Durban port upgrade and expansion project, South Africa

4th September 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Durban port upgrade and expansion project, KwaZulu-Natal, South Africa.

Client
The Transnet National Ports Authority (TNPA) and Transnet Port Terminals (TPT), divisions of freight logistics company Transnet.

Project Description
The Durban Container Terminal (DCT) is the biggest and busiest in the southern hemisphere and currently handles 64% of the country’s seaborne container traffic.

Transnet is implementing an ambitious expansion project at the Durban port and its container terminals, comprising several individual work packages, to increase the DCT’s container-handling capacity.

The main projects include the expansion of the DCT Pier 1, which will increase the capacity of the terminal to 1.2-million TEUs by 2016/17.

In addition, the North quay at DCT Pier 2 will be extended to increase capacity to 3.3-million TEUs by 2017/18.

Container capacity is also being created at other terminals, such as the Durban Ro-Ro and Maydon Wharf terminals, through the acquisition of new equipment, including mobile cranes and various infrastructure upgrades.

Transnet is further proposing the phased development of a new dig-out port on the old Durban International Airport (DIA) site, among other projects.

Value
The project forms part of an initial five-year R110.5-billion capital expenditure programme until 2015/16 and the group’s larger R312.2-billion (from R307.5-billion) seven-year Market Demand Strategy (MDS) until 2018/19.

However, funding for the new port at the DIA is not included in the strategy.

Transnet has indicated that it is in the final stages of appointing a transaction adviser and is considering various funding options and models for private-sector participation in the project.

Duration
Ongoing.

Latest Developments
A delay in repairs to the hospital ship Africa Mercy has resulted in a two-and-a-half week adjustment of timelines for TNPA’s R30-million repair project at the Prince Edward Graving dry dock, in Durban.

This follows private ship-repair company Dormac Marine and Engineering’s discovery that additional work was required on the ship’s shaft during a routine repair and survey exercise at the TNPA-owned dry dock, which was due to be nonoperational over August and September.

Parts had to be sourced from overseas and the vessel departed from the dock on August 18 rather than the planned July 31 departure date.

The two-month nonoperational period at the dock was adjusted to start from August 19 – when appointed contractor Channel Construction took full occupation of the dock – and end on October 20.

The expected completion date of the caisson repair project has been postponed from November to mid-December.


The 90-year-old Durban dry dock is undergoing the third and final phase of a comprehensive repair programme on its 35-m-long, 900 t steel caisson, which was deemed unsafe and in need of repair.

Channel Construction is working with managing contractor Sebata Group, which is overseeing the caisson repair project.

The team is working in 24-hour shifts, with the majority of the work being carried out off site at the contractor’s Bayhead workshop.

Work includes demolition and waste disposal, structural repair, welding, modification and replacement of structural members and plates, design and fabrication certification, commissioning and final handover.

The outer caisson repair project forms part of TNPA’s large-scale repair programme for the dry dock.

The authority has accelerated planned refurbishments of existing ship repair facilities at its ports, in line with the South African government’s Operation Phakisa initiative, which aims to unlock the economic potential of South Africa’s oceans.

Under Transnet’s Market Demand Strategy, the plans are a key aspect of TNPA’s R35-billion-plus investments into port infrastructure, capacity and maintenance over seven years until 2019.

Key Contracts and Suppliers
Protekon Consulting & Construction; CPS; IMPSA-Jikelele joint venture (JV); Kalmar African National Engineering, or ANE, JV; Hydroflow and Liebherr Cranes (Germany); Grinaker-LTA, Interbeton and Bafokeng Bateman Services (Bafokeng Civil Works and Bateman Materials Handling) JV; DSE and Dorbyl (subcontractors steelwork fabrication); La Spezia Container Terminal, Italy (three Liebherr cranes); Kalmar (straddle carriers); DSE (manufacture of structural components and the erection and installation of mechanical and electrical work); Protekon (planning and designing the infrastructure for the installation of the Liebherr cranes at the south terminal); Protekon Construction (two new berths for Island View terminal); Dura Piling (piling contract – Island View); Basil Read (main contractor – Pier 1, civil and paving works – DCT); Chryso South Africa (concrete products – hard standing area, Pier 1); Lafarge Readymix (design and supply of concrete – hard standing area, Pier 1); Natal Portland Cement, or NPC (cement – Pier 1); Kalmar Industries (30 straddle carriers); TBA (review, analysis and simulation of DCT’s container-handling operations); Sarens Group (crawler crane); the Japan Bank for International Cooperation (loan finance); Shanghai Zhenhua Port Machinery Company (rail-mounted gantry cranes); Shanghai Zhenhua Heavy Industries Co, or  ZPMC (design, manufacture, delivery and commissioning of cranes); Dredging International and Group Five (port-widening project); C3 Shared Services (codesign of security solution at Pier 1); Mott MacDonald, in JV with Hatch and Goba (widening of Durban harbour entrance and construction of Pier 1 container terminal); Blue IQ (financial coordinator for proposed container terminal at the old DIA site); and Liebherr (design, fabrication, delivery, erection, testing and commissioning of the cranes).

On Budget and on Time?
The project is on schedule and within budget.

Contact Details for Project Information
ANE Durban head office, tel +27 31 579 3301, fax +27 31 579 3323 or email aned@mweb.co.za.
Basil Read, tel +27 11 418 6375 or fax +27 11 418 6334.
Bateman, tel +27 11 899 9111 or email pgm@batemanbv.com.
Chryso South Africa, tel +27 11 395 9700 or fax +27 11 397 6644.
Dorbyl, tel +27 41 408 6009, fax +27 41 408 6035 or email dorbyl@guestroauto.com.
Dredging International, tel +32 3 250 52 11, fax +32 3 250 56 50 or email dredging@dredging.com.
DSE, tel +27 11 871 4111 or fax +27 11 871 4141.
Grinaker-LTA, tel +27 11 578 6000, fax +27 11 578 6161 or email enquiry@grinaker-lta.co.za.
Group Five, tel +27 11 806 0111, fax +27 11 803 5520 or email info@g5.co.za.
Kalmar Industries, tel +27 31 327 1800 or fax +27 31 327 1811.
Lafarge Readymix, tel +27 31 275 7400.
NPC, tel +27 31 450 4411 or fax +27 31 451 9010.
Sarens Group, Hendrik Sarens, tel +32 52 319 397 or email hendrik.sarens@sarens.com.
Transnet Port Terminals, tel + 27 31 308 8000 or fax +27 31 308 8084.
ZPMC, tel + 86 21 58396666, fax +86 21 58399555 or email mail@zpmc.com.

Edited by Creamer Media Reporter

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.083 0.135s - 159pq - 2rq
Subscribe Now