Glencore’s new low-cost Tweefontein coal mine coming in below budget

New structures at Glencore's Tweefontein Optimisation Project in Mpumalanga.
Coal mining under way at Glencore's Tweefontein Optimisation Project.
Coal at Glencore's Tweefontein Optimisation Project in Mpumalanga.

Glencore’s Tweefontein Optimisation Project GM Allen Butcher talks to Mining Weekly Online’s Martin Creamer about the R8-billion project that is ramping up to a throughput of 12.5-million tons of run-of-mine coal a year. Photographs: Duane Daws. Video and Video Editing: Nicholas Boyd.

New structures at Glencore's Tweefontein Optimisation Project in Mpumalanga.

Photo by Duane Daws

Coal mining under way at Glencore's Tweefontein Optimisation Project.

Photo by Duane Daws

Coal at Glencore's Tweefontein Optimisation Project in Mpumalanga.

Photo by Duane Daws

28th November 2014

By: Martin Creamer

Creamer Media Editor

  

Font size: - +

OGIES, Mpumalanga (miningweekly.com) – The new coal emerging from Glencore’s on-time, 85%-complete, R8.213-billion Tweefontein Optimisation Project (TOP) is coming in under budget.

The project has delivered a low-cost, long-life brownfield expansion that has elevated Tweefontein into a modern, predominantly opencast operation that mines the rich pillar reserves that were left behind in discontinued underground workings.

TOP’s mining segment is already close to steady state and by August the project’s new high-capacity washing plant will have fully ramped up to 12.5-million tons of run-of-mine coal a year, TOP GM Allen Butcher told Mining Weekly Online during a site visit. (Also see attached video).

The first two of a total of seven openpit operations are already producing at the operation, which is on the way to becoming Glencore’s second-largest coal operation after Optimum Coal.

Mining, which began at Tweefontein at the turn of the last century, will continue for the next 24 years on a mine authorisation area covering 113 km2.

Seventy five per cent of the more than seven-million tons of saleable coal that will be produced is destined for the export market and the remainder for the domestic market, with most of the domestic coal going to State electricity utility Eskom, which the London-, Hong Kong- and now also Johannesburg-listed Glencore group goes all out to assist.

On completion of the project in May/June, Tweefontein will be employing 750 full-time employees, many of them redeployed from Tweefontein’s closing underground operations.

Most of the employees at the operation, which is located 110 km north-east of Johannesburg, near the town of Ogies in Mpumalanga province, live in surrounding areas and there is no hostel environment.

“We have a policy of recruiting in local communities,” Butcher told Mining Weekly Online.

The group has a centralised training facility 10 km from Tweefontein, where mining operators and plant operators are trained.

Mining equipment, bought for R1.5-billion, includes a large 1570 Bucyrus dragline, which will move huge volumes of material at optimal efficiency in the large pits.

The truck-and-shovel mining method, which has already been deployed in the first two pits, is earmarked for use in the smaller pits.

The productivity of mining equipment is measured across the Glencore group monthly, taking in the company's coal operations in Australia, Colombia and South Africa.

Output is measured in bank cubic metres (bcm) against the nameplate capacity of the equipment used.

The target for the dragline is to achieve 2 000 bcm an hour, while the target for the bigger shovels is 1 100 bcm an hour and 750 bcm an hour for the smaller shovels.

Caterpillar supplied most of the rubber-tyred mobile equipment and dozers and Hitachi the excavators and backhoes.

Topsoil fleets are made up of 85 t excavators and 40 t articulated dump trucks and the primary loading fleet is made up of 260 t backactors, 350 t face shovels and a 200 t class front-end loader.

Although in-house crews do most of the maintenance, upkeep of large haul trucks has been contracted out to Barloworld and the upkeep of the large excavators to Hitachi – contracts that will be exited once the company is in steady state and has completed the building of its own large workshop facilities.

A big eight-bay workshop, which is still under construction, includes a tyre-handling facility, a million-litre fuel and lubrication service station, offices and a dragline section.

The R2-billion worth of operating infrastructure, which includes a high volume tip that feeds a run-of-mine facility designed to handle pillared coal, has been built along a dyke to avoid the sterilisation of coal reserves.

Project house DRA designed and built the R3.5-billion double-stage cyclone coal plant, which is similar to four others in the Glencore group, two in Australia and two in South Africa.

A rapid loadout facility feeds the rail siding that connects the mine to the Richards Bay Coal Terminal  (RBCT), the coal-export port in KwaZulu-Natal where Glencore is the largest shareholder.

Once the coal is extracted, the pits are backfilled as part of a rehabilitation process.

During the visit of Mining Weekly Online, rehabilitation was already under way in the two fully developed pits, where the first cuts have been filled, levelled, top soiled and seeded.

Edited by Creamer Media Reporter

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.071 0.126s - 156pq - 2rq
Subscribe Now