Eurasia tunnel project, Asia and Europe

5th June 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Eurasia tunnel project, Asia and Europe.

Client
The Turkey Ministry of Transport, Maritime Affairs and Communications and General Directorate of Infrastructure Investments (AYGM) commissioned Avrasya Tüneli İşletme İnşaat ve Yatırım (ATAŞ) for the design, construction and operation of the Eurasia tunnel project.

Project Description
The project will connect the Asian and European sides through a highway tunnel underneath the seabed.

The tunnel will serve the Kazlıçeşme-Göztepe route, where vehicle traffic is most intense in Istanbul, and will cover a total of 14.6 km.
The tunnel construction will start on the Anatolian side and will be completed on the European side, after about 25 m have been dug under the seabed using a tunnel-boring machine.

While 5.4 km of the project will comprise a two-storey tunnel to be built underneath the seabed using special technology with connecting tunnels to be constructed using other methods, road expansion and improvement works will be carried out on 9.2 km on the European and Asian sides. The access roads between Sarayburnu-Kazlıçeşme and Harem-Göztepe will be enlarged.

Vehicle underpasses and pedestrian overpasses will be built.

Tunnel pass and road improvement-expansion works will relieve traffic congestion.

Travel time on the route will decrease from 100 minutes to 15 minutes.

It will also contribute to the reduction of environmental and noise pollution.

Value
$1.25-billion.

Duration
Construction started in February 2013 and operation is expected to start in 2017.

Latest Developments
The AYGM has commissioned ATAŞ for the design, construction and operation of the Eurasian tunnel project for 24 years and five months.

Completion of the tunnel-boring machine excavation is expected in July.

Key Contracts and Suppliers
ATAŞ (design, construction and operation of the tunnel).

On Budget and on Time?
Not stated.

Contact Details for Project Information
ATAŞ, tel +90 216 474 05 20, fax +90 216 474 05 24 or email info@avrasyatuneli.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.456 0.51s - 159pq - 2rq
Subscribe Now