to Cenpower, post the settlement of the $62.7-million, amounted to $43.8-million.

In terms of the contractual process, Group Five will continue to progress its contractual rights and entitlements for payment of all amounts due and owing under the contract, including the recovery of delay damages (paid in terms of the guarantees) and claims against the client.

This includes a submission to the International Chamber of Commerce, in Paris, for the resolution of a dispute through expert proceedings, which is a considerably quicker process for resolution of disputes than arbitration. Good progress has been made in this regard, with the first dispute resolutions expected to be completed in early 2019.

The termination also enabled the company to proceed to dispute resolution, in accordance with the contract, for payment of all amounts due and owing to Group Five under the contract.

Group Five’s legal counsel remained of the considered view that the claims have merit and that the company has a reasonable prospect of recovering payment from the client.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
Updated 5 hours ago By: Martin Creamer
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.09 0.149s - 151pq - 2rq
Subscribe Now