Flamanville 3 European pressurised reactor project, France

12th January 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Flamanville 3 European pressurised reactor (EPR) project.

Location
France.

Client
Électricité de France (EDF).

Project Description
The Flamanville EPR is the first nuclear power station to be built in France in the past 15 years and the first third-generation-type plant.

The nuclear plant will have a net electricity output of 1 650 MWe.

Potential Job Creation
Not stated.

Value
EDF announced this month that it has revised the cost of the project from €8-billion to €10.5-billion.

Duration
Work began at the site in December 2007. First fuel loading and start-up of the reactor has been revised from 2017 to the fourth quarter of 2018, a year later than initially announced.

Latest Developments
EDF completed the cold functional test phase for the Flamanville EPR on January 6 this year. This stage is part of the system performance testing, which started in the first quarter of 2017.

The cold functional test phase tests the leak performance on the primary system at a pressure greater than 240 bar (higher than the pressure of this system in operation), with more than 500 welds inspected during this hydrostatic testing, supervised by the Nuclear Safety Authority.

Hot functional testing is scheduled to start in July 2018 to demonstrate the good working order of the plant by testing components at temperature and pressure levels similar to those inoperating conditions.

More than 1 000 EDF and industry partner engineers and technicians have been mobilised to perform these system performance tests.

Fuel loading and start-up of Flamanville are expected at the end of the last quarter of 2018.

Key Contracts and Suppliers
Areva (nuclear steam supply system), Bouygues (civil work) and Alstom (turbine island).

On Budget and on Time?
Start-up of the project has been revised from 2017 to 2018 and the cost of the project has escalated from €8-billion to €10.5-billion.

Contact Details for Project Information
EDF, Véronique Ferdinand, tel +33 2 33 78 59 93 or email Veronique.ferdinand@edf.fr.
Areva, Alexandre Thébault, tel +331 34 96 12 15, fax +331 34 96 16 54 or email press@areva.com.
Bouygues, tel +33 1 30 60 33 00, fax +33 1 30 60 48 61 or email communication@bouygues-construction.com.

Edited by Creamer Media Reporter

Comments

Showroom

Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.271 0.325s - 159pq - 2rq
Subscribe Now