https://www.engineeringnews.co.za

Gautrain rapid rail link, South Africa

17th July 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Gautrain rapid rail link, Gauteng, South Africa.

Client
The Gautrain has been structured as a public–private partnership project.

The client is the Gauteng provincial government. The Bombela Concession Company (BCC) is the private-sector partner, with Bombardier Transportation (17%), Bouygues Travaux Publics (17%), Murray & Roberts (33%), J & J (8%) and the Strategic Partners Group (SPG) (25%) as shareholders.

Project Description
The Gautrain project comprises a state-of-the-art rail connection, linking Johannesburg, Sandton, Tshwane and OR Tambo International Airport. The network, which consists of about 80 km of railway line and which might be extended in the future, comprises two links – one between Tshwane and Johannesburg, and one between Sandton and OR Tambo International Airport.

Besides the three anchor stations at Johannesburg Park station, Pretoria and OR Tambo, there are seven other stations: Hatfield, Centurion, Midrand, Sandton, Rosebank, Rhodesfield and Marlboro.

The project is expected to generate numerous benefits for Gauteng, including economic development, job creation, a world-class transport system and environmental benefits.

Value
The rail project cost an estimated R27-billion, as inflationary pressures caused the cost of the Gautrain to escalate by R1-billion.

Duration
Construction started at the end of September 2006. The Gautrain was completed in two phases.

Phase 1 was initially planned to last 45 months; however, it was completed three weeks ahead of schedule. It included the network between OR Tambo International Airport and Sandton; the OR Tambo, Rhodesfield, Marlboro and Sandton stations; the bus and train depots; as well as the operations control centre, located near Allandale road, in Midrand.

The mechanical and electrical installation work was completed in January 2010, excluding some automatic fare-collection equipment.

Complete area integration testing took place in February 2010, during which the main bus depot, a dedicated bus system that feeds into the train route, was also completed.

Military-grade thermal-imaging cameras were installed by the end of April 2010.

A trial running period of ten weeks for the Phase 1 section was completed in May 2010.

Trial running is a process that follows the completion of testing and commissioning activities, during which all systems and subsystems are commissioned and tested to demonstrate that they meet the required performance standards. This process is carried out under the control of an operator. It comprises numerous drills and exercises, familiarising staff with operating conditions and, during the latter stages, running the full system according to the service timetable.

On June 8, 2010, Phase 1 of the Gautrain rail system was opened for commercial service. Phase 1 operations included the airport train service between Sandton station and OR Tambo International Airport, a commuter service between Sandton and Rhodesfield – with an intermediate stop at Marlboro station – as well as dedicated feeder and distribution bus services to and from the Sandton and Rhodesfield stations.

The remaining sections of the Sandton station, required for Phase 2 operations, were completed in March 2011. These works included the podium slab over the station complex, the remaining parking facilities, the third platform to service the southbound line to the Rosebank and Park stations and an undercover taxi terminus. The reinstatement of Rivonia road, which also formed part of these works, was completed and the road reopened to traffic in its final two-way configuration during December 2010.

Phase 2, which was constructed concurrently, was initially expected to be completed in 54 months; however, it was later announced that it would be completed in 57 months, in June 2011. The Gauteng Management Agency (GMA) stated in that same month that the second phase of the Gautrain would be opened at the end of July 2011 or early August 2011. The Bombela Operating Company was granted access to the full rail alignment between Rosebank and Pretoria, which includes all stations along this section of the route, in early March 2011. Under the control of the operator, trial running between the Rosebank and Pretoria stations started on March 8, 2011, with trial running along the final links to the Park and Hatfield stations having started in May 2011.

On August 2, 2011, the Rosebank-to-Pretoria link of the Gautrain rail project was opened. The remaining link, between Rosebank and Park stations, in Johannesburg, began operations in June 2012.

Latest Developments
The legal process involving the delay and disruption claim, which the Bombela consortium filed against the Gauteng provincial government regarding the construction of the R26.4-billion Gautrain rapid rail system is progressing, Murray & Roberts (M&R) has said.

The process started in August 2012.

Owing to the complexity of the arbitration, initial hearings were focused on clarifying the legal interpretation of various clauses in the Gautrain concession agreement.

The rulings of these initial hearings were largely in favour of the Bombela Concession Company, which was pursuing the claims on behalf of the Bombela Civil Joint Venture, in which M&R holds a 45% shareholding, Bouygues 45% and SPG 10%.

“The legal basis of the claim has now firmly been established. It is important to note, however, that the merits and quantum hearings will only be heard as from the first quarter of 2016 with financial conclusion only likely the following year,” M&R has noted in a statement.

The rulings from the initial hearings pertained to the right to proceed with a claim for additional costs incurred on two cantilever bridges which had now been confirmed; and the late handover of land, which was determined to be a project event giving rise to an entitlement to an extension of time and compensation for additional costs incurred.

M&R has said these rulings having reaffirmed its accounting position taken in previous financial years, when part of the claim was recognised as uncertified revenue.

Key Contracts and Suppliers
Bohlweki Environmental (environmental-impact assessment and biophysical and socioeconomic evaluation); Standard Bank and Rand Merchant Bank (lead arrangers, underwriters and sole lenders to the Gautrain project); Nedbank (agent bank to the lender to manage the financial transactions and the bank issuing project bonds to contractors); Arup SA (independent certifier); Tractionel Enterprise (supply and installation of the overhead contact distribution); Thales Transportation Systems and Sims (automatic fare-collection system); Bouygues Travaux Publics (tunnel-boring machine [TBM] operation); West Rand Engineering (valves, fittings and other consumables); Infrasors (aggregate and crusher sand); SPGIO (transportation of material excavated during construction); SA French (passenger hoists); Chryso South Africa (concrete admixture); SPC (concrete segments); Herrenknecht Engineers (TBM design and manufacture); Sarens (mobile-crane hire); Afri-Sam (supply of aggregate and 200 000 t of cement to the rail link's south section); C3 Shared Services, or C3SS (thermal-imaging equipment); ITT Water & Wastewater (drainage pumps); Railway Safety Regulator, or RSR (safety permit); Taemane Consulting (electrical engineers); and Atkins Global (detailed designs for 15 km of underground tunnels, three underground stations, seven emergency shafts, designs for the permanent way, alignment for the entire route and a cooling system).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Afri-Sam, tel +27 11 670 5500 or fax +27 11 670 5793.
Arup SA, tel +27 11 218 7600 or email johannesburg@arup.com.
Atkins Global, tel +44 13 7275 2350.
Bohlweki Environmental, tel +27 11 798 6001, fax +27 11 798 6010 or email info@bohlweki.co.za.
Bombadier Transportation media relations, tel +44 1332 266 470 or fax +44 1332 266 472.
Bombela, tel +27 11 997 8222, fax +27 11 997 8011, cell +27 83 229 2243.
Bouygues Travaux Publics, tel +33 1 3060 3300, fax +33 1 3060 4861 or email communication@bouygues-construction.com.
C3SS, tel 0861 2377 00, fax +27 86 500 9925 or email marketing@c3ss.co.za.
Chryso South Africa, tel +27 11 395 9700 or fax +27 11 397 6644.
Herrenknecht Engineers, tel +49 7824 3020, fax +49 7824 3403 or email info@herrenknecht.de.
Infrasors, tel +27 11 234 0109, fax +27 11 807 2468 or email Contact@infrasors.co.za.
RSR, tel +27 11 417 0000, fax +27 11 417 0010 or email helpdesk@rsr.org.za.
SA French, tel +27 11 822 8782, fax +27 11 822 8922 or email info@safrench.co.za.
Sarens, tel +27 11 861 3800, fax +27 11 861 3899 or email info@sarenssa.co.za.
Sims, tel +27 12 665 4446 or fax +27 12 665 4337.
Taemane Consulting, tel +27 11 608 5000, fax +27 11 608 3333 or email gauteng@taemane.co.za.
Thales Transportation Systems investor relations, tel +33 1 57 77 89 02 or email ir@thalesgroup.com.
Tractionel Enterprise, tel +27 11 768 7373, fax +27 11 768 7376 or email info@traction.co.za.
West Rand Engineering, tel +27 11 952 9800, fax +27 11 660 3206 or email wreng@wre.co.za.

Edited by Creamer Media Reporter

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.457 0.532s - 208pq - 2rq
Subscribe Now