R/€ = 15.11Change: 0.14
R/$ = 13.45Change: 0.10
Au 1149.14 $/ozChange: 2.69
Pt 940.50 $/ozChange: 6.00
Note: Search is limited to the most recent 250 articles. Set date range to access earlier articles.
Where? With... When?

And must exclude these words...
Close Main Search
Close Main Login
My Profile News Alerts Newsletters Logout Close Main Profile
Agriculture   Automotive   Chemicals   Competition Policy   Construction   Defence   Economy   Electricity   Energy   Environment   ICT   Metals   Mining   Science and Technology   Services   Trade   Transport & Logistics   Water  
What's On Press Office Tenders Suppliers Directory Research Jobs Announcements Letters About Us
RSS Feed
Article   Comments   Other News   Research   Magazine  
Jul 08, 2011

Environmental projects at Vanderbijlpark works well under way

ArcelorMittal South Africa environmental GM Siegfried Spanig discusses the company's plans to spend more than R2-billion over the coming four years to ensure that all its operations are compliant with the country's increasingly stringent environmental legislation.
© Reuse this

Steel producer ArcelorMittal South Africa’s rehabilitation projects at its Vanderbijlpark waste disposal facilities are well under way.

The steel giant is currently undertaking remediation projects at the former waste- water disposal dam (Dam 10), the central effluent treatment plant (CETP) sludge dams, the maturation ponds and the old steel manufacturing waste disposal site at its Vanderbijlpark works.

Mittal expects the R48-million bio- remediation of Dam 10 to be completed by October this year.

The project forms part of the company’s R2-billion drive to further improve the environmental impact of its plants across the country in the coming years.

The 75 ha dam was commissioned in 1960 as part of a number of wastewater storage and evaporation dams. Two of the dams were used for organically contaminated wastewater, while the remaining dams were used for inorganic wastewater.

Organic effluent from coke ovens at the site’s coke plant was historically pumped into Dam 10 and contaminated the underlying clay sediment.

Coke oven effluent contains significant amounts of polycyclic aromatic hydrocarbons (PAHs) along with more soluble components such as cyanide, phenols and ammonia.

Mittal environmental manager Karien Zantow explains that the insoluble PAH-containing tars settled out and built up at the bottom of the dam. Little biodegra- dation took place in the bottom sludge and the organics accumulated over the years. Thus, after extensive dewatering of the dam, tar pools appeared in some areas.

Changes in environmental policy and concern over accumulated priority pollutants resulted in the effluent-handling process being changed and the dam being decommissioned.

“Disposal of the settled sludge and contaminated soil became a priority and various methods were investigated. “Eventually 150 000 m3 of sludge and soil was identified for cleanup and on-site bioremediation was the most cost effective option,” she adds.

Use of the dam stopped in 2000 and it is currently undergoing rehabilitation using archaea microorganisms that are added to the contaminated soil to break down waste compounds.

Each species of archaea serves a specific purpose and functions optimally at varying levels of pH and temperature.

Zantow explains that the addition of high concentrations of a diverse range of archaea to a treatment system permits some species to select to the environment encountered. As the environment changes, the continuous addition of the biosystem ensures that the microorganisms continue to populate the treatment system and perform effective breakdown.

The archaea are grown in an on-site reactor and mixed with the soil using custom-built windrowers.

Between six and seven months are required for the soil to achieve a 97% rehabilitated status.

Between 2002 and 2004, the dam was dried out, followed by remediation of 98% of the area between 2008 and 2010. The process involved excavation of the 800-mm-thick layer of tar sludge and contaminated soil that was stacked into windrows within the existing footprint and surface of the dam.

Hay and organic compost are added to the top of the piles by 20% of volume and are mixed using the self-propelled windrow machines. Simultaneously, 25 ℓ of archaea, which consists of 8% solution with 0.05% surfactant, was sprayed for each cubic metre of soil.

The application is strictly controlled by Mittal technologist Johan Hattingh.

Zantow says testing indicated that organic breakdown had been successful in the completed section and the required soil cleanup targets for all organic pol- lutants achieved.

“Testing on the windrows showed that between 88% and 99% of all pollutants were broken down,” she notes.

Chemical composition of the prepared windrows was determined by taking core samples from each side along the length of the windrows. The cores were blended and samples submitted for analysis of PAH, which is regarded as a priority pollutant by the Environmental Protec- tion Agency and known to be present in coke oven effluent.

The rehabilitation process further entails that the windrows be turned at least every two weeks. The revitalised soil is then reworked into the lower clay layer to serve as the topsoil, after which five indigenous grass species are planted. The end result is a completely self-sustaining open field.

Similar remediation of the remaining 2% of the area is currently under way with final vegetation to be completed by October this year.

“The main objective of the project was to limit possible contamination of sur- face water and ensure clean stormwater runoff from the site after remediation,” Zantow says.

Other benefits of the rehabilitation project will be the lowering of the risk of contamination seepage into the ground and reducing dust to a large extent by planting grass. The grass also serves to transform the former dam into an aesthetically pleasing area.

Zantow adds that, when rehabilitation is complete, the space will be reserved as a storage area; however, until it is needed for that purpose, it will remain an unused vegetated field.

“This flagship project will reduce the impact of a legacy facility that has been in operation for the last 50 years,” she states.

The site’s old CETP sludge dams will undergo the same bioremedation procedure once Dam 10’s bioremediation has reached completion.

The remediation of the CETP sludge dams comprises different phases, with the first phase, which involved the safe disposal of inorganic sludge, having been completed at a cost of R12-million last year.

“The company excavated 650 000 m3 of inorganic sludge from these dams in August last year. The remaining material is currently being windrowed for bioremediation,” says Zantow.

Further, Mittal budgeted R11-million for the second phase, during which about 45 000 m3 of sludge will undergo organic remediation. The second phase is expected to start in October and be completed by July next year.

The third phase will entail sloping and shaping of the area and the implementation of a stormwater control system. The phase is set to start in June next year and reach completion by June 2013.

Soil stabilisation and revegetation will be done during the fourth and final phase that will run from July next year to March 2014.

Maturation Ponds
Mittal is also currently undertaking reme- diation projects at its Vanderbijlpark maturation ponds that were initially used to moderate the effluent toxicity to vegetation to enable use of the water for turf irrigation in the Kiewiets area.

The maturation ponds, which comprise three dams (Dam 1, Dam 2 and Dam 3), were decommissioned in 2008.

Remediation of the dams entails soil pH stabilisation. The process at Dam 3 started in 2009 and was completed last year.

The same soil stabilisation method, which has been determined and implemented by remediation specialist Viljoen & Associates at Dam 3, will also be implemented at Dams 1 and 2.

Viljoen & Associates owner Chris Viljoen explains that the soil is characterised and polygons of contamination are drawn on areas with similar contamination levels. Specific and differential application and treatment rates are then determined for each polygon area.

This means that the entire surface is not treated or stabilised as one homo- genous soil body, but that targeted and specific treatment is applied depending on the soil quality.

“The success of the soil remediation strategy in conjunction with pH stabilisation is embedded in the increase in buffer capacity through an increase in the percentage of amorphous carbon per mass and/or volume soil content. “Owing to the adsorptive characteristics of carbon, a significant dilution effect is created in the double layer solution around the colloidal soil particles. “Sufficient gypsum, lime and carbon are also added in specific ratios to ensure the sodium adsorption ratio is corrected,” Viljoen says.

At Dam 2, windrows have been packed and remediation is expected to start in October this year and be completed in December next year.

Dam 1 is currently undergoing on-site water and sludge remediation, which will be completed in 2012.

The total remediation process of the maturation ponds is expected to be complete by the end of 2015. To date, R6.5-million of the R30-million allocated for the project has been spent.

Waste Disposal Site
Further, remediation of the Vanderbijlpark works’ old 170 ha waste disposal site is in progress.

Zantow says about 40-million cubic metres of waste, which consists mainly of steelmaking slag, dust and filter cake, has been disposed of at the site since its inception in the early 1960s.

Disposal on the old waste site was terminated in December 2010 as dictated by water use licence requirements that prohibit disposal beyond the site reaching 40 m in height.

Remediation of the site is done in three phases, during which the area is divided into three sections that will each undergo subsequent remediation through sloping, shaping and soil capping.

Stormwater drainage canals will also be constructed to divert clean runoff into the main stormwater chute that joins the clean stormwater system.

During capping, the area surface is covered with a 1.5 mm flexible high- density polyethylene liner and then covered by a 500-mm-thick layer of clean com- pacted soil, followed by a 200-mm-thick clean topsoil layer.

The side slopes are also covered with three 150-mm-thick compacted layers of clean clay.

Fertilisers are then added to the topsoil and hydroseeding is done for the establishment of indigenous vegetation.
Phase one cost R30-million and ran from September 2009 to October 2010.

Sloping and shaping of the soil for the similar, but much larger, second phase began in January this year, with capping to start in July. The total environmental provision budget for phase two is R47-million.

Zantow says that packing of the liners for the second phase of the project started in June.

“According to our project programme, the second phase is to be completed in September next year,” she adds.

The third and final phase will begin in 2013 and will be completed by 2015 at the latest.

The total budget for the waste site remediation project amounts to about R100-million.

New Waste Disposal Site
Construction of Mittal’s new waste disposal facility started in January last year.

Further, construction of the leachate dam, which is designed to store toxic liquids, started in April last year. The R23-million project was completed in December last year, with operation starting in January this year.

Edited by: Chanel de Bruyn
Creamer Media Senior Deputy Editor Online
© Reuse this Comment Guidelines (150 word limit)
Other Environment News
The City of Cape Town has successfully reapplied for an environmental-impact assessment (EIA) for its routine stormwater management activities following changes in national legislation; however, this time, the city gained citywide authorisation. The City of Cape Town...
The much anticipated traffic restrictions into Sandton, Johannesburg, began Monday as the EcoMobility World Festival took off. Organisers said the festival aims to demonstrate the possibilities and benefits of urban mobility without dependency on private cars in a city.
Energy analyst and EE Publishers MD Chris Yelland warned recently against excessive optimism regarding timescales for the proposed construction of new nuclear power plants (NPPs) in South Africa. He was speaking at a Nuclear Roundtable in Johannesburg. “I think we...
Latest News
Updated 2 minutes ago Allied Electronics (Altron) has dipped into the red in the six months ended August 31, as the JSE-listed firm continued to experience “adverse” challenges weighing on its Powertech Transformers, Altech Multimedia, Altech Autopage and Altech Node business units. The...
Updated 33 minutes ago Global brewer Anheuser-Busch InBev (AB InBev) has announced a revised merger offer to British–South African multinational brewing and beverage company SABMiller in its bid to combine the two firms and form a global beer conglomerate with yearly revenues of...
Updated 50 minutes ago US private equity firm KKR & Co LP is considering investing around $100-million in Africa within a year, a senior executive said on Tuesday. KKR is looking at the agriculture and food business, the energy industry and infrastructure projects, Dominique Lafont, a...
Recent Research Reports
Liquid Fuels 2015: A review of South Africa's liquid fuels sector (PDF Report)
Creamer Media’s Liquid Fuels 2015 Report examines these issues in the context of South Africa’s business environment; oil and gas exploration; fuel pricing; the development of the country’s biofuels industry; the logistics of transporting liquid fuels; and...
Road and Rail 2015: A review of South Africa's road and rail sectors (PDF Report)
Creamer Media’s Road and Rail 2015 report examines South Africa’s road and rail transport system, with particular focus on the size and state of the country’s road and rail infrastructure and network, the funding and maintenance of these respective networks, and...
Defence 2015: A review of South Africa's defence sector (PDF Report)
Creamer Media’s Coal 2015 report examines South Africa’s coal industry with regards to the business environment, the key participants in the sector, local demand, export sales and coal logistics, projects being undertaken by the large and smaller participants in the...
Real Economy Year Book 2015 (PDF Report)
There are very few beacons of hope on South Africa’s economic horizon. Economic growth is weak, unemployment is rising, electricity supply is insufficient to meet demand and/or spur growth, with poor prospects for many of the commodities mined and exported. However,...
Real Economy Insight: Automotive 2015 (PDF Report)
Creamer Media’s Real Economy Year Book comprises separate reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, gold, iron-ore and platinum sectors.
Real Economy Insight: Water 2015 (PDF Report)
Creamer Media’s Real Economy Year Book has been divided into individual reports under the banner Real Economy Insight and investigates key developments in the automotive, construction, electricity, road and rail, steel, water, coal, gold, iron-ore and platinum sectors.
This Week's Magazine
Sphere Holdings CEO Itumeleng Kgaboesele
Black-owned investment holding company Sphere Holdings plans to raise a further R1-billion in the coming months in support of its strategy to become a leading black industrial enterprise, which could ultimately seek a listing on the JSE.
Energy analyst and EE Publishers MD Chris Yelland warned recently against excessive optimism regarding timescales for the proposed construction of new nuclear power plants (NPPs) in South Africa. He was speaking at a Nuclear Roundtable in Johannesburg. “I think we...
Malawi’s Lilongwe Water Board (LWB) is inviting eligible bidders to prequalify for the board’s efficiency improvement works, which will be implemented as part of the E24-million Lilongwe Water Resources Efficiency Programme.   LWB CEO Alfonso Chikuni explains that...
CROATIA, AN EU MEMBER BUT NOT A TDCA MEMBER On July 1, 2013, Croatia officially became the twenty-eighth member of the European Union (EU). Despite Croatia’s accession into the EU, it is yet to become party to the Trade, Development and Cooperation Agreement (TDCA)...
The Council for Scientific and Industrial Research (CSIR) has announced that its new Inundu airborne electronics testing, evaluation and training pod had made its first test flight on September 10. The successful flight was undertaken from Lanseria International...
Alert Close
Embed Code Close
Research Reports Close
Research Reports are a product of the
Research Channel Africa. Reports can be bought individually or you can gain full access to all reports as part of a Research Channel Africa subscription.
Find Out More Buy Report
Engineering News
Completely Re-Engineered
Experience it now. Click here
*website to launch in a few weeks
Subscribe Now for $96 Close
Subscribe Now for $96