Eskom resumes construction work at most sites
Work has resumed at parastatal Eskom’s construction sites across the country, besides Ingula, following a temporary suspension of activities on November 1 to assess the safety conditions across all operations.
Construction at Eskom’s Ingula underground pumped-storage construction site, near Ladysmith, in KwaZulu-Natal, however, remains suspended pending the outcomes of continuing investigations by the Department of Mineral Resources and corporate law firm Webber Wentzel into the death of six workers at the site last month.
CEO Brian Dames announced on November 1 that construction at all Eskom construction sites would be halted indefinitely to assess working conditions.
“At the moment, project timelines are the least of our concerns, they are not our priority. The work stoppages will last [until] every Eskom manager and contractor is comfortable that the existing security and safety systems are in place,” he said at a press briefing at the time.
While Dames would not at the time elaborate on the length of the suspension, an Eskom spokesperson told Engineering News Online on Monday that work across most of the energy utility’s construction sites was only halted for a few hours that afternoon, with a return to full construction by the following Monday, November 4.
Six workers, who were employed by a subcontractor, were killed at Ingula when an 8 t gantry, or platform, came loose from its anchoring and travelled at speed down a 938-m-high inclined underground shaft, connecting with a monorail used to transport workers, as well as two other gantries on which employees were standing.
Four of the deceased were foreign nationals, while two were South African citizens.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation