Durban dry dock completion date brought forward

7th October 2015

By: Natalie Greve

Creamer Media Contributing Editor Online

  

Font size: - +

With close to 60% of the work already completed on Transnet National Ports Authority’s (TNPA’s) R30-million caisson repair project at the 90-year old Prince Edward Graving Dry Dock in Durban, the project’s handover date has been brought forward by a month to November 25.

The four-month project initially entailed a two-month nonoperational period in August and September, followed by a partly operational period in October and November.

However, as previously reported, the contractor was unable to take occupation of the dry dock, owing to an unexpected delay on the repair of the hospital ship Africa Mercy. The project, therefore, started on August 20.

TNPA Durban port manager Moshe Motlohi said in a statement that the delayed start impacted on the erection of scaffolding and the appointed contractor’s occupation of the dock, which had a direct knock-on effect on critical path activities and threatened to push the completion date of the project to December 24.

Owing to the 21 working days that were lost at the start of the project, it became apparent that the contractor’s methodology would need to be changed.

“We have tried to minimise any further impact on the ship repair industry by taking measures to bring the project completion date forward by a month, although the dock’s nonoperational period has been extended from late October to also end on November 25,” he said.

TNPA said it had formally engaged with the South African Association of Ship Operators and Agents and the South African Ship Builders and Repairers Association to keep them abreast of the adjusted timelines.

“While the revised methodology presents the benefit of an earlier project completion, it also poses serious risks associated with docking a vessel while the project is in progress. Dry dock bookings will, therefore, only be accepted for dates after November 25,” Motlohi added.

This was the third and final phase of a comprehensive repair programme on the dry dock’s outer caisson, which was deemed unsafe and in need of repair.

Work completed, to date, included the refurbishment of certain sections of the 35-m-long, 900 t steel caisson and the installation of other new sections.

Additional work included demolition and waste disposal, structural repair, welding, modification and replacement of structural members and plates, design and fabrication certification, commissioning and final handover.

The outer caisson repair project was the first of 11 Operation Phakisa projects at the dry dock and formed part of TNPA’s large-scale repair programme for the facility.

The authority had accelerated planned refurbishments of existing ship repair facilities at its ports in line with the South African government’s Operation Phakisa initiative, which aimed to unlock the economic potential of South Africa’s oceans.

Under Transnet’s Market Demand Strategy, the plans were a key aspect of TNPA’s R35-billion-plus investments into port infrastructure, capacity and maintenance over seven years, ending 2019.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.104 0.157s - 157pq - 2rq
Subscribe Now