Nearly 50% of the Gautrain rapid-rail link's 150 km of track had been laid by the end of January.
All the train depot facilities, including the maintenance workshops, the train system administration buildings and operations control centre, are already completed and operational.
The control centre is set to be the heartbeat of the train system, and will house the signalling, telecommunications, automatic fare collection, traction power and overhead distribution, closed-circuit television cameras and maintenance capacities.
The R25,4-billion rail project will start full system trial operations on the first phase section between Sandton station and the OR Tambo International Airport in March.
The operator, Bombela, is expected to complete its ten-week trial run for this section in May.
Although the contractual completion date for the first phase is June 27, Bombela and the client – the Gauteng provincial government – aim for it to be wrapped up by May 27, so that it will be finished in time for the World Cup kick-off in June.
Complete area integration testing will already take place this month.
The OR Tambo International Airport station, Rhodesfield, Marlboro and Sandton stations, which all form part of phase one, should all be largely completed and operational before the end of May.
As for rolling stock, sub-assembly for the rail cars delivered from Derby, in the UK, to Nigel here in South Africa, is expected to be completed by February.
By the end of January, 49 of the 96 rail cars had been delivered to the depot. This equates to 12 complete four-car trains.
The last rolling stock four-car unit is expected to be completed for final acceptance testing by June.
The remainder of the 80 km route – phase two – which includes the line north to Tshwane and the line south to Park station, in Johannesburg, is scheduled for completion in 2011.




































