Creamer Media’s Engineering News Online
Advanced Search
 
 
 
We have detected that the browser you are using is no longer supported. As a result, some content may not display correctly.
We suggest that you upgrade to the latest version of any of the following browsers:
         
close notification
powered by
GOLD 1734.98 $/ozChange: -1.79
PLATINUM 1654.50 $/ozChange: 8.50
R/$ exchange 7.56Change: 0.00
R/€ exchange 10.00Change: -0.09
 
CONSTRUCTION UPDATE
Gautrain tracklaying reaches halfway mark
 
12th February 2010
TEXT SIZE
Text Smaller Disabled Text Bigger
 

Nearly 50% of the Gautrain rapid-rail link's 150 km of track had been laid by the end of January.

All the train depot facilities, including the maintenance workshops, the train system administration buildings and operations control centre, are already completed and operational.

The control centre is set to be the heartbeat of the train system, and will house the  signalling, telecommunications, automatic fare collection, traction power and overhead distribution, closed-circuit television cameras and maintenance capacities.

The R25,4-billion rail project will start full system trial operations on the first phase section between Sandton station and the OR Tambo International Airport in March.

The operator, Bombela, is expected to complete its ten-week trial run for this section in May.

Although the contractual completion date for the first phase is June 27, Bombela and the client – the Gauteng provincial government – aim for it to be wrapped up by May 27, so that it will be finished in time for the World Cup kick-off in June.

Complete area integration testing will already take place this month.

The OR Tambo International Airport station, Rhodesfield, Marlboro and Sandton stations, which all form part of phase one, should all be largely completed and operational before the end of May.

As for rolling stock, sub-assembly for the rail cars delivered from Derby, in the UK, to Nigel here in South Africa, is expected to be completed by February.

By the end of January, 49 of the 96 rail cars had been delivered to the depot. This equates to 12 complete four-car trains.

The last rolling stock four-car unit is expected to be completed for final acceptance testing by June.

The remainder of the 80 km route – phase two – which includes the line north to Tshwane and the line south to Park station, in Johannesburg, is scheduled for completion in 2011.

Edited by: Creamer Media Reporter
FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
 
 
 
Hide Comments  
 
This article contains no Comments

 
 
All comments must be approved by our editors, click here to read the editorial guidelines for comments. Please allow some time for our editors to approve your comment after posting.
 * Required Fields

image
image
 *
 

 

image
image
 *
 

image
image
 

Verification Image

image
image
 * Please enter the text you see in the above image.
 

 
PARK STATION At the underground station, the roof slab, concourse slab and the platforms are all nearly complete. Internal brickwork and plastering are well advanced at concourse and platform levels. Wall tiling and mechanical and electrical installations are ongoing. At the parkade structure, three of the six levels of deck slabs have been cast
 
Picture by: Gautrain
PARK STATION At the underground station, the roof slab, concourse slab and the platforms are all nearly complete. Internal brickwork and plastering are well advanced at concourse and platform levels. Wall tiling and mechanical and electrical installations are ongoing. At the parkade structure, three of the six levels of deck slabs have been cast
ROSEBANK STATION Backfilling over the station top slab and the adjacent cut and cover at the northern end is in progress. Reinstatement of Oxford road above the station structure will follow in the next few months. Platform structures, brickwork and plastering are all substantially complete, and painting and plumbing at both platform and concourse levels are well advanced. Wall tiling within the station is ongoing. Elevators have been positioned within the station box and mechanical and electrical installations are in progress
 
Picture by: Gautrain
ROSEBANK STATION Backfilling over the station top slab and the adjacent cut and cover at the northern end is in progress. Reinstatement of Oxford road above the station structure will follow in the next few months. Platform structures, brickwork and plastering are all substantially complete, and painting and plumbing at both platform and concourse levels are well advanced. Wall tiling within the station is ongoing. Elevators have been positioned within the station box and mechanical and electrical installations are in progress
SANDTON STATION Underground station construction works are well advanced in the cavern section between the south and north shafts, as well as within the shafts themselves. These works include construction of the various platforms, the technical rooms and operational rooms, as well as the escalator and lift shafts and stairways that are located within the shafts. The escalators that will transport commuters between the station entrance and the underground platforms have been installed. Tracklaying within the station is complete and tiling of platforms has started
 
Picture by: Gautrain
SANDTON STATION Underground station construction works are well advanced in the cavern section between the south and north shafts, as well as within the shafts themselves. These works include construction of the various platforms, the technical rooms and operational rooms, as well as the escalator and lift shafts and stairways that are located within the shafts. The escalators that will transport commuters between the station entrance and the underground platforms have been installed. Tracklaying within the station is complete and tiling of platforms has started
MARLBORO STATION At Marlboro station, internal finishes – including floor and wall tiling and painting – are well advanced, as is glazing of the external walls of the concourse and over-platform links. Tiling of the platforms has recently started. Railway tracks have been laid through the station and installation of associated railway equipment is ongoing. Externally, works continue at the bus terminal, with kerb laying on the parking deck and construction of the boundary around the station site also in progress
 
Picture by: Gautrain
MARLBORO STATION At Marlboro station, internal finishes – including floor and wall tiling and painting – are well advanced, as is glazing of the external walls of the concourse and over-platform links. Tiling of the platforms has recently started. Railway tracks have been laid through the station and installation of associated railway equipment is ongoing. Externally, works continue at the bus terminal, with kerb laying on the parking deck and construction of the boundary around the station site also in progress
RHODESFIELD STATION Rhodesfield station is positioned about one-third of the way along viaduct 15, directly above the existing railway lines running between Isando and Kempton Park. The platforms are elevated, with the station entrance, concourse and parking area located at ground level, on the eastern side of the existing railway lines. Construction of the station is approaching completion. The platforms, access ways and the station buildings are all substantially complete. Internal finishes are well advanced and technical equipment and mechanical and electrical installations are ongoing. Railway tracks have been laid through the station and the lines are in use
 
Picture by: Gautrain
RHODESFIELD STATION Rhodesfield station is positioned about one-third of the way along viaduct 15, directly above the existing railway lines running between Isando and Kempton Park. The platforms are elevated, with the station entrance, concourse and parking area located at ground level, on the eastern side of the existing railway lines. Construction of the station is approaching completion. The platforms, access ways and the station buildings are all substantially complete. Internal finishes are well advanced and technical equipment and mechanical and electrical installations are ongoing. Railway tracks have been laid through the station and the lines are in use
TRAINS PULLING IN AT OR TAMBO INTERNATIONAL AIRPORT STATION The station concourse is located at the eastern end of viaduct 15 and is directly linked to the departures level of the adjacent new central terminal building, one level below. Finishing works within the station concourse shell are substantially complete, as are electrical and mechanical installations. Ticket vending machines and fare gates have been installed and are being tested. Public address systems have been installed. Externally, the platform structures and canopies are substantially complete, with platform tiling to commence shortly. Rail tracks have been installed through the station
 
Picture by: Gautrain
TRAINS PULLING IN AT OR TAMBO INTERNATIONAL AIRPORT STATION The station concourse is located at the eastern end of viaduct 15 and is directly linked to the departures level of the adjacent new central terminal building, one level below. Finishing works within the station concourse shell are substantially complete, as are electrical and mechanical installations. Ticket vending machines and fare gates have been installed and are being tested. Public address systems have been installed. Externally, the platform structures and canopies are substantially complete, with platform tiling to commence shortly. Rail tracks have been installed through the station
OR TAMBO INTERNATIONAL AIRPORT STATION The station concourse is located at the eastern end of viaduct 15 and is directly linked to the departures level of the adjacent new central terminal building, one level below. Finishing works within the station concourse shell are substantially complete, as are electrical and mechanical installations. Ticket vending machines and fare gates have been installed and are being tested. Public address systems have been installed. Externally, the platform structures and canopies are substantially complete, with platform tiling to commence shortly. Rail tracks have been installed through the station
 
Picture by: Gautrain
OR TAMBO INTERNATIONAL AIRPORT STATION The station concourse is located at the eastern end of viaduct 15 and is directly linked to the departures level of the adjacent new central terminal building, one level below. Finishing works within the station concourse shell are substantially complete, as are electrical and mechanical installations. Ticket vending machines and fare gates have been installed and are being tested. Public address systems have been installed. Externally, the platform structures and canopies are substantially complete, with platform tiling to commence shortly. Rail tracks have been installed through the station
MIDRAND STATION At Midrand station, station building works are well advanced, roof cladding to the platforms is substantially complete and is ongoing over the concourse. Interior tiling and finishing works are ongoing. Platforms are substantially complete and platform tiling will start in the next few weeks, Tracklaying through the station is in progress. Retaining walls, earthworks and drainage for the parking areas are well advanced and layerworks and surfacing are ongoing
 
Picture by: Gautrain
MIDRAND STATION At Midrand station, station building works are well advanced, roof cladding to the platforms is substantially complete and is ongoing over the concourse. Interior tiling and finishing works are ongoing. Platforms are substantially complete and platform tiling will start in the next few weeks, Tracklaying through the station is in progress. Retaining walls, earthworks and drainage for the parking areas are well advanced and layerworks and surfacing are ongoing
CENTURION STATION The Centurion station platforms are elevated and are located on Viaduct five, which runs immediately adjacent and parallel to West Street. The concourse buildings and parking area are at ground level. Erection of the precast platforms and parapets atop the viaduct is complete and platform roof cladding is well advanced. Station building works, platform access stairs and lift shaft construction are all substantially complete
 
Picture by: Gautrain
CENTURION STATION The Centurion station platforms are elevated and are located on Viaduct five, which runs immediately adjacent and parallel to West Street. The concourse buildings and parking area are at ground level. Erection of the precast platforms and parapets atop the viaduct is complete and platform roof cladding is well advanced. Station building works, platform access stairs and lift shaft construction are all substantially complete
PRETORIA STATION At Pretoria station, concrete and building works, as well as the platform and concourse roof cladding, are substantially complete. Curtain wall framing and glazing are approaching completion and internal finishing works are ongoing. Mechanical and electrical installations have started. Parking area construction has started and refurbishing of the historically significant coach washing shed, that has been incorporated into the station design, will start shortly
 
Picture by: Gautrain
PRETORIA STATION At Pretoria station, concrete and building works, as well as the platform and concourse roof cladding, are substantially complete. Curtain wall framing and glazing are approaching completion and internal finishing works are ongoing. Mechanical and electrical installations have started. Parking area construction has started and refurbishing of the historically significant coach washing shed, that has been incorporated into the station design, will start shortly
HATFIELD STATION Structural works for the concourse slab being constructed over the future platforms are progressing well, as does construction of the adjacent parkade structure, where most of the final eighth level deck had been cast by the end of January. Between Pretoria station and Hatfield station, a number of bridges crossing the existing railway line require to either be widened or lengthened to accommodate the adjacent Gautrain tracks. Whilst most of these bridges have already been completed and reopened to traffic, works on the remaining structures are ongoing
 
Picture by: Gautrain
HATFIELD STATION Structural works for the concourse slab being constructed over the future platforms are progressing well, as does construction of the adjacent parkade structure, where most of the final eighth level deck had been cast by the end of January. Between Pretoria station and Hatfield station, a number of bridges crossing the existing railway line require to either be widened or lengthened to accommodate the adjacent Gautrain tracks. Whilst most of these bridges have already been completed and reopened to traffic, works on the remaining structures are ongoing
 
Previous Play Next