Creamer Media’s Engineering News Online
Advanced Search
 
 
 
We have detected that the browser you are using is no longer supported. As a result, some content may not display correctly.
We suggest that you upgrade to the latest version of any of the following browsers:
         
close notification
powered by
GOLD 1343.90 $/ozChange: -30.62
PLATINUM 1411.50 $/ozChange: -15.00
R/$ exchange 10.25Change: -0.24
R/€ exchange 13.58Change: -0.18
 
ROAD CONSTRUCTION
 
Esorfranki aims to complete R21 upgrade near airport by May 28
 
26th March 2010
TEXT SIZE
Text Smaller Disabled Text Bigger
 

With a tight deadline and many challenges, Esorfranki Civils was working around the clock to ensure that the stretch of the R21 highway between Pomona road and the R24 split, in Kempton Park, east of Johannesburg, would be ready before the start of the 2010 FIFA World Cup.

Senior site agent for the project Morné Barnard said during a site visit on Friday that this section of work near the OR Tambo International Airport had to be completed by May 28, before the World Cup starts on June 11.

This formed part of the work package J of the Gauteng Freeway Improvement Project (GFIP), which Esorfranki Civils was responsible for.

The highway was being widened to four lanes on each side, while a number of bridges had to be lengthened and refurbished and some pedestrian bridges removed.

Barnard highlighted that the supply of bitumen was one of the greatest challenges it was facing at present.

Despite placing orders for bitumen two to three weeks ahead of time, not enough supply was coming through, as many of the oil refineries that supplied the bitumen were undertaking maintenance shutdowns for the World Cup period.

He noted that while about 1 000 t/d of bitumen was required by the road construction industry, only about 30 t/d to 70 t/d was currently being delivered.

Barnard said that it had informed the South African National Roads Agency Limited (Sanral) of the potential delays that this could cause.

It would meet with Sanral again next week regarding this matter.

Esorfranki also noted that another challenge was the electrical cabling that had to go underneath this stretch of road, while nearby reservoirs that were leaking were also hampering the project.

Meanwhile, Barnard said that the heavy rains experienced in the Kempton Park area during January had delayed the overall work package J project by about two months.

While the area usually got about 136 mm of rain in January, about 400 mm of rain had been recorded in January this year.

The entire project, which involved the 12 km between the Pomona road off-ramp and the Rietfontein interchange, would be completed by April 2011.

Edited by: Mariaan Webb

 

To subscribe to Engineering News's print magazine email subscriptions@creamermedia.co.za or buy now.

FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
Esorfranki Civils senior site agent for the project Morné Barnard
 
Picture by: Duane Daws
Esorfranki Civils senior site agent for the project Morné Barnard
 
Esorfranki Civils was working around the clock to complete a section of the R21 before the start of the World Cup
 
Picture by: Duane Daws
Esorfranki Civils was working around the clock to complete a section of the R21 before the start of the World Cup
 
 
Previous Play Next