http://www.engineeringnews.co.za
  SEARCH
Login
R/€ = 17.12Change: -0.11
R/$ = 15.01Change: -0.10
Au 1278.71 $/ozChange: 1.89
Pt 1063.00 $/ozChange: 1.50
 
 
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?








Start
 
End
 
 
And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
 
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters About Us
 
 
 
RSS Feed
Article   Comments   Other News   Research   Magazine  
 
 
Dec 12, 2008

Global economic slowdown not a concern for Gautrain project

Back
Jack van der Merwe talking about the future operating schedule of the Gautrain
 
 
 
Construction|Africa|Building|Civils|Concrete|Cutting|Design|Engineering|Flow|Gautrain|PROJECT|Property Development|Road|System|Technology|Tunnelling|Water|Africa|Gautrain|Flow|Property Development|Tunnelling|Gautrain|Drilling|Gautrain
Construction|Africa|Building|Civils|Concrete|Cutting|Design|Engineering|Flow|Gautrain|PROJECT|Property Development|Road|System|Technology|Tunnelling|Water|Africa|Gautrain|Flow|Property Development|Tunnelling|Gautrain|Drilling|Gautrain
construction|africa-company|building|civils|concrete|cutting|design|engineering|flow-company|gautrain-company|project|property-development-company|road|system|technology|tunnelling-company|water|africa|gautrain-facility|flow-industry-term|property-development|tunnelling|gautrain-organization|drilling|gautrain



The current global economic slowdown will not significantly influence the budget of the Gautrain project, assures Gautrain project leader Jack van der Merwe.

Van der Merwe explains that the contract for the public-private partnership (PPP), which is a joint venture between the Gauteng provincial government and Bombela Concession Company, which consists of Bombardier Transportation, Bouygues Travaux Public, Murray & Roberts and the Strategic Partners Group as shareholders, is based on a fixed price, scope and time contract, securing the project against fluctuations in the economy. He notes, however that other factors could increase the price tag of the project.

He says that when there is a variation order, for instance, if the project is extended or a deviation on the project is required, the project price will increase. Also, if the consumer price index is higher than initially predicted and the inflation cost is higher than the amount predicted, the province will have to pay the difference. Van der Merwe says that any claims from contractors will also increase the project price; however, no claims have been reported to date.

Another aspect that has to be accounted for, is the exchange rate. All the Gautrain certificates are paid in rands, pounds and euros. Van der Merwe assures that all foreign currencies have been hedged, and consequently, the volatility of the market does not hold any real danger. The project works on a year-to-year basis, which means what is spent in excess one year, can be balanced with the expenditure of the following year. He says the budget is a challenge that every construction site in South Africa faces.

Carriage Construction

As part of the socioeconomic development component of the project 20 of the Gautrain train sets are being assembled at Union Carriage Works in Nigel, in an effort to create jobs and develop local skills.

Van der Merwe says that four complete train sets were manufactured and assembled in London. The remaining train sets were built in segments, and transported to South Africa by sea freight. In total, 24 train sets will be in use on the Gautrain project.

One train set is four carriages long. A static test is carried out on each carriage; the carriage is then linked into a train set, followed by another static test and lastly, a dynamic test, where the train set will run on the tracks at the depot.

Van der Merwe says that dynamic tests will be conducted in February next year. "By February 2009, the trains will be running on the test track. The test track will run from the depot site to the Midrand station, covering a 7-km stretch of track," he says.

All the tracks in the depot have been laid and contractors are now laying the tracks on the main lines. Van der Merwe says that to date, the production on site has mainly concentrated on the civils side of the project, however, significant progress is now being seen on the mechanical and electrical side of the project.

The assembly of the train sets will be completed around the last two quarters of 2009.

Tunnelling Trough

Van der Merwe reports that 9 km, out of the 15 km of tunnelling necessary for the Gautrain project, has already been completed. The tunnels are constructed by means of drilling-and-blasting, cutting-and-covering and by boring through underground sections using the tunnel-boring machine (TBM).

The bulk of the tunnelling is done through drilling-and-blasting. Van der Merwe explains that with the drill-and-blast method a section is primed and filled with dynamite. With every blast, a 5-m segment of the tunnel is created. It takes about 12 hours to repeat the process, and currently, the production rate of the tunnelling stands at about 10 m/d, says Van der Merwe.

He notes that about 12 km of tunnelling has to be completed by drilling-and-blasting. Bombela opened as many faces to the tunnels as possible to achieve this objective quicker and more efficiently

The longest continuous tunnel is the 6-km section between the Marlboro station and the Sandton station, which is why an extra face was opened at Mushroom Farm park. In September this year the connection between the Marlboro portal and Mushroom Farm park was opened, forming a continuous tunnel of just over 4,2 km long.

In instances where the tunnel is shallow the cut-and-cover method is used. This method involves the excavation of a large open cavern in the ground, which is covered up again after the completion of the structure. The Gautrain project uses the cut-and-cover method at its underground stations at Park station, the Rosebank station and the Sandton station, as well as for structures at the Marlboro portal.

Van der Merwe says the cut-and-cover process firstly involves the excavation of a shallow trench. Drilling-and-blasting is used to excavate rock. While the rock underneath the highway is being excavated, lateral supporting pillars are put in place to stabilise the highway and prevent the trench from collapsing.

Traffic flow continues undisturbed on the temporary deviations, while excavation continues. Once the underpass structure has been completed, the surface is reinstated or roofed over. This process is a significant engineering challenge that has been achieved through careful design and construction techniques.

Cut-and-cover tunnels at shallow depth have been used worldwide for centuries. New technology now allows the use of cut-and-cover methods at increasing depths and very close to, or even under, existing tall buildings.

Meanwhile, a 3-km portion of the tunnel between the Park station and the Rosebank station is being excavated using the high-technology TBM.

The R300-million TBM was designed and custom-built by Herrenknecht, in Germany, to cope with the complex underground geological conditions south of Rosebank. Geology in this area features a high-water table, as well as varying degrees of hard rock, sand, and soft, waterlogged soil.

At the front of the TBM machine is a rotating cutting wheel, which excavates the ground. Behind this wheel is a chamber where the excavated material accumulates, before being extracted by a pressure relief discharge system called a screw conveyor.

Excavated soil is then transported by means of a conveyor belt up to the Rosebank shaft opening, and weighed. The front cutter head of the machine advances at roughly 220 m a month. A concrete tunnel lining is built ring-by-ring in the rear.

A computerised guidance monitoring system provides information to the TBM pilot on a continuous basis.

It also allows the pilot to steer the machine, and to continuously monitor the actual position of the TBM in relation to the theoretical centre line of the tunnel at any given location along its route.

Van der Merwe notes that some sinkholes at Oxford road were formed while tunnelling with the TBM machine. However, he points out that this was not a significant engineering challenge, and that the integrity of the tunnel was never in question.

Building Bridges

The Gautrain project requires the construction of 80 bridges and a number of very large culverts, equates to about 11 km of bridges.

Civil engineers constructing the close to 100 piers that will support the viaducts, or elevated railways, have had to develop a technique to overcome the problematic dolomitic ground in the Centurion and Pretoria area.

Between Centurion and Pretoria, the Gautrain alignment traverses through about 16 km of dolomitic ground, of which 5,8 km will be on viaducts, with the remaining portion constructed at surface level. To manage the risk associated with the dolomite rock, the construction of the viaducts includes the sinking and concreting of shafts down to the dolomitic rock, on which the foundations for viaduct piers are laid.

Property Development

Van der Merwe says that one of the key performance indicators of the Gautrain project, where R3-million is spent every hour for 54 months, is the land use around the Gautrain system.

The Gautrain project has affected 1 142 property stands. Van der Merwe reports that the last four property stands have now been handed over to the Bombela concession, giving the consortium access to the entire site.

Van der Merwe points out that when the system was designed, an average of 50% of land within a 2-km radius of the anticipated project was undeveloped, as was 75% within a 5-km radius. "When building a system like the Gautrain, an initial uncertainty develops, with property values falling."

As densification around the system develops, property values begin to increase again. "We expected this would happen in South Africa, but could not predict the pace at which this property explosion would occur," says Van der Merwe.

He reports that investment group Old Mutual will develop 250 000 m2 of mixed land next to the station in Midrand. This development has a value of around R20-billion and will be almost three times larger than the Menlyn shopping centre in Pretoria.

In addition, numerous hotels, offices, and retail centres are in the process of being developed close to the Gautrain Sandton station. Plans include the linking of the station with some of the hotels.

Van der Merwe concludes that the success of the Gautrain system lies in developing a train system that is constantly running on a planned schedule and not just during peak times.

 

Edited by: Laura Tyrer

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here
 
Comment Guidelines (150 word limit)
 
 
 
 
 
 
 
 
Other Automotive News
Updated 7 hours ago South African car and bakkie exports into Africa declined for the third year in a row in 2015, falling from 79 228 units in 2012, to 77 589 units in 2013, 60 189 units in 2014, and 41 446 units last year – this according to the Automotive Industry Export Council’s...
Updated 7 hours ago   Hyundai Automotive South Africa (HASA) hopes to see 2016 sales reach around the same level as 2015, defying a South African new-vehicle market most analysts agree will drop around 10% this year.
Updated 7 hours ago A 30c/l increase in the fuel levy, another rise in interest rates and new consignor/consignee legislation will all load more costs onto a transport industry that is already struggling to remain profitable, says Standard Bank business vehicle and asset finance head...
More
 
 
Latest News
Emira CEO Geoff Jennett
The JSE-listed Emira Property Fund has invested over R250-million in acquiring new centres and upgrading its shopping centres to strengthen its retail assets, according to Emira CEO Geoff Jennett, who stated on Thursday that the company was investing strategically....
Equites CEO Andrea Taverna-Turisan
JSE-listed Equites Property Fund achieved an 18.3% year-on-year increase in distributions to 96.6c a share for the year ended February 29. “The distribution growth reflects the strong property fundamentals of the Equites logistics portfolio,” Equites CEO Andrea...
It takes a coherent company to successfully and sustainably close the gap between strategy and execution in Africa, and one of the key factors in doing so is unconventional leadership, which is needed to foster the behavior required of coherent companies, according...
More
 
 
Recent Research Reports
Energy Roundup – May 2016 (PDF Report)
The May 2016 roundup covers activities across South Africa for April 2016 and includes details of the National Energy Regulator of South Africa’s proposal to introduce a coal benchmark cost as part of its final decision on Eskom’s multiyear price determination...
Automotive 2016: A review of South Africa's automotive sector (PDF Report)
Creamer Media’s Automotive 2016 Report provides an overview of South Africa’s automotive industry over the past 12 months. The report provides insight into local demand and production, vehicle imports and exports, investment and competitiveness in the sector, as well...
Energy Roundup – April 2016 (PDF Report)
The April 2016 roundup covers activities across South Africa for March 2016 and includes details of a North Gauteng High Court Judge’s dismissal of a court application to postpone the 9.4% electricity tariff increase, which the National Energy Regulator of South...
Electricity 2016: A review of South Africa's electricity sector (PDF Report)
Creamer Media’s Electricity 2016 report provides an overview of South Africa’s electricity sector, focusing on State-owned power utility Eskom and independent power producers, electricity planning, transmission, distribution and the theft thereof, besides other issues.
Energy Roundup – March 2016 (PDF Report)
The March 2016 roundup covers activities across South Africa for February 2016 and includes details of the Department of Energy’s plans to announce the preferred bidders for the first tranche of the coal independent power producer procurement programme; the Council...
Steel 2016: A review of South Africa's steel sector (PDF Report)
Creamer Media’s Steel 2016 Report examines South Africa’s steel industry over the past 12 months. The report provides insight into the global steel market and and particularly into South South Africa’s steel sector, including production and consumption, main...
 
 
 
 
 
This Week's Magazine
Updated 7 hours ago Following the drop in commodity prices and China’s demand for Africa’s resources, African economies were slumping and gross domestic product growth was stagnating in most of the continent’s emerging markets, said the New Partnership for Africa’s Development, or...
Updated 7 hours ago The New Development Bank, a multilateral lender formerly known as the Brics Development Bank, will provide $811-million in a first round of loans for clean energy projects in four nations.
Updated 7 hours ago South African car and bakkie exports into Africa declined for the third year in a row in 2015, falling from 79 228 units in 2012, to 77 589 units in 2013, 60 189 units in 2014, and 41 446 units last year – this according to the Automotive Industry Export Council’s...
Updated 7 hours ago Networking systems multinational Cisco is training 75 people as part of a pilot project to develop specialist networking skills in South Africa, says Cisco South Africa CTO Vernon Thaver. The trainees were nominated by and selected from Cisco’s local partners and...
Updated 7 hours ago The threat landscape is changing, along with technologies, impacting on new fields, such as industrial infrastructure, which is becoming increasingly connected. Smart cities are also developing fast through connected devices, Web services and cloud solutions, but...
 
 
 
 
 
 
 
 
 
Alert Close
Embed Code Close
content
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
 
 
Close
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $149 Close
Subscribe Now for $149