Gautrain additional rolling stock and depot enhancement procurement programme, South Africa

11th January 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gautrain additional rolling stock and depot enhancement procurement programme.

Location
Gauteng, South Africa.

Client
Gautrain Management Agency (GMA), an agency of the Gauteng Provincial government (GPG).

The Gautrain is operated by the Bombela Concession Company (BCC).

Project Description
The project involves the acquisition of additional rolling stock comprising 12 new trains of four cars each and a workshop for the maintenance of the new trains.

The first contract includes the design, supply and maintenance of the new rolling stock, as well as the design, construction and maintenance of the depot extensions to accommodate the new trains. Three service providers were pre-qualified and participated in the bidding process.

Jobs to be Created
The project is expected to sustain 10 000 jobs in Gauteng.

Value
The total project value is estimated at R2.5-billion.

The GPG will be the owner of the project and funding will be provided by the Development Bank of Southern Africa.

It is, however, amenable to alternative funding options as presented by the successful bidder.

Duration
The new rolling stock is planned to start operations towards the end of 2021.

Latest Developments
It is back to the drawing board for the procurement of additional rolling stock for the Gautrain system, after the three prequalified bidders’ submissions failed to meet procurement requirements.

The prequalified bidders – Bombardier Transport, CRRC E-Loco Supply and Egoli Rail Consortium – submitted proposals in October last year to supply 12 new four-car trains for Gauteng’s rapid rail network.

The evaluation by teams of legal, technical, financial and economic development experts was completed in early December, but none were compliant.

The GMA says the tender issued contained minimum requirements in technical, financial, legal and socioeconomic development categories, as well as statutory compliance requirements that are part of South African supply chain management.

Of the three prequalified bidders, two did not submit any bid, with the submitted bid not meeting all the minimum requirements set in the tender.

The Gautrain system remains in need of additional rolling stock owing to congestion, especially during peak periods, and the GMA and the BCC will continue exploring options to obtain new train sets, the GMA has said.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
GMA senior executive manager communication and marketing Dr Barbara Jensen, email barbaraj@gautrain.co.za.

 

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 10 May 2024
10th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.3 0.357s - 159pq - 2rq
Subscribe Now