Endeavour moves forward Ity gold pour
The process plant construction is more than 70% complete, tracking ahead of schedule.
The Ity carbon-in-leach (CIL) gold project that Endeavour Mining’s in-house team is building in Côte d'Ivoire is tracking two months ahead of schedule and will pour its first gold at the beginning of the March 2019 quarter, rather than mid-year, the Canadian firm reported on Wednesday.
In a construction update, the company said that the project was about 75% completed. Nearly all the $412-million initial capital cost had been committed and about 65% had been spent.
“Completing the construction sooner is expected to result in material improvement to our 2019 free-cash flow generation potential as Ity CIL will be a low-cost operation with an all-in sustaining cost (AISC) expected to be below $500/oz over its first five years," president and CEO Sébastien de Montessus said.
COO and VP for projects Jeremy Langford noted that the project had benefited from the experience of Endeavour’s in-house construction team, which previously built in the Houndé and Agbaou mines in the region, as well as the three-month early installation of the ball and semi-autonomous grinding mills.
Further, Endeavour reported zero lost-time injuries during more than six-million man-hours worked. Currently, about 2 800 personnel, including contractors, are employed on site, about 90% of whom are locals.
Construction of the Ity CIL project started in September last year. An optimised study has demonstrated the significant potential for Ity, which has already been in operation for more than 20 years, to become another flagship asset for Endeavour.
The Ity CIL project is expected to produce about 204 000 oz/y for the first ten years, at an AISC of $549/oz.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation